Question
Chapter 14, Problem 16P
To determine
The total overhaul cost using the given data.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
In a site balancing project, the total haul distance starts from Sta. 2+720 and ends in Sta.
4+450. The freehaul distance starts 430 m. away from the starting station of the total haul
distance and ends before the total haul distance which is also at a distance of 430 m.
a. Get the total haul distance
b. Locate the starting and end stations of the free haul distance
c. Get the overhaul distance.
d. Get the freehaul volume if it is estimated that the overhaul is approximately 5264
m3-m. .
e. Sketch the mass diagram based on the given.
Determine:
a) the overhaul volume
b) the volume of borrow
c) the volume of waste
*3 dec places all answer
The following cross-section notes of the road was examined to calculate volumes. The
width of the roadway is 12m
-12
-3
+6
-6
-6
+24
-9
STA 5+040
是 号 是
-15
-4.5
-6
-6
+6
-8
30
-12
-7
STA 5+140
Compute the volume between two stations using prismoidal method.
Chapter 14 Solutions
MindTap Engineering for Garber/Hoel's Traffic and Highway Engineering, 5th Edition, [Instant Access], 1 term (6 months)
Knowledge Booster
Similar questions
- Please explainarrow_forwardThe hourly passenger volume is expected to be 8,750. The transit center is being design with 6, 2.5 ft doors. What is the expected level of service of the doorways?arrow_forwardGiven the following transportation network with travel time in minutes: 3 2 2. 3 4 3 The trip production from TAZ 3 is 1,000. The trip attractions from TAZ 3 to all other zones are shown below: From/To 1 500 2 300 4 Trip Attraction 300 The minimum path from zone 3 to zone 1 is: Links 3-4, 4-1 5 min Links 3-2, 2-1 Link 3-1arrow_forward
- Do it anyways I will like your solutionarrow_forwardDetermine the breakeven travel time to the nearest 0.1 hours for the following conditions: Vehicle 1: Direct Haul Operating Cost = $69/hour; Vehicle Capacity = 6.47 tons Vehicle 2: Transfer Station Cost = $6.3/ton; Trailer Operating cost = $240/hour; Trailer Capacity = 30 tonsarrow_forwardPlease fastarrow_forward
- The following cross-section notes of the road was examined to calculate volumes. The width of the roadway is 12m -12 -3 -6 4 +6 -6 +24 -9 STA 5+040 +6 -15 -4.5 -6 -6 30 -12 -7 -8 STA 5+140 Compute the volume between two stations using end area method.arrow_forwardQUESTION 1 The hourly passenger volume is expected to be 8,750. The transit center is being design with 6, 2.5 ft doors. What is the expected level of service of the doorways? O A O O CO Ов OO Farrow_forwardDesign Hourly Volume (DHV) is the projected hourly volume that is used for design. This volume is taken as a percentage of choose one of the following the average annual traffic the average weekley traffic the average daily traffic none of the given choicesarrow_forward
- Current Year Future Yeare T[I] = 300e %3D T[II] =1000 %3D T[III] =800 %3D T[IV] = 300 %3D Distribute the trips for inter zonal movement based on Detroit Method.arrow_forwardUsing the following trip distribution matrix and road network: a) Identify the minimum path between each TAZ pair. b) Estimate the traffic flow on each linkarrow_forward(2d) To complement the new rail-project described in question 2a above, the city public-works department has also engaged your design-&-construct company to complete the work necessary for upgrading-repair to a small stretch of an existing city ring-road, to allow better access to an outlying train-station. You are assigned by the project manager of this road repair project, to lead a team of 5 workers. You are expected to finish all repair work within 15 days, and have been asked by your project manager what you will do to complete the project within the stipulated time. Discuss the measures required to achieve your manager's deadline, in terms of: your definition of quality in this project and what should be included in the quality management plan here; the procedures required for this project development process: what is to be included in your scope-of-works document, your leadership role as it relates to the company's quality policy towards the successful completion of the…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning