
Introduction:-
Capital Budgeting is used by organisations to evaluate a project in hand i.e. whether to proceed with it or leave it. There are various methods or techniques of capital budgeting. The most popular are
To determine:-
Here, in the given problem we are supposed to calculate NPV based on the inputs given like sales, cost of goods sold, equipment cost, investment in

Answer to Problem 1AE
Solution:-
Net Present Value is a Capital Budgeting technique which is used by management to decide as to whether proceed with a given project or not. It is calculated by discounting all the
When we solve the problem, the NPV of purchasing the equipment @14% is $31, 493 and NPV @10% is $56, 517 and as can be seen that NPV has increased when the discount rate is decreased.
Explanation of Solution
Explanation:-
Here, following key inputs given are as follows:-
Purchase of Equipment | 60000 |
Investment in working capital | 100000 |
Sales | 200000 |
Cost of goods sold | 125000 |
Out of pocket operating costs | 35000 |
Overhaul of equipment | 5000 |
Salvage value of equipment | 10000 |
Now, calculating NPV at 14% and 10% discount rate At 14 % discount rate
Years | ||||||
Now | 1 | 2 | 3 | 4 | 5 | |
Purchase of Equipment | -60000 | |||||
Investment in working capital | -100000 | |||||
Sales | 200000 | 200000 | 200000 | 200000 | 200000 | |
Cost of goods sold | 125000 | 125000 | 125000 | 125000 | 125000 | |
Out of pocket operating costs | 35000 | 35000 | 35000 | 35000 | 35000 | |
Overhaul of equipment | 5000 | |||||
Salvage value of equipment | 10000 | |||||
Working Capital Released | 100000 | |||||
Total |
-160000 | 40000 | 40000 | 40000 | 35000 | 150000 |
Discount factor @14% (b) | 1 | 0.87719 | 0.76947 | 0.67497 | 0.59208 | 0.51937 |
Present value of cash flows (a x b) | -160000 | 35087.7 | 30778.7 | 26998.9 | 20722.8 | 77905.3 |
Net Present Value | 31493.4 |
At 10% discount rate
Years | ||||||
Now | 1 | 2 | 3 | 4 | 5 | |
Purchase of Equipment | 60000 | |||||
Investment in working capital | 100000 | |||||
Sales | 200000 | 200000 | 200000 | 200000 | 200000 | |
Cost of goods sold | 125000 | 125000 | 125000 | 125000 | 125000 | |
Out of pocket operating costs | 35000 | 35000 | 35000 | 35000 | 35000 | |
Overhaul of equipment | 5000 | |||||
Salvage value of equipment | 10000 | |||||
Working Capital Released | 100000 | |||||
Total Cash flows (a) | -160000 | 40000 | 40000 | 40000 | 35000 | 150000 |
Discount factor @10% (b) | 1 | 0.90909 | 0.82645 | 0.75131 | 0.68301 | 0.62092 |
Present value of cash flows (a x b) | -160000 | 36363.6 | 33057.9 | 30052.6 | 23905.5 | 93138.2 |
Net Present Value | 56517.7 |
Now, we are asked to explain as to why the NPV has increased from $31493 to $56517 when the discount rate is reduced from 14% to 10%. Actually, with the decrease in the discount rate the Present Value factor increases and when we multiply that increased factor with the net cash flows, the resultant present value of the cash flows increases and ultimately the NPV figure.
Now, in the second query, the company is considering to purchase new equipment
Years | ||||||
Now | 1 | 2 | 3 | 4 | 5 | |
Purchase of Equipment | 120000 | |||||
Investment in working capital | 80000 | |||||
Sales | 255000 | 255000 | 255000 | 255000 | 255000 | |
Cost of goods sold | 160000 | 160000 | 160000 | 160000 | 160000 | |
Out of pocket operating costs | 50000 | 50000 | 50000 | 50000 | 50000 | |
Overhaul of equipment | 40000 | |||||
Salvage value of equipment | 20000 | |||||
Working Capital Released | 80000 | |||||
Total Cash flows (a) | -200000 | 45000 | 45000 | 45000 | 5000 | 145000 |
Discount factor @14% (b) | 1 | 0.87719 | 0.76947 | 0.67497 | 0.59208 | 0.51937 |
Present value of cash flows (a x b) | -200000 | 39473.7 | 34626 | 30373.7 | 2960.4 | 75308.5 |
Net Present Value @ 14% | -17258 |
Therefore, NPV of the project is - $17, 258 Now, we will calculate the NPV at various discount rates i.e.13%, 12%, 11% and 10% and determine on which discount rate NPV turns profitable from the negative figure.
Total Cash flows (a) | -200000 | 45000 | 45000 | 45000 | 5000 | 145000 |
Discount factor @13% (b) | 1 | 0.88496 | 0.78315 | 0.69305 | 0.61332 | 0.54276 |
Present value of cash flows (a x b) | -200000 | 39823 | 35241.6 | 31187.3 | 3066.59 | 78700.2 |
Net Present Value @ 13% | -11981 | |||||
Total Cash flows (a) | -200000 | 45000 | 45000 | 45000 | 5000 | 145000 |
Discount factor @12% (b) | 1 | 0.89286 | 0.79719 | 0.71178 | 0.63552 | 0.56743 |
Present value of cash flows (a x b) | -200000 | 40178.6 | 35873.7 | 32030.1 | 3177.59 | 82276.9 |
Net Present Value @ 12% | -6463.1 | |||||
Total Cash flows (a) | -200000 | 45000 | 45000 | 45000 | 5000 | 145000 |
Discount factor @11% (b) | 1 | 0.9009 | 0.81162 | 0.73119 | 0.65873 | 0.59345 |
Present value of cash flows (a x b) | -200000 | 40540.5 | 36523 | 32903.6 | 3293.65 | 86050.4 |
Net Present Value @ 11% | -688.74 | |||||
Total Cash flows (a) | -200000 | 45000 | 45000 | 45000 | 5000 | 145000 |
Discount factor @10% (b) | 1 | 0.90909 | 0.82645 | 0.75131 | 0.68301 | 0.62092 |
Present value of cash flows (a x b) | -200000 | 40909.1 | 37190.1 | 33809.2 | 3415.07 | 90033.6 |
Net Present Value @ 10% | 5357 |
As we can see that the NPV has turned positive from 14% discount rate to 10% discount rate.
Now, we are asked to determine the IRR of the project. As we can see above that NPV has turned positive at 10% discount rate, therefore the IRR of the project should lie between 10% and 11% discount rates i.e. at a place where NPV is zero. Actually, if calculated IRR is 10.88%. Now, we are asked to determine the salvage value of the equipment so that the NPV becomes positive, assuming that the amount given in the question is not given If we see in the initial table of discount rate of 14%, the NPV is -$17258 taking into account the salvage value of $20000 in the fifth year. Now, if we increase the salvage value, then only we will get the positive NPV.
Without taking into account the salvage value, then NPV is -$27645. Now dividing it by the PVIF @ 14% which is .51937, we will get the minimum salvage value of the equipment to turn NPV into positive figure.
=27645÷.51937
=$53,229
Therefore, the minimum salvage value should be $53229 to turn NPV into positive figure.
Conclusion:-
Since, the resultant net present value is positive in problem 1, therefore it is viable to proceed with the given project.
However, NPV is negative in project 2, therefore it is not viable to purchase the equipment.
Want to see more full solutions like this?
Chapter 13 Solutions
Managerial Accounting
- Please don't use AI And give correct answer .arrow_forwardLouisa Pharmaceutical Company is a maker of drugs for high blood pressure and uses a process costing system. The following information pertains to the final department of Goodheart's blockbuster drug called Mintia. Beginning work-in-process (40% completed) 1,025 units Transferred-in 4,900 units Normal spoilage 445 units Abnormal spoilage 245 units Good units transferred out 4,500 units Ending work-in-process (1/3 completed) 735 units Conversion costs in beginning inventory $ 3,250 Current conversion costs $ 7,800 Louisa calculates separate costs of spoilage by computing both normal and abnormal spoiled units. Normal spoilage costs are reallocated to good units and abnormal spoilage costs are charged as a loss. The units of Mintia that are spoiled are the result of defects not discovered before inspection of finished units. Materials are added at the beginning of the process. Using the weighted-average method, answer the following question: What are the…arrow_forwardQuick answerarrow_forward
- Financial accounting questionarrow_forwardOn November 30, Sullivan Enterprises had Accounts Receivable of $145,600. During the month of December, the company received total payments of $175,000 from credit customers. The Accounts Receivable on December 31 was $98,200. What was the number of credit sales during December?arrow_forwardPaterson Manufacturing uses both standards and budgets. For the year, estimated production of Product Z is 620,000 units. The total estimated cost for materials and labor are $1,512,000 and $1,984,000, respectively. Compute the estimates for: (a) a standard cost per unit (b) a budgeted cost for total production (Round standard costs to 2 decimal places, e.g., $1.25.)arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education





