
Concept explainers
Determine material requirements plans for pans N and V and subassembly I as described in Solved Problem 3 for each of the following:
a. Assume that there are currently 100 Ns on hand and scheduled receipts of 40 Is and 10 Vs at the beginning of week 3. No Es are on hand: 120 Es are needed at the start of week 5.
b. Assume on-hand and scheduled receipts as in part a. Now suppose that 100 Es are needed at the stmt of week 5 and 55 at the start of week 7. Also, use multiples of these order sizes: N, 800; V, 200. Use lot-for-lot ordering for I.
C. Using your answer to part b, update the MRP for V, using the following additional information for each of these cases: (1) one week has elapsed (making it the start of week 2), and (2) three weeks have elapsed (making it the start of week 4).
The updated master
a)

To prepare A Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which is used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 40 units of Component I and 10 units of Component C would arrive at the beginning of Week 3. 120 units of Component E are needed at the beginning of Week 5.
Product structure tree:
Prepare master schedule:
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Quantity | 120 |
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 120 units of End item E, which must be shipped at the start of week 5.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 120 units (120-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 120 units in the beginning of week 5. Hence, they need to order for 120 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 200 units on week 4 (240-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 200 units in the beginning of week 4. Hence, they need to order for 200 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 700 units on week 3 (800-100).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 10 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 190 units on week 3 (200-10).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 0 units. Calculation is as follows:
b)

To prepare A Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 40 units of Component I and 10 units of Component C would arrive at the beginning of week 3. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in the start of week 5 and 55 units of End item E in the start of week 7.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units in week 5 (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of Week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units on week 4 (200-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 160 units in the beginning of week 4. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 540 units on week 3 (640-100).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 540 units in the beginning of week 3. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 260 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 10 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 150 units on week 3 (160-10).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 150 units in the beginning of week 3. Hence, they need to order for 200 units (as the lot size is multiples of 200) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 50 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
c)
1)

To prepare: Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 800 units of Component N and 200 units of Component V would arrive at the beginning of week 3. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Week 1 has elapsed. Hence, plan has to be prepared from week 2 through week 9. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. In addition to that, 100 units of End item E are needed in week 9.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in week 5, 55 units in week 7, and 100 units in week 9.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units on week 4 (200-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 160 units in the beginning of week 4. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Scheduled receipt is 800 units at the beginning of week 3
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units on week 5 (440-260).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 180 units in the beginning of week 5. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 4 is 260 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 210 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 60 units on week 5 (110-50).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 50 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
1)

To prepare: Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 800 units of Component N and 200 units of Component V would arrive at the beginning of week 3. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Week 1 has elapsed. Hence, plan has to be prepared from week 2 through week 9. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. In addition to that, 100 units of End item E are needed in week 9.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in week 5, 55 units in week 7, and 100 units in week 9.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units on week 4 (200-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 160 units in the beginning of week 4. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Scheduled receipt is 800 units at the beginning of week 3
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units on week 5 (440-260).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 180 units in the beginning of week 5. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 4 is 260 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 210 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 60 units on week 5 (110-50).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 50 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
2)

To prepare: Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Two weeks (week 2 and week 3) has elapsed. Hence, plan has to be prepared from week 4 through week 11. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. In addition to that, 100 units of End item E are needed in week 9.
Planned order releases from 2nd and 3rd week should be used as scheduled receipt units. Scheduled receipt are 160 units of Component I at the start of 4th week, 800 units of Component N at the start of 5th week, and 200 units of Component V at the start of 5th week.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in week 5, 55 units in week 7, and 100 units in week 9.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units at week 5 (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 40 units.
- Scheduled receipt is 160 units at the beginning of week 4.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units on week 6 (110-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 110 units in the beginning of week 6. Hence, they need to order for 110 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 5.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 260 units.
- Scheduled receipt is 800 units at the beginning of week 3
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units on week 7 (800-620).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 180 units in the beginning of week 7. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 5.
- Projected on hand inventory for week 5 is 1,060 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 50 units.
- Scheduled receipt is 200 units at the beginning of week 5.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 60 units on week 7 (200-140).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 60 units in the beginning of week 7. Hence, they need to order for 200 units (as the lot size is multiples of 200) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 5.
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
Want to see more full solutions like this?
Chapter 12 Solutions
Loose Leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Additional Business Textbook Solutions
Intermediate Accounting (2nd Edition)
Managerial Accounting (5th Edition)
Marketing: An Introduction (13th Edition)
Horngren's Accounting (12th Edition)
Essentials of MIS (13th Edition)
Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)
- PepsiCo South Africa says the incident where a woman discovered part of a rodent in her loaf of bread, is anisolated occurrence.Durban woman, Nombulelo Mkumla, took to social media last week to share how she discovered the rodent.In a lengthy Facebook post, she said she purchased the loaf of bread from a local shop after work on August 27.For the next days, Mkumla proceeded to use slices of bread from the load to make toast."Then, on the morning of August 31, I took the bread out of the fridge to make toast and noticed something disgusting andscary. I took a picture and sent it to my friends, and one of them said, 'Yi mpuku leyo tshomi' [That's a rat friend]“."I was in denial and suggested it might be something else, but the rat scenario made sense - it's possible the rat got into thebread at the factory, and no one noticed," Mkumla said.She went back to the shop she'd bought the bread from and was told to lay a complaint directly with the supplier.She sent an email with a video and…arrow_forwardThe deaths are included in the discharges; this includes deaths occurring in less than 48 hours and postoperative deaths. Rehabilitation had 362 discharges, 22 deaths, 1<48 hours, 0 Postoperative. what is the gross death rate for the rehabilitation service?arrow_forwardA copy machine is available 24 hours a day. On a typical day, the machine produces 100 jobs. Each job takes about 3 minutes on the machine, 2 minutes of which is processing time and 1 minute is setup time (logging in, defining the job). About 20 percent of the jobs need to be reworked, in which case the setup time and the processing time have to be repeated. The remainder of the time, the equipment is idle. What is the OEE of the equipment?arrow_forward
- How do you think we can keep updating Toyota's ideas as new technologies come out and what customers want keeps changing?arrow_forwardGiven how TPS has helped change things in so many fields, do you think there are parts of it that might be hard to use in areas that aren’t about making things, like in healthcare or services? If so, why do you think that might be?arrow_forwardDo you feel there is anything positive about rework?arrow_forward
- Do you think technology can achieve faster setup times? How would it be implemented in the hospital workforce?arrow_forwardIn your experience or opinion, do you think process changes like organizing workspaces make a bigger difference, or is investing in technology usually the better solution for faster setups?arrow_forwardHave you seen rework done in your business, and what was done to prevent that from occurring again?arrow_forward
- Research a company different than case studies examined and search the internet and find an example of a business that had to rework a process. How was the organization affected to rework a process in order to restore a good flow unit? Did rework hurt a process or improve the organization's operational efficiency? • Note: Include a reference with supportive citations in the discussion reply in your post.arrow_forwardSetup time is very important in affecting a process and the capacity of a process. How do you reduce setup time? Give examples of reducing setup time. Please Provide a referenecearrow_forwardDo you think TPS was successful? If so, how? Are there other companies that have used TPS? If so, give examples. Please provide a referencearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage Learning

