a)
To determine: The initial cash flow of the project at Time 0
Introduction:
Project evaluation refers to the process of evaluating the project for its feasibility and economic viability.
a)
Answer to Problem 25QP
The initial cash flow at Time 0 is $20,825,000.
Explanation of Solution
Given information:
Company D manufactures radar detection systems. It is planning to open a new manufacturing plant overseas. The project will take five years. It had purchased a land overseas at $4,500,000 for dumping chemical waste. However, the company found an alternative to dispose of waste and the land remained unused.
The current after-tax valuation of the land is $5,000,000. It would be worth $5,300,000 in five years. The company wants to implement the project on this unused land. The cost of plant and equipment would be $15,000,000. The current market data for Company D is as follows:
- Debt: Company D has bonds with a face value of $1,000 and a coupon rate of 6.2 percent. There are 40,000 outstanding bonds. The bonds will mature in 25 years, and they make semiannual coupon payments. The bond currently sells at 95 percent of the face value.
- Common equity: The common equity of Company D has 825,000 shares outstanding. The current selling price of the share is $97. The stock has a beta of 1.15. The risk-free rate is 3.8 percent, and the market risk premium is 7 percent.
- Preferred stock: Company D has 45,000 outstanding
preferred shares . The dividend is 5.8 percent, and the current market value is $95 per share. Assume that the face value of the share is $100.
The tax rate applicable to Company D is 34 percent. The project needs an initial net working capital of $825,000 to begin the operations.
Explanation:
Compute the initial
The initial cash flow includes the cost of the land, plant, and equipment, and the initial net working capital. The land currently values at $5,000,000. The cost of buying plant and equipment is $15,000,000. The initial working capital required is $825,000. Hence, the initial cash outflow at Time 0 is $20,825,000
b)
To determine: The discount rate
Introduction:
Project evaluation refers to the process of evaluating the project for its feasibility and economic viability.
b)
Answer to Problem 25QP
The discount rate is 11.31 percent.
Explanation of Solution
The company can use the weighted average cost of capital as its discount rate if the new project’s risk is similar to the company’s risk. It is given that the project is riskier than the firm is. The company adds 2 percent to its weighted average cost of capital to match the riskiness of the project. Therefore, the discount rate for the project would we equal to the sum of the weighted average cost of capital and the adjustment factor of 2 percent.
The formula to calculate the market value of debt:
The formula to calculate the market value of equity:
The formula to calculate the market value of preferred stock:
The formula to calculate the total market value of the capital structure:
The formula to calculate the
“RE” refers to the expected
“Rf” refers to the risk-free rate
“RM” refers to the expected return on the market portfolio
“βE” refers to the beta or risk of the equity
The formula to calculate the cost of preferred stock:
Where,
“RP” refers to the return on preferred stock or cost of preferred stock
“D” refers to the dividend earned on the preferred stock
“P0” refers to the current price of preference stock
The formula to calculate annual coupon payment:
The formula to calculate the current price or the market value of the debt:
The formula to calculate the yield to maturity:
Where,
“C” refers to the coupon paid per period
“F” refers to the face value paid at maturity
“r” refers to the yield to maturity
“t” refers to the periods to maturity
The formula to calculate the after-tax cost of debt:
Where,
“RD” refers to the cost of debt
“TC” refers to the corporate tax rate
The formula to calculate the weighted average cost of capital:
Where,
“WACC” refers to the weighted average cost of capital
“RE” refers to the return on equity or cost of equity
“RD” refers to the return on debt or cost of debt
“RP” refers to the return on debt or cost of preferred stock
“E” refers to the amount of common equity capital
“D” refers to the amount of debt
“P” refers to the amount of preferred stock
“V” refers to the total amount of capital
“TC” refers to the corporate tax rate
Compute the market value of debt:
Hence, the market value of debt is $38,000,000.
Compute the market value of equity:
Hence, the market value of common equity is $80,025,000.
Compute the market value of preferred stock:
Hence, the market value of preferred stock is $4,275,000.
Compute the total market value of the capital structure:
Hence, the total market value of the capital structure is $122,300,000.
Compute the cost of equity:
Hence, the cost of equity is 11.85 percent.
Compute the cost of preferred stock:
The face value of the preferred stock is $100. The dividend percent is 5.8. Hence, the dividend is $5.8
Hence, the cost of preferred stock is 6.11 percent.
Compute the annual coupon payment:
Hence, the annual coupon payment is $62.
Compute the current price of the bond:
The face value of the bond is $1,000. The
Hence, the current price of the bond is $950.
Compute the semiannual yield to maturity of the bond as follows:
The bond pays the coupons semiannually. The annual coupon payment is $62. However, the bondholder will receive the same is two equal installments. Hence, semiannual coupon payment or the 6-month coupon payment is $31
The time to maturity is 25 years. As the coupon payment is semiannual, the semiannual periods to maturity are 50
Finding “r” in Equation (1) would give the semiannual yield to maturity. However, it is difficult to simplify the above the equation. Hence, the only method to solve for “r” is the trial and error method.
The first step in trial and error method is to identify the discount rate that needs to be used. The bond sells at a premium in the market if the market rates (Yield to maturity) are lower than the coupon rate. Similarly, the bond sells at a discount if the market rate (Yield to maturity) is greater than the coupon rate.
In the given information, the bond sells at a discount because the market value of the bond is lower than its face value. Hence, substitute “r” with a rate that is higher than the coupon rate until one obtains the bond value close to $950.
The coupon rate of 6.2 percent is an annual rate. The semiannual coupon rate is 3.1 percent
The attempt under the trial and error method using 3.306 percent as “r”:
The current price of the bond is $949.94 when “r” is 3.306 percent. Hence, 3.306 percent is the semiannual yield to maturity.
Compute the annual yield to maturity:
Hence, the yield to maturity is 6.61 percent.
Compute the after-tax cost of debt:
The pre-tax cost of debt is equal to the yield to maturity of the bond. The yield to maturity of the bond is 6.61 percent. The corporate tax rate is 34 percent.
Hence, the after-tax cost of debt is 4.36 percent.
Compute the weighted average cost of capital:
The market value of equity (E) is $80,025,000, the market value of preferred stock (P) is $4,275,000, and the market value of debt (D) is $38,000,000. The total market value (V) is $122,300,000. The cost of equity “RE” is 11.31 percent, the cost of preferred stock “RP” is 6.11 percent, and the after-tax cost of debt “RD” is 4.36 percent. As the after-tax cost of debt is available, omit “1‑TC” from the formula.
Hence, the weighted average cost of capital is 9.31 percent.
Compute the discount rate:
The company adds 2 percent to its weighted average cost of capital to match the riskiness of the project. The weighted average cost of capital is 6.45 percent. Hence, the discount rate is 11.31 percent
c)
To determine: The after-tax salvage value after 5 years
Introduction:
Project evaluation refers to the process of evaluating the project for its feasibility and economic viability.
c)
Answer to Problem 25QP
The after-tax salvage value after 5 years is $3,298,500.
Explanation of Solution
The formula to calculate the
The formula to calculate the book value after 5 years:
The formula to calculate the after-tax salvage value:
Compute the depreciation per year:
The cost of the equipment is $15,000,000, and its tax life is 8 years (Given).
Hence, the depreciation per year is $1,875,000.
Compute the book value after 5 years:
Hence, the book value after five years is $5,625,000.
Compute the after-tax salvage value:
It is given that the market value of the equipment after 5 years is $2,100,000. The book value after 5 years is $5,625,000. The tax rate is 34 percent.
Hence, the after-tax salvage value is $3,298,500.
d)
To determine: The operating cash flow of the project
Introduction:
Project evaluation refers to the process of evaluating the project for its feasibility and economic viability.
d)
Answer to Problem 25QP
The operating cash flow of the project every year is $5,455,500.
Explanation of Solution
Given information:
The new project has annual fixed costs worth $3,500,000. The new plant will manufacture 12,000 products. The selling price of each product is $10,800, and the cost of production is $9,900.
The formula to calculate the operating cash flow:
Compute the operating cash flow:
The selling price of each product is $10,800, and the cost of production is $9,900. The depreciation per year is $1,875,000. The fixed costs are $3,500,000. The tax rate is 34 percent.
Hence, the operating cash flow is $5,455,500.
e)
To determine: The
Introduction:
Project evaluation refers to the process of evaluating the project for its feasibility and economic viability.
e)
Answer to Problem 25QP
The net present value is $4,696,660.43, and the internal rate of return is 18.6401270 percent.
Explanation of Solution
Net present value is a tool that helps in evaluating a new project. It determines whether the present value of cash flows from the project exceed the initial cost of investment. The internal rate of return in a return where the net present value of the project is zero.
The formula to calculate the net present value and the internal rate of return:
Where,
“CF1 to CFt” refer to the cash flow from period 1 to period t
“r” refers to the discount rate
Compute the net present value:
The initial investment in the project is $20,825,000. The operating cash flow of the project is $5,455,500. Hence, it is the cash flow from Year 1 to Year 4. For Year 5, the cash flow should include the operating cash flow plus the after-tax salvage value, after-tax land value, and the recovery of the initially invested working capital.
The after-tax salvage value is $3,298,500 the after-tax land value is $5,300,000, and the initial working capital is $825,000. Hence, the cash flow in Year 5 is $14,879,000
Hence, the net present value is $4,696,660.43.
Compute the internal rate of return:
The internal rate of return in a return where the net present value of the project is zero. It is possible to determine the internal rate of return only through the trail and error method or by using a software. The net present value is positive. Hence, the trial and error rate should be higher than the discount rate. Use a trial rate of 18.6401270 percent to determine whether the net present value is zero.
Hence, the approximate internal rate of return is 18.6401270 percent.
Want to see more full solutions like this?
Chapter 12 Solutions
Essentials of Corporate Finance
- Consider a situation involving determining right and wrong. Do you believe utilitarianism provides a more objective viewpoint than moral rights in this context? Why or why not? How about when comparing utilitarianism to principles of justice? Share your thoughts. Reflect on this statement: "Every principle of distributive justice, whether that of the egalitarian, the capitalist, the socialist, the libertarian, or Rawls, in the end is illegitimately advocating some type of equality." Do you agree or disagree with this assertion? Why might someone claim this, and how would you respond?arrow_forwardI need help checking my spreadsheet. Q: Assume that Temp Force’s dividend is expected to experience supernormal growth of 73%from Year 0 to Year 1, 47% from Year 1 to Year 2, 32% from Year 2 to Year 3 and 21% from year3 to year 4. After Year 4, dividends will grow at a constant rate of 2.75%. What is the stock’sintrinsic value under these conditions? What are the expected dividend yield and capital gainsyield during the first year? What are the expected dividend yield and capital gains yield duringthe fifth year (from Year 4 to Year 5)?arrow_forwardwhat are the five components of case study design? Please help explain with examplesarrow_forward
- Commissions are usually charged when a right is exercised. a warrant is exercised. a right is sold. all of the above will have commissions A and B are correct, C is not correctarrow_forwardWhat is Exploratory Research Case Study? What is the main purpose of Exploratory Research?arrow_forwardplease help with how to solve this thank you.arrow_forward
- Question 25 Jasmine bought a house for $225 000. She already knows that for the first $200 000, the land transfer tax will cost $1650. Calculate the total land transfer tax. (2 marks) Land Transfer Tax Table Value of Property Rate On the first $30 000 0% On the next $60 000 0.5% (i.e., $30 001 to $90 000) On the next $60 000 1.0% (i.e., $90 001 to $150 000) On the next $50 000 1.5% (i.e., $150 001 to $200 000) On amounts in excess of $200 000 2.0% 22 5000–200 000. 10 825000 2.5000.00 2 x 25000 =8500 2 maarrow_forwardQuestion 25 Jasmine bought a house for $225 000. She already knows that for the first $200 000, the land transfer tax will cost $1650. Calculate the total land transfer tax. (2 marks) Land Transfer Tax Table Value of Property Rate On the first $30 000 0% On the next $60 000 0.5% (i.e., $30 001 to $90 000) On the next $60 000 1.0% (i.e., $90 001 to $150 000) On the next $50 000 1.5% (i.e., $150 001 to $200 000) On amounts in excess of $200 000 2.0% 225000–200 000 = 825000 25000.002 × 25000 1= 8500 16 50+ 500 2 marksarrow_forwardSuppose you deposit $1,000 today (t = 0) in a bank account that pays an interest rate of 7% per year. If you keep the account for 5 years before you withdraw all the money, how much will you be able to withdraw after 5 years? Calculate using formula. Calculate using year-by-year approach. Find the present value of a security that will pay $2,500 in 4 years. The opportunity cost (interest rate that you could earn from alternative investments) is 5%. Calculate using the formula. Calculate using year-by-year discounting approach. Solve for the unknown in each of the following: Present value Years Interest rate Future value $50,000 12 ? $152,184 $21,400 30 ? $575,000 $16,500 ? 14% $238,830 $21,400 ? 9% $213,000 Suppose you enter into a monthly deposit scheme with Chase, where you have your salary account. The bank will deduct $25 from your salary account every month and the first payment (deduction) will be made…arrow_forward
- Essentials Of InvestmentsFinanceISBN:9781260013924Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.Publisher:Mcgraw-hill Education,
- Foundations Of FinanceFinanceISBN:9780134897264Author:KEOWN, Arthur J., Martin, John D., PETTY, J. WilliamPublisher:Pearson,Fundamentals of Financial Management (MindTap Cou...FinanceISBN:9781337395250Author:Eugene F. Brigham, Joel F. HoustonPublisher:Cengage LearningCorporate Finance (The Mcgraw-hill/Irwin Series i...FinanceISBN:9780077861759Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan ProfessorPublisher:McGraw-Hill Education