SummerFun. Inc., produces a variety of recreation and leisure products. The
Use the following information to develop aggregate plans.
Develop an aggregate plan using each of the following guidelines and compute the total cost for each plan. Hint: You will need extra output in April and August to accommodate demand in the following months.
a. Use regular production. Supplement using inventory, overtime, and subcontracting as needed. No backlogs allowed.
b. Use a level strategy. Use a combination of backlogs, subcontracting, and inventory to handle variations in demand. There should not be a backlog in the final period.
a)
To determine: The total cost using an aggregate plan.
Introduction:The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Answer to Problem 7P
Explanation of Solution
Given information:
Regular production cost is $80, overtime production cost is $120, subcontracting cost is $140, backorder cost is $20, holding cost is $10, regular capacity is 40 units, overtime cost is 8 units, and subcontracting capacity is 12 units. Beginning inventory is given as 0 units. In addition to this forecast for 7 months is given as follows:
Month | March | April | May | June | July | August | September | Total |
Forecast | 50 | 44 | 55 | 60 | 50 | 40 | 51 | 350 |
Determine the total cost of the plan:
It is given that regular productions should be used. No backlogs are allowed. Supplements can be satisfied using overtime, subcontracting, and inventory.
Supporting explanation:
Forecast and regular time capacity are given. Regular time capacity is given as 40 units, remaining units should be produced using the overtime capacity. Maximum overtime capacity is given as 8 units. Thus, if the forecast is not satisfied, it can be produced using the subcontract:
Calculate the difference for the month of March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Calculate the difference for the month of April:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 4 units.
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -4 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Ending inventory for the month of April:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 4 units.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Note: The calculation repeats for all the months.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 0 units.
Average inventory for the month of April:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of April:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $22,400.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of April:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 6,120.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $140 and subcontract unit is given as 2. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $280.
Calculate the subcontract cost for the month of April:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $140 and subcontract unit is given as 3. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $420.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $2,660.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $0.
Calculate the inventory cost for the month of April:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $70.
Calculate the backorder cost for the month of March:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of April:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of May:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Note: The calculation repeats for all the months.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $31,250.
b)
To determine: The total cost using a level strategy of aggregate planning.
Introduction:Level production strategy is a production strategy used to produce at a constant rate. This strategy keeps constant level of workforce and backlog of demand.
Answer to Problem 7P
Explanation of Solution
Given information:
Regular production cost is $80, overtime production cost is $120, subcontracting cost is $140, backorder cost is $20, holding cost is $10, regular capacity is 40 units, overtime cost is 8 units, and subcontracting capacity is 12 units. Beginning inventory is given as 0 units. In addition to this forecast for 7 months is given as follows:
Month | March | April | May | June | July | August | September | Total |
Forecast | 50 | 44 | 55 | 60 | 50 | 40 | 51 | 350 |
Determine the total cost of the plan:
Subcontracting, inventory, and backlogs can be used to handle the fluctuations in the demand. Initial solution using regular time and overtime without using subcontracting is as follows:
Supporting explanation:
Determine the regular time productivity:
It is calculated by taking an average of the given forecast.
Calculate the difference for the month of March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -2 units.
Calculate the difference for the month of April:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 4 units.
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is --7 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Ending inventory for the month of April:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Difference between output and forecast is 2 (4-2). Hence, the ending inventory is 2 units.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Note: The calculation repeats for all the months.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 0 units.
Average inventory for the month of April:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 1unit.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 1unit.
Note: The calculation repeats for all the months.
Backlogs for the month of 1:
It is number of units required in the month. As there is no previous month for 1st month, the difference would be the backlog. Hence, the backlog for 1st is 2 units.
Backlogs for the month of 2:
As the difference is positive, there would not be backlog.
Backlogs for the month of 3:
It is number of units required in the month. It is calculated by adding the backlog of previous month and the difference between output and forecast of current month (without considering the negative sign). Hence, the backlog is 5 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of April:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $22,400.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of April:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 6,120.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $140.
Calculate the subcontract cost for the month of April:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $0.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $0.
Calculate the inventory cost for the month of April:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $10.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $10.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $70.
Calculate the backorder cost for the month of March:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $40.
Calculate the backorder cost for the month of April:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of May:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $100.
Note: The calculation repeats for all the months.
Calculate the total backorder cost:
It is calculated by adding the backorder cost of all the months.
Hence, the total backorder cost is $1,360.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $30,500.
Determine the total cost of the plan:
Subcontracting, inventory, and backlogs can be used to handle the fluctuations in the demand. Final solution using regular time, overtime, and subcontracting is as follows:
Supporting explanation:
Determine the regular time productivity:
It is calculated by taking an average of the given forecast.
Calculate the difference for the month of March:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 0 units.
Calculate the difference for the month of April:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is 4 units.
Calculate the difference for the month of May:
It is the calculation of difference between forecast and output. Hence, it can be calculated by subtracting the forecast from the output. Hence, the difference is -4 units.
Note: The calculation repeats for all the months.
Beginning inventory:
The initial inventory is given as 0. For the remaining months, ending inventory of previous month would be the beginning inventory of present month.
Ending inventory for the month of March:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Ending inventory for the month of April:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 4 units.
Ending inventory for the month of May:
Ending inventory can be determined by adding the beginning inventory and difference between output and forecast. Hence, the ending inventory is 0 units.
Note: The calculation repeats for all the months.
Average inventory for the month of March:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 0 units.
Average inventory for the month of April:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Average inventory for the month of May:
It is calculated by taking an average of beginning inventory and ending inventory. Hence, the average inventory is 2 units.
Note: The calculation repeats for all the months.
Backlogs for the month of June:
It is number of units required in the month. It is calculated by adding the backlog of previous month and the difference between output and forecast of current month (without considering the negative sign). Hence, the backlog is 3 units.
Backlogs for the month of July:
It is number of units required in the month. It is calculated by adding the backlog of previous month and the difference between output and forecast of current month (without considering the negative sign). Hence, the backlog is 5 units.
Note: The calculation repeats for all the months.
Calculate the regular time cost for the month of March:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of April:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Calculate the regular time cost for the month of May:
Regular time cost per unit is given as $80 and regular time unit is given as 40. Regular time cost is calculated by multiplying regular time unit and regular time cost per unit. Hence, the regular time cost is $3,200.
Note: The calculation repeats for all the months.
Calculate the total regular time cost:
It is calculated by adding the regular time cost of all the months.
Hence, the total regular time cost is $22,400.
Calculate the overtime cost for the month of March:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of April:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Calculate the overtime cost for the month of May:
Overtime cost per unit is given as $120 and overtime unit is given as 8. Overtime cost is calculated by multiplying overtime unit and overtime cost per unit. Hence, the overtime cost is $960.
Note: The calculation repeats for all the months.
Calculate the total overtime cost:
It is calculated by adding the overtime cost of all the months.
Hence, the total overtime cost is 6,120.
Calculate the subcontract cost for the month of March:
Subcontract cost per unit is given as $140 and subcontract unit is given as 2. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $280.
Calculate the subcontract cost for the month of April:
Subcontract cost per unit is given as $140 and subcontract unit is given as 0. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $0.
Calculate the subcontract cost for the month of May:
Subcontract cost per unit is given as $140 and subcontract unit is given as 3. Subcontract cost is calculated by multiplying subcontract unit and subcontract cost per unit. Hence, the subcontract cost is $420.
Note: The calculation repeats for all the months.
Calculate the total subcontract cost:
It is calculated by adding the subcontract cost of all the months.
Hence, the total subcontract cost is $1,960.
Calculate the inventory cost for the month of March:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $0.
Calculate the inventory cost for the month of April:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Calculate the inventory cost for the month of May:
It is calculated by average balance inventory cost and the average inventory units. Hence, the inventory cost is $20.
Note: The calculation repeats for all the months.
Calculate the total inventory cost:
It is calculated by adding the inventory cost of all the months.
Hence, the total inventory cost is $70.
Calculate the backorder cost for the month of March:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of April:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Calculate the backorder cost for the month of May:
It is calculated by multiplying the backorder cost and the backlog. Hence, the backorder cost is $0.
Note: The calculation repeats for all the months.
Calculate the total backorder cost:
It is calculated by adding the backorder cost of all the months.
Hence, the total backorder cost is $160.
Calculate the total cost of the plan:
It is calculated by adding the total regular time cost, overtime cost, subcontract cost, and inventory cost.
Hence, the total cost of the plan is $31,310.
Want to see more full solutions like this?
Chapter 11 Solutions
Operations Management (Comp. Instructor's Edition)
- Analyse the impact of integrating EDI (Electronic Data Interchange) with API (Application Programming Interface) on supply chain management, particularly focusing on how this integration enhances information flow and operational efficiency. Consider the challenges that might arise from this integration in terms of managing legacy systems alongside modern applications.arrow_forward1) View the video What is Operations Management (14.01 minutes, Ctrl+Click on the link); what are your key takeaways (tie to one or more of the topics discussed in Chapters 1 and/or 2) after watching this video. (https://www.viddler.com/embed/d01189e1) Note: As a rough guideline, please try to keep the written submission to one or two paragraphs. 2) View the video What McDonald’s is serving up at its new CosMc’s Chain (3.42 mins, Ctrl+Click in the link), and answer the following questions: (https://www.youtube.com/watch?v=k7ojpUzE8q4) i) From a strategic perspective, why do you think McDonald’s is opting for this new chain rather than trying to launch the new menu in its existing restaurants? ii) What factors do you think in McDonald’s external and internal environments are driving its decision to open the CosMc’s locations? iii) How do you think this format will improve McDonald’s profit margin as compared to its regular fast-food restaurants? Note: As a…arrow_forwardSince the end of World War II, globalization has steadily increased with rapid expansion around the turn of the 21st century. What are some of the forces driving globalization and international business? What are some of the challenges of engaging in international business compared to doing business in your home country?arrow_forward
- PS.53 Brother I.D. Ricks is a faculty member at BYU-Idaho whose grandchildren live in Oklahoma and California. He and his wife would like to visit their grandchildren at least once a year in these states. They currently have one vehicle with well over 100,000 miles on it, so they want to buy a newer vehicle with fewer miles and that gets better gas mileage. They are considering two options: (1) a new subcompact car that would cost $18,750 to purchase or (2) a used sedan that would cost $12,750.They anticipate that the new subcompact would get 37 miles per gallon (combined highway and around town driving) while the sedan would get 26 miles per gallon. Based on their road tripping history they expect to drive 13,000 miles per year. For the purposes of their analysis they are assuming that gas will cost $2.93 per gallon.Question: How many miles would the Ricks need to drive before the cost of these two options would be the same? (Display your answer to the nearest whole number.) (Hint:…arrow_forwardChoose one major approach to job design, and then discuss how best that approach can be utilized in either your current or previous employer, including a discussion of its strengths and weaknesses.arrow_forwardThe results of your four plans will provide an indicative EOQ value. State this value and discuss in a precise manner, why it is not the exact, true value. Additional calculations in the form of plans E, F etc. may also assist your explanation of the EOQ and can be includedarrow_forward
- i). Complete the table assuming a Level production plan. ii) Comment on your results and explain whether at this stage, you consider a Level plan is a suitable approach for this particular business. Your comment should include reference to a calculated ‘fill rate’.arrow_forwardIn the following sawtooth inventory profile diagram, two inventory plans with different order quantities (Q) and different frequencies of delivery are shown; order quantity for Plan A = 200 units and Plan B = 50 units. i). Total demand (D) is 350 units, the holding cost per unit (Ch) is equal to (£0.8) and the ordering cost per order (Co) is (£12.5). Calculate the total costs for each plan and state which one is more preferable along with the reason why. ii). There is a stark difference in the composition of the total costs of Plans A and B. Explain this difference and why it occurs. Use the breakdown of costs for each plan to help illustrate your answer.arrow_forwardi). Complete the table for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible. You should support your answer with numerical data derived from Table 3. In comparing the costs, state any other assumptions made.arrow_forward
- i). Complete for a Chase production plan. ii). Explain whether a Level or Chase plan is more suitable for the demand pattern experienced by this particular business, which incidentally relies on highly skilled workers in the production process. Assume a starting workforce of 7 and that fractional workers are permissible.arrow_forwardComplete the table for a Chase production plan.arrow_forwardHow much can the garden centre expect to sell during each quarter of next year (Year 3) accounting for seasonality? Your forecast must make use of seasonal indices. All workings must be shown in full. (NOTE: Please round your calculations to three decimal places).arrow_forward
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational PublishingPurchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningPractical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
- Foundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning