Question
Chapter 12, Problem 25P
(a):
To determine
Make the decision.
(b):
To determine
Expected value of perfect information.
(c):
To determine
Decision tree.
(d):
To determine
Expected value of perfect information after survey.
(e):
To determine
Expected value survey information.
(f):
To determine
Optimal decision.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The research department at a manufacturing company has developed a new process that it believes will result in an improved product Management must decide whether to go
ahead and market the new product. The new product may or may not be better than the old one. If the new product is better and the company decides to market it, sales should
increase by $50,000. If it is not better and they replace the old product with the new product on the market, they will lose $24,000 to competitors. If they decide not to market the
new product, they will lose a total of $30,000 if it is better and just research costs of $10,000 if it is not. Answer parts a through c below.
(a) Prepare a payoff matrix.
(Type an integer or decimal for each matrix element. Do not include the $ symbol in your answer.)
(b) If management believes there is a probability of 0.4 that the new product is better, find the expected profits under each strategy and determine the best action. Select the
correct answer below and fill…
A retailer of a perishable item that has a life of 3 months
is in a dilemma. The forecast for the three months (which
is a function of the price charged) is expected to be 2500
- pl, 2500 -1.2 p2 and 2500 1.55 p3 respectively. If the
purchase price of the item is Rs 200 and if the retailer
wants to charge the same price in each of the three
months, what price ( optimal ) should he charge, how
much should he order and what is the expected profit?
Excel output to be provided.
If he were to follow dynamic pricing, how can you get
the prices to be charged in the
three months? Do you foresee any advantage in
following this?
The business manager decides to access the latest macroeconomic predictions from the Bank of England. This provides him with the following probabilities: Recession (15%), Low Growth (30%), Medium Growth (35%), and High Growth (20%). Which option is preferred according to the expected monetary value (EMV) criterion? What attitude to risk does this represent?
Chapter 12 Solutions
Contemporary Engineering Economics (6th Edition)
Ch. 12 - Prob. 1PCh. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Prob. 4PCh. 12 - Prob. 5PCh. 12 - Prob. 7PCh. 12 - Prob. 8PCh. 12 - Prob. 9PCh. 12 - Prob. 10PCh. 12 - Prob. 11P
Ch. 12 - Prob. 12PCh. 12 - Prob. 13PCh. 12 - Prob. 14PCh. 12 - Prob. 15PCh. 12 - Prob. 16PCh. 12 - Prob. 17PCh. 12 - Prob. 18PCh. 12 - Prob. 19PCh. 12 - Prob. 20PCh. 12 - Prob. 21PCh. 12 - Prob. 22PCh. 12 - Prob. 23PCh. 12 - Prob. 24PCh. 12 - Prob. 25PCh. 12 - Prob. 26PCh. 12 - Prob. 27PCh. 12 - Prob. 28P
Knowledge Booster
Similar questions
- There are two types of projects in the market: A (safer) and B (riskier). At time 1, the payoff of A will be either $500 (probability 0.75) or $300 (probability 0.25). The appropriate discount rate for project A is 12%. The minimum price A can accept is $350. The payoff of B will be either $800 (probability 0.2) or $100 (probability 0.8). The appropriate discount rate for project B is 20%. In this simple economy, there are 90% chance that the project will be A. Evaluate the funding situation, i.e., which type of project will be funded and the price, based on the following scenarios: If an honest information service firm exists in the market that can separate A from B and provide credible certification. What is the maximum price that the agent can charge for the service? If a bank exists and can provide partial financing and tell the difference between A & B but cannot verify the outcomes, what will be the maximum face values of loans to each project?arrow_forwardThere are two types of projects in the market: A (safer) and B (riskier). At time 1, the payoff of A will be either $500 (probability 0.75) or $300 (probability 0.25). The appropriate discount rate for project A is 12%. The minimum price A can accept is $350. The payoff of B will be either $800 (probability 0.2) or $100 (probability 0.8). The appropriate discount rate for project B is 20%. In this simple economy, there are 90% chance that the project will be A. Evaluate the funding situation, i.e., which type of project will be funded and the price, based on the following scenarios: When there is no information asymmetry and everyone knows everything. When there is information asymmetry and investors cannot tell if the project is A or B.arrow_forwarda manager is trying to decide whether to buy one machine or two. If only one is purchased and demand proves to be excessive, the second machine can be purchased later. some sales will be lost, however, because the lead time will be lower if both are purchased at the same time. the probability of low demand is estimated to be 0.20. the after- tax net present value of the benefits from purchasing the two machines together is $90,000 if demand is low and $180,000 if demand is high. if one machine is purchased and demand is low, the net present value is $120,000. if demand is high, the manager has 3 options. doing nothing has a net present value of $120,000, subcontracting $160,000, and buying the second machine, $140,000. a. draw a decision tree for this probelm b how many machines should the company buy initially? what is the expected payoff for this alternative?arrow_forward
- Prospect A and Prospect B have the same expected value (-500), but different outcome probabilities: Prospect A P(0.80, -625; 0.20, O) Prospect B P(0.20, -2500; 0.80, 0) Under prospect theory, which prospect preferred?arrow_forwardA company is considering launching a new product on the market and needs help assessing its profit potential. The fixed cost to launch this new product is $250,000. The variable (per unit) cost for the product is expected to be between $100 and $260. The product will sell for $350 per unit. Demand estimates vary widely, ranging from 0 to 25,000 units. Compute profit for the base-case scenario using the average of the uncertain parameters. Compute profit for the worst-case scenario. Compute profit for the best-case scenario.arrow_forwardJoosey Technologies have developed a new manufacturing process which they believe will revolutionize the smartphone industry. They are, however, uncertain how they should go about exploiting this advance. Initial indications of the likely success of marketing the process are 55%, 30%, 15% for "high success", "medium success" and "probable failure", respectively. The company has three options; they can go ahead and develop the technology themselves, license it or sell the rights to it. The financial outcomes (in R millions) for each option are presented in Table 3. Table 3: Financial outcomes (in R millions) Probable failure -100 0 25 Develop License Sell High success 80 40 25 Medium success 40 30 25 a) Draw a decision tree to represent the company's problem. b) Calculate the Expected Monetary Value (EMV) for all possible decisions the company may take and hence determine the optimal decision for the company.arrow_forward
- Researchers conducted a survey to determine the quality weight of a particular disease. Respondents of the survey claimed they were indifferent between living 6 years without the disease and living 10 years with the disease. (1) What is the implied quality weight q for a year with the disease? Assume a patient with such a disease can only live for 10 years. Now a drug has been developed to treat this disease. With the drug, the quality of life can be improved to 0.7 and patients can live for 12 years. (2) Calculate the QALYS gained due to the treatment (relative to no treatment). Assume no discounting of future years. (3) If the drug costs $24,000, what is the incremental cost-effectiveness ratio of the treatment compared with no treatment? (4) Assume it is agreed that a QALY is worth $5000. Will this patient decide to get the drug? (5) If the patient has an insurance which pays (with 10% coinsurance) for the drug. Will the patient decide to get the drug?arrow_forwardA manager must decide whether to lease a small or large machine for one year. The small machine will cost them £10,000; the large machine £30,000. The small machine can produce up to 500 units a month;the large machine 3000 units. If they find a distributor (an event which they believe has a probability p) then there will be a market for 2200 units per month over the year; otherwise just 400 units. Whichever machine they lease, they will manufacture precisely the number of units which they sell. The profit per unit sold is £5. For what values of p, rounded to 2 decimal places, is the optimal EMV solution to lease the small machine?arrow_forwardYou are taking a multiple-choice test that awards you one point for a correct answer and penalizes you 0.25 points for an incorrect answer. If you have to make a random guess and there are five possible answers, what is the expected value of guessing? Group of answer choices -0.25. 0.25. 0.5. 1. 0.arrow_forward
- Researcher wants to test the efficacy of drug “X” in children. This drug has not previously tested in animals or any in vivo or in vitro studies. What decision will IRB take in respect to this proposed study? Approve Reject Yes Noarrow_forwardThe Polytechnic campus bookstore sells diploma frames stamped with Sparky. The frames must be purchased in bundles of one dozen (12) each. Each frame in the bundle costs $65 and will sell for $90. Frames unsold by end of Spring semester will be clearance priced at $20. The bookstore estimates that demand patterns will follow the table below. Demand level Probability DO NOT BUILD the entire payoff table. Compute the expected monetary value for purchasing two bundles. 1 bundle 0.10 2 bundles 0.30 3 bundles 0.60arrow_forwardOp2.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial Economics: Applications, Strategies an...EconomicsISBN:9781305506381Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. HarrisPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage Learning
Managerial Economics: Applications, Strategies an...
Economics
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning