Concept explainers
A manager receives a
a. Assuming that monthly demand will be level during each of the six-month periods covered by the forecast (e.g., 100 per month for each of the first six months), determine an order size that will minimize the sum of ordering and carrying costs for each of the six-month periods. for each of the first six months), determine an order size that will minimize the sum of ordering and carrying costs for each of the six-month periods.
b. Why is it important to be able to assume that demand will be level during each six-month period?
c. If the vendor is willing to offer a discount of $10 per order for ordering in multiples of 50 units (e.g., 50, 100, 150), would you advise the manager to take advantage of the offer in either period? If so, what order size would you recommend?
a)
To determine: The order size that will minimize the sum of ordering and carrying cost.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 7P
Explanation of Solution
Given information:
Formula:
Calculation of order size:
- First half:
The order size for first six month period is calculated by dividing the product of 2 and 100 and 55 with 2 and taking square root which gives the resultant value as 74 units.
- Second half:
The order size for second six month period is calculated by dividing the product of 2 and 150 and 55 with 2 and taking square root which gives the resultant value as 91 units.
Hence, the order size that will minimize the sum of ordering and carrying cost is 74 units and 91 units.
b)
To determine: The importance of assuming that demand will be level during each six-month period.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 7P
Explanation of Solution
Given information:
Determine the importance of assuming that demand will be level during each six-month period:
Economic order quantity model is essential to determine the amount of order to be placed at the right time and with right quantity. In order to use the economic quantity model, the demand assumed must be constant and must not vary only then the model gives accurate result.
Hence, stable demand level is required to use the EOQ.
c)
To determine: The decision on accepting or rejecting the offer and provide recommendations on order size.
Introduction: Inventory is a stock or store of goods. Every company store lots of goods as inventory which will be used during replenishment periods. Management of inventory is so much essential to manage cost and also to reduce cost.
Answer to Problem 7P
Explanation of Solution
Given information:
Formula:
Determination on decisions to accept or reject the offer:
Calculation of total cost for first six-month period:
- Q=74 units
With discounts of $10, S=$55-10 = $45.
- Q=50
- Q=100
- Q=150
Recommendation:
From the above calculation it is evident that the offer can be accepted which proves to be cost savings at Q=50 units. So, it is advised to the manager to take advantage of the offer.
Calculation of total cost for second six-month period:
- Q=91 units
With discounts of $10, S=$55-10 = $45.
- Q=50
- Q=100
- Q=150
Recommendation:
From the above calculation it is evident that the offer can be accepted which proves to be cost savings at Q=100 units. So, it is advised to the manager to take advantage of the offer.
Hence, it is advised to the manager to take advantage of the offer.
Want to see more full solutions like this?
Chapter 13 Solutions
OPERATIONS MANAGEMENT(LL)-W/CONNECT
- Solve the following Question 1. How do volume and variety affect the process selection and layout types? Discuss 2. How is the human resource aspect important to operation function? Discuss 3. Discuss the supply network design and its impact on the overall performance of the organization.arrow_forwardHelp with question?arrow_forwardWhat are some good examples of bullet points on a resume for a Christian Elementary School?arrow_forward
- What is an example of a cover letter for a Christian School Long-Term Substitute Teaching position?arrow_forwardThe supply chain is a conventional notion, but organizations are only really interested in making products that they can sell to customers. Provided they have reliable supplies of materials and reasonable transport for finished products, logistics is irrelevant. Do you think this is true? If yes, explain, and if no, clearly explain as well.arrow_forwardworking as a program operations managerarrow_forward
- 12 X1, X230 1 x =0x2 write the Following linear Programming model by 1- general Form Canonical Forms Canonical formY 2- Standard Form Max Z=35X+ 4 X 2 +6 X3 ST. X+2X2-5x3 = 40 3X, + 6X2 + 7x 3 = 30 7x, +lox2 x3 = 50 X3 X 2 X 3 <0arrow_forwarda/ a Minimum cost assign each worker for one job at Jobs J1 12 33 WI 2 4 6 W2 5 W3 5 33 6 7arrow_forwardوبة واضافة هذه القيمة الى القيم Ex: Assign each job for each worker at minimum total Cost عمل لكل عامل وبأقل كلفة ممكنة obs الأعمال Workors العمال J1 J2 J3 J4 W₁ 15 13 14 12 W2 11 12 15 13 W3 13 12 10 11 W4 15 17 14 16arrow_forward
- The average completion time (flow time) for the sequence developed using the FCFS rule = 11.75 days (round your response to two decimal places). The percentage utilization for the sequence developed using the FCFS rule = 42.55 % (enter your response as a percentage rounded to two decimal places). b) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): An Alabama lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard's schedule. In what sequence would the jobs be ranked according to the decision rules on the left: Job Due Date A 212 B 209 C 208 D 210 Duration (days) 6 3 3 8 Sequence 1 Job B 2 3 4 A D The average tardiness (job lateness) for the sequence developed using the SPT rule = 5.00 days (round your response to two decimal places). The average completion time (flow time) for the sequence developed using the SPT rule = 10.25 days…arrow_forwardWith the aid of examples, fully discuss any five (5) political tactics used in organisations.arrow_forwarda. With the aid of examples, define discrimination. b. Fully discuss any four (4) types of discrimination in the workplacearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.