Concept explainers
Concept Introduction:
Activity Based Costing (ABC):
ABC costing method is generally used to allocate the
Predetermined Overhead allocation rate:
The Predetermined Overhead allocation rate is used to allocate the manufacturing overhead over the jobs. Predetermined Overhead allocation rate is calculated by dividing the Total Estimated overhead cost by the Total Estimated allocation base.
The formula to calculate the Predetermined Overhead allocation rate is as follows:
Requirement-a:
To Calculate:
The Total

Answer to Problem 13.22P
The Total Manufacturing cost and Cost per unit produced during the month using the Activity Based Costing are as follows:
Total Manufacturing cost | $ 679,040 |
Cost per unit | $ 212.20 |
Explanation of Solution
The Total Manufacturing cost and Cost per unit produced during the month using the Activity Based Costing are calculated as follows:
Direct Material Cost | $ 107,200 |
Direct Labor Cost (13120 hours *$15) | $ 196,800 |
Overhead Costs: | |
Materials handling (70400 parts * $0.20) | $ 14,080 |
Cutting and leather work (70400 parts * $1.40) | $ 98,560 |
Assembly and inspection (13120 hours *$20) | $ 262,400 |
Total Manufacturing cost | $ 679,040 |
Cost per unit ($679040/3200 Units) | $ 212.20 |
Concept Introduction:
Activity Based Costing (ABC):
ABC costing method is generally used to allocate the overhead costs to the product using activity rates differently for each activity. Unlike traditional method, the ABC costing method does not use the plant wide overhead rate, rather it used different allocation rate for different production activity.
Predetermined Overhead allocation rate:
The Predetermined Overhead allocation rate is used to allocate the manufacturing overhead over the jobs. Predetermined Overhead allocation rate is calculated by dividing the Total Estimated overhead cost by the Total Estimated allocation base.
The formula to calculate the Predetermined Overhead allocation rate is as follows:
Requirement-b:
To Calculate:
The Total Manufacturing cost and Cost per unit produced during the month using the predetermined overhead allocation rate

Answer to Problem 13.22P
The Total Manufacturing cost and Cost per unit produced during the month using the predetermined overhead allocation rate are as follows:
Total Manufacturing cost | $ 697,600 |
Cost per unit | $ 218.00 |
Explanation of Solution
The Total Manufacturing cost and Cost per unit produced during the month using the predetermined overhead allocation rate are calculated as follows:
Direct Material Cost | $ 107,200 |
Direct Labor Cost (13120 hours *$15) | $ 196,800 |
Overhead Costs (13120 hours *$30) | $ 393,600 |
Total Manufacturing cost | $ 697,600 |
Cost per unit ($679040/3200 Units) | $ 218.00 |
Note: Calculation of Predetermined Overhead allocation Rate: | |
Total Overhead Costs (250000+1750000+4000000) (A) | $ 6,000,000 |
Total Direct Labor hours (B) | 200,000 |
Predetermined Overhead allocation Rate = A/B = | $ 30 |
Concept Introduction:
Activity Based Costing (ABC):
ABC costing method is generally used to allocate the overhead costs to the product using activity rates differently for each activity. Unlike traditional method, the ABC costing method does not use the plant wide overhead rate, rather it used different allocation rate for different production activity.
Predetermined Overhead allocation rate:
The Predetermined Overhead allocation rate is used to allocate the manufacturing overhead over the jobs. Predetermined Overhead allocation rate is calculated by dividing the Total Estimated overhead cost by the Total Estimated allocation base.
The formula to calculate the Predetermined Overhead allocation rate is as follows:
Requirement-c:
To Compare:
The Total Manufacturing cost and Cost per unit produced during the month calculated using the activity based and costing and using the predetermined overhead allocation rate

Answer to Problem 13.22P
ABC costing method does not use the plant wide overhead rate, rather it uses different allocation rate for different production activity, which results in fair calculation of the cost per unit of the product.
Explanation of Solution
The Total Manufacturing cost and Cost per unit produced during the month using the Activity Based Costing are as follows:
Total Manufacturing cost | $ 679,040 |
Cost per unit | $ 212.20 |
The Total Manufacturing cost and Cost per unit produced during the month using the predetermined overhead allocation rate are as follows:
Total Manufacturing cost | $ 697,600 |
Cost per unit | $ 218.00 |
The Predetermined Overhead allocation rate is used to allocate the manufacturing overhead over the jobs. Predetermined Overhead allocation rate is calculated by dividing the Total Estimated overhead cost by the Total Estimated allocation base.
ABC costing method is generally used to allocate the overhead costs to the product using activity rates differently for each activity. Unlike traditional method, the ABC costing method does not use the plant wide overhead rate, rather it used different allocation rate for different production activity.
Hence, ABC costing method does not use the plant wide overhead rate, rather it uses different allocation rate for different production activity, which results in fair calculation of the cost per unit of the product.
Want to see more full solutions like this?
Chapter 13 Solutions
Principles of Financial Accounting (Elon University)
- Ansarrow_forwardA $2,000 bond issued in 2018 pays $180 in interest each year. What is the current yield on the bond if it can be purchased for $1,500?arrow_forwardVelocity Industries acquired a machine for $310,000, with a salvage value of $25,000 and a useful life of 8 years. The total expected production capacity is 450,000 units. The machine produced 45,000 units in year 1 and 38,000 units in year 2. Using the units of activity method, determine the depreciation expense for year 2.arrow_forward
- ??arrow_forwardA company has a total cost of $50.00 per unit at a volume of 100,000 units. The variable cost per unit is $20.00. What would the price be if the company expected a volume of 120,000 units and used a markup of 50%?arrow_forwardPlease provide correct answer this financial accounting question not use chatgpt please don'tarrow_forward
- A business has $210,000total liabilities. At start-up, the owners invested $500,000 in the business. Unfortunately, the business has suffered a cumulative loss of $200,000 up to the present time. What is the amount of its total assets at the present time?arrow_forwardNet change in working capital isarrow_forwardWhen a company receives cash in advance from a customer for services to be provided in the future, which account is credited?a) Accounts Receivableb) Cashc) Unearned Revenued) Revenuearrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education