Concept explainers
a)
To determine: Thejob sequence, flow time, utilization metric, average number of jobs, and average lateness for EDD, SPT, LPT, and FCFS.
Introduction:
a)

Answer to Problem 18P
The values in the given table have been computed.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
All the jobs are arrived on day 241.
Table to compute:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | |||||
SPT | |||||
LPT | |||||
FCFS |
Computed table:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
Supporting calculation:
Determine the sequence of the job using FCFS:
Processing time | Due date | Flow time | Completion time | Late | |
BR-02 | 15 | 300 | 15 | 265 | 0 |
CX-01 | 25 | 270 | 40 | 280 | 0 |
DE-06 | 35 | 320 | 75 | 315 | 0 |
RG-05 | 40 | 360 | 115 | 345 | 35 |
SY-11 | 30 | 310 | 145 | 385 | 25 |
Total | 390 | 60 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
First Come First Served (FCFS):
Completion day of CX-01:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 265.
Completion day of BR-02:
Start day of BR-02 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of BR-02. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of DE-06 is 315.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of SY-11 is 345.
Completion day of RG-05:
Start day of RG-05 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of RG-05 is 385.
Lateness of CX-01, BR-02, and DE-06:
Completion day of CX-01, BR-02, and DE-06 is less than its respective due date. Hence, there would be no lateness.
Lateness of SY-11:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 35.
Lateness of RG-05:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Determine the sequence of the job using SPT:
Processing time | Due date | Flow time | Completion time | Late | |
BR-02 | 15 | 300 | 15 | 255 | 0 |
CX-01 | 25 | 270 | 40 | 280 | 10 |
SY-11 | 30 | 310 | 70 | 310 | 0 |
DE-06 | 35 | 320 | 105 | 345 | 25 |
RG-05 | 40 | 360 | 145 | 385 | 25 |
Total | 375 | 60 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
Shortest Processing Time (SPT):
Completion day of BR-02:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 255.
Completion day of CX-01:
Start day of CX-01 is the next day of the completion day of BR-02. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 310.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 345.
Completion day of RG-05:
Start day of RG-05 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 385.
Lateness of BR-02 and SY-11:
Completion day of BR-02 and SY-11 is less than its respective due date. Hence, there would be no lateness.
Lateness of CX-01:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 10.
Lateness of DE-06:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Lateness of RG-05:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Determine the sequence of the job using LPT:
Processing time | Due date | Flow time | Completion time | Late | |
RG-05 | 40 | 360 | 40 | 280 | 0 |
DE-06 | 35 | 320 | 75 | 315 | 0 |
SY-11 | 30 | 310 | 105 | 345 | 35 |
CX-01 | 25 | 270 | 130 | 370 | 100 |
BR-02 | 15 | 300 | 145 | 385 | 85 |
Total | 495 | 220 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
Largest Processing Time (LPT):
Completion day of RG-05:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of RG-05. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 315.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 345.
Completion day of CX-01:
Start day of CX-01 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 370.
Completion day of BR-02:
Start day of BR-02 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 385.
Lateness of RG-05 and DE-06:
Completion day of RG-05 and DE-06 is less than its respective due date. Hence, there would be no lateness.
Lateness of SY-11:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 35.
Lateness of CX-01:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 100.
Lateness of BR-02:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 85.
Determine the sequence of the job using EDD:
Processing time | Due date | Flow time | Completion time | Late | |
CX-01 | 25 | 270 | 25 | 265 | 0 |
BR-02 | 15 | 300 | 40 | 280 | 0 |
SY-11 | 30 | 310 | 70 | 310 | 0 |
DE-06 | 35 | 320 | 105 | 345 | 25 |
RG-05 | 40 | 360 | 145 | 385 | 25 |
Total | 385 | 50 |
Working note:
Duration and due date for the jobs has been given. Flow time is the cumulative value of the duration. Jobs arrival rate is given as 241.
Earliest Due Date (EDD):
Completion day of CX-01:
Jobs arrival rate is given as 241. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 265.
Completion day of BR-02:
Start day of BR-02 is the next day of the completion day of CX-01. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day is 280.
Completion day of SY-11:
Start day of SY-11 is the next day of the completion day of DE-06. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of SY-11 is 310.
Completion day of DE-06:
Start day of DE-06 is the next day of the completion day of BR-02. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of DE-06 is 345.
Completion day of RG-05:
Start day of RG-05 is the next day of the completion day of SY-11. Completion day is calculated by adding the start day with the value attained by subtracting 1 from the duration. Hence, the completion day of RG-05 is 385.
Lateness of CX-01, BR-02, and SY-11:
Completion day of CX-01, BR-02, and SY-11 is less than its respective due date. Hence, there would be no lateness.
Lateness of DE-06:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Lateness of RG-05:
It is calculated by subtracting the completion day of the job from the due date of the project. Hence, the lateness is 25.
Summary:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
Working note:
Job sequence and flow time have been calculated in the above segments.
Earliest Due Date (EDD):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 10.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.66.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 38.6%.
Shortest Processing Time (SPT):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 12.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.59.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 38.6%.
Largest Processing Time (LPT):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 44.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 3.41.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 29.3%.
First Come First Served (FCFS):
Average lateness:
It is calculated by dividing the total lateness with the number of jobs. Hence, the average tardiness is 44.
Average number of jobs in the system:
It is calculated by dividing the total flow time with total duration of all the jobs. Hence, the average number of jobs in the system is 2.69.
Utilization rating:
It is calculated by dividing total processing time and total flow time. Hence, the utilization rating is 37.2%.
b)
To determine: The dispatching rule that has the best score in flow time.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
b)

Answer to Problem 18P
Shortest Processing Time has the best flow time.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in flow time:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, Shortest Processing Time (SPT) has the best score in flow time. It has less flow time when compare to EDD, LPT, and FCFS.
Hence, SPT has the best score in flow time.
c)
To determine: The dispatching rule that has the best score in utilization metric.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan on allocating human resources and machinery.
c)

Answer to Problem 18P
Shortest Processing Time has the best utilization metric.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in utilization metric:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, Shortest Processing Time (SPT) has the best score in utilization metric. It has maximum utilization metric when compare to EDD, LPT, and FCFS.
Hence, SPT has the best score in utilization metric.
d)
To determine: The dispatching rule that has the best score in average lateness.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan allocating human resources and machinery.
d)

Answer to Problem 18P
Earliest Due Date has the best utilization metric.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in average lateness:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, Earliest Due Date (EDD) has the best score in average lateness. It has less average lateness when compare to SPT, LPT, and FCFS.
Hence, EDD has the best score in average lateness.
e)
To determine: The dispatching rule that would be selected by Person X.
Introduction: Scheduling is the process of controlling and arranging the workloads of the production process using the optimized way. It is used to plan allocating human resources and machinery.
e)

Answer to Problem 18P
Person X would select Earliest Due Date.
Explanation of Solution
Given information:
The following information has been given:
Job | Date order received | Production days needed | Date order due |
BR-02 | 228 | 15 | 300 |
CX-01 | 225 | 25 | 270 |
DE-06 | 230 | 35 | 320 |
RG-05 | 235 | 40 | 360 |
SY-11 | 231 | 30 | 310 |
Best score in average lateness:
Dispatching rule | Job sequence | Flow time | Utilization rating | Average number of jobs | Average lateness |
EDD | CX-BR-SY-DE-RG | 385 | 37.60% | 2.66 | 10 |
SPT | BR-CX-SY-DE-RG | 375 | 38.60% | 2.59 | 12 |
LPT | RG-DE-SY-CX-BR | 495 | 29.30% | 3.41 | 44 |
FCFS | CX-BR-DE-SY-RG | 390 | 37.20% | 2.69 | 12 |
According to the above table, EDD has the less average lateness and other values are also having a slight difference when compared with SPT. Thus, EDD should be selected.
Hence, Person X would choose Earliest Due Date (EDD).
Want to see more full solutions like this?
Chapter 15 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- Currently a company that designs Web sites has five customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. The customers are ready to be scheduled today, which is the start of day 190. Time Since Order Arrived Customer (days ago) Processing Time (days) Due Date (days from now) A 3 24 58 B 2 32 100 с 10 20 26 D E 8 6 12 28 50 66 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the customers, the order is: Sequence Customer 1 2 3 4 5arrow_forwardThe Donald Fertilizer Company produces industrial chemical fertilizers. The projected manufacturing requirements (in gallons) for the next four quarters are 60,000, 90,000, 90,000, and 140,000 respectively. A level workforce is desired, relying only on anticipation inventory as a supply option. Stockouts and backorders are to be avoided, as are overtime and undertime. a. Determine the quarterly production rate required to meet total demand for the year, and minimize the anticipation inventory that would be left over at the end of the year. Beginning inventory is 0. The quarterly production rate is ☐ gallons. (Enter your response as an integer.)arrow_forwardHow would you design an operations plan and schedule for a new product/service? What factors would you consider and what challenges would you anticipate? Why are these factors and challenges relevant and how would you address them?arrow_forward
- You are the newly appointed CEO of TechSouth, a South African multinational technology company based in Cape Town. TechSouth specialises in manufacturing smartphones, laptops, and smart home devices. The company has a significant presence in the African market and has recently expanded into Europe and Asia. However, TechSouth is facing several critical challenges:· Declining Market Share - Over the past three years, TechSouth has lost considerable market share to both localcompetitors and international giants like Samsung and Apple. The company's products are perceived as outdated and lacking innovation.· Employee Engagement Issues - Recent employee surveys indicate low morale and engagement levels, particularly among the younger workforce, leading to high turnover rates. Many employees feel disconnected from the company's vision and mission.· Siloed Departments - The organizational structure at TechSouth is highly siloed, with departments operatingindependently rather than…arrow_forwardWhat is the best way to manage emotions and thoughts? How to work through Emotions and thoughts?arrow_forwardWhat are the emotions or stressful thoughts? What are the differences between them? How can we work through the emotions or stressful thoughts? How can we avoid or prevent emotions or stressful thoughts from happening or occurring? What are the obstacles?arrow_forward
- Main Challenges at TechInnovateStrategic DirectionTechInnovate's board of directors is pushing for a more aggressive expansion into emerging markets, particularly in Africaand Southeast Asia. However, there's internal disagreement about whether to focus on these new markets or consolidatetheir position in existing ones. Sarah Chen favors rapid expansion, while some senior executives advocate for a morecautious approach.Ethical ConcernsThe company's AI algorithms have come under scrutiny for potential biases, particularly in facial recognition technology.There are concerns that these biases disproportionately affect minority groups. Some employees have voiced ethicalconcerns about selling this technology to law enforcement agencies without addressing these issues.Team Leadership and DiversityTechInnovate's leadership team is predominantly male and Western, despite its global presence. There's growing pressurefrom employees and some board members to diversify the leadership team to…arrow_forwardSarah Anderson, the Marketing Manager at Exeter Township's Cultural Center, is conducting research on the attendance history for cultural events in the area over the past ten years. The following data has been collected on the number of attendees who registered for events at the cultural center. Year Number of Attendees 1 700 2 248 3 633 4 458 5 1410 6 1588 7 1629 8 1301 9 1455 10 1989 You have been hired as a consultant to assist in implementing a forecasting system that utilizes various forecasting techniques to predict attendance for Year 11. a) Calculate the Three-Period Simple Moving Average b) Calculate the Three-Period Weighted Moving Average (weights: 50%, 30%, and 20%; use 50% for the most recent period, 30% for the next most recent, and 20% for the oldest) c) Apply Exponential Smoothing with the smoothing constant alpha = 0.2. d) Perform a Simple Linear Regression analysis and provide the adjusted…arrow_forwardRuby-Star Incorporated is considering two different vendors for one of its top-selling products which has an average weekly demand of 70 units and is valued at $90 per unit. Inbound shipments from vendor 1 will average 390 units with an average lead time (including ordering delays and transit time) of 4 weeks. Inbound shipments from vendor 2 will average 490 units with an average lead time of 2 weeksweeks. Ruby-Star operates 52 weeks per year; it carries a 4-week supply of inventory as safety stock and no anticipation inventory. Part 2 a. The average aggregate inventory value of the product if Ruby-Star used vendor 1 exclusively is $enter your response here.arrow_forward
- Sam's Pet Hotel operates 50 weeks per year, 6 days per week, and uses a continuous review inventory system. It purchases kitty litter for $13.00 per bag. The following information is available about these bags: > Demand 75 bags/week > Order cost = $52.00/order > Annual holding cost = 20 percent of cost > Desired cycle-service level = 80 percent >Lead time = 5 weeks (30 working days) > Standard deviation of weekly demand = 15 bags > Current on-hand inventory is 320 bags, with no open orders or backorders. a. Suppose that the weekly demand forecast of 75 bags is incorrect and actual demand averages only 50 bags per week. How much higher will total costs be, owing to the distorted EOQ caused by this forecast error? The costs will be $higher owing to the error in EOQ. (Enter your response rounded to two decimal places.)arrow_forwardYellow Press, Inc., buys paper in 1,500-pound rolls for printing. Annual demand is 2,250 rolls. The cost per roll is $625, and the annual holding cost is 20 percent of the cost. Each order costs $75. a. How many rolls should Yellow Press order at a time? Yellow Press should order rolls at a time. (Enter your response rounded to the nearest whole number.)arrow_forwardPlease help with only the one I circled! I solved the others :)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage LearningFoundations of Business - Standalone book (MindTa...MarketingISBN:9781285193946Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning


