Question
Chapter 11, Problem 7CRCT
Summary Introduction
To discuss: Whether the new project of a firm will reach cash breakeven point, accounting breakeven point or financial breakeven point first. Also, determine which reaches second and last.
Introduction:
Accounting break-even is a sales point at which there is no profit or loss. It is the most widely used measure of break-even point.
Financial break-even point is a point that occurs at the time when a particular project breaks even on a financial basis. This means that the
Cash break-even point specifies a sales level that can result in a zero operating cash flow.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Question 6
Which one of the following methods predicts the amount by which the value of a firm will
change if a project is accepted?
O Payback
O Profitability index
O Net present value
O Internal rate of return
O Discounted payback
LO3
Explain how to set a bid price for a project.
LO4
Evaluate the equivalent annual cost of a project.
Divisional Cost of Capital [LO5] Under what circumstances would it be appropriate for a firm to use different costs of capital for its different operating divisions? If the overall firm WACC were used as the hurdle rate for all divisions, would the riskier divisions or the more conservative divisions tend to get most of the investment projects? Why? If you were to try to estimate the appropriate cost of capital for different divisions, what problems might you encounter? What are two techniques you could use to develop a rough estimate for each division’s cost of capital?
Chapter 11 Solutions
Fundamentals of Corporate Finance with Connect Access Card
Ch. 11.1 - Prob. 11.1ACQCh. 11.1 - What are some potential sources of value in a new...Ch. 11.2 - Prob. 11.2ACQCh. 11.2 - What are the drawbacks to the various types of...Ch. 11.3 - How are fixed costs similar to sunk costs?Ch. 11.3 - What is net income at the accounting break-even...Ch. 11.3 - Why might a financial manager be interested in the...Ch. 11.4 - If a project breaks even on an accounting basis,...Ch. 11.4 - If a project breaks even on a cash basis, what is...Ch. 11.4 - Prob. 11.4CCQ
Ch. 11.5 - What is operating leverage?Ch. 11.5 - How is operating leverage measured?Ch. 11.5 - Prob. 11.5CCQCh. 11.6 - What is capital rationing? What types are there?Ch. 11.6 - Prob. 11.6BCQCh. 11 - Prob. 11.1CTFCh. 11 - Marcos Entertainment expects to sell 84,000...Ch. 11 - Delta Tool has projected sales of 8,500 units at a...Ch. 11 - What is true for a project if that project is...Ch. 11 - A capital-intensive project is one that has a...Ch. 11 - Pavloki, Inc., has three proposed projects with...Ch. 11 - Forecasting Risk [LO1] What is forecasting risk?...Ch. 11 - Sensitivity Analysis and Scenario Analysis [LO1,...Ch. 11 - Prob. 3CRCTCh. 11 - Operating Leverage [LO4] At one time at least,...Ch. 11 - Operating Leverage [LO4] Airlines offer an example...Ch. 11 - Prob. 6CRCTCh. 11 - Prob. 7CRCTCh. 11 - Prob. 8CRCTCh. 11 - Prob. 9CRCTCh. 11 - Scenario Analysis [LO2] You are at work when a...Ch. 11 - Calculating Costs and Break-Even [LO3] Night...Ch. 11 - Prob. 2QPCh. 11 - Scenario Analysis [LO2] Sloan Transmissions, Inc.,...Ch. 11 - Sensitivity Analysis [LO1] For the company in the...Ch. 11 - Sensitivity Analysis and Break-Even [LO1, 3] We...Ch. 11 - Prob. 6QPCh. 11 - Prob. 7QPCh. 11 - Calculating Break-Even [LO3] In each of the...Ch. 11 - Calculating Break-Even [LO3] A project has the...Ch. 11 - Using Break-Even Analysis [LO3] Consider a project...Ch. 11 - Calculating Operating Leverage [LO4] At an output...Ch. 11 - Leverage [LO4] In the previous problem, suppose...Ch. 11 - Operating Cash Flow and Leverage [LO4] A proposed...Ch. 11 - Cash Flow and Leverage [LO4] At an output level of...Ch. 11 - Prob. 15QPCh. 11 - Prob. 16QPCh. 11 - Sensitivity Analysis [LO1] Consider a four-year...Ch. 11 - Operating Leverage [LO4] In the previous problem,...Ch. 11 - Project Analysis [LO1, 2, 3, 4] You are...Ch. 11 - Project Analysis [LO1, 2] McGilla Golf has decided...Ch. 11 - Prob. 21QPCh. 11 - Sensitivity Analysis [LO1] McGilla Golf would like...Ch. 11 - Break-Even Analysis [LO3] Hybrid cars are touted...Ch. 11 - Break-Even Analysis [LO3] In an effort to capture...Ch. 11 - Prob. 25QPCh. 11 - Operating Leverage and Taxes [LO4] Show that if we...Ch. 11 - Scenario Analysis [LO2] Consider a project to...Ch. 11 - Sensitivity Analysis [LO1] In Problem 27, suppose...Ch. 11 - Prob. 29QPCh. 11 - Prob. 30QP
Knowledge Booster
Similar questions
- Basic NPV methods tell us that the value of a project today is NPV0. Time value of money issues also lead us to believe that if we choose not to do the project that it will be worth NPV1 one period from now, such that NPV0 > NPV1. Why then do we see some firms choosing to defer taking on a project?arrow_forwardQUESTION 15 The internal rate of return is defined as the: rate at which the net present value of a project is equal zero. rate of return a project will generate if the project in financed solely with internal funds. O rate that equates the net cash inflows of a project to zero. maximum rate of return a firm expects to earn on a project. rate that causes the profitability index for a project to equal zero.arrow_forwardAnswer the following question (Q#4) Consider a poor country with an under-developed economy which could invest trillions into its current capital stock – either moving “up” its current productivity “curve” (PC) or shifting to a new and higher productivity (PC) curve. Which approach is likely best for increasing the country’s living standards (Real GDP Per Person) through time? (a) A continuous build-up of the current capital stock with established technology will achieve more – capital “deepening” with more capital for each worker. (b) R&D that supports “cutting edge” invention and innovation will propel labor (Q#8) Until recently, the economy in China has grown steadily due to the deliberate emphasis on low skill – low wage factory labor methods. However, China’s economic standard of living is still comparatively low. To achieve a U.S. or German standard of living what should be done? a) China should…arrow_forward
- Which of the following is TRUE about NPV? LO3 NPV is the ratio of a project's present value to the amount of resources consumed in generating it. O NPV is the rate at which IRR equals $0. O NPV and IRR are equally reliable investment decision rules when evaluating mutually exclusive projects. O NPV is the difference between the present value of the benefits and the present value of the costs of a project.arrow_forwardnote : please you dont use excel.arrow_forwardMaking the accept or reject decision Hungry Whale Electronics's decision to accept or reject project Alpha is independent of its decisions on other projects. If the firm follows the NPV method, it should project Alpha. Which of the following statements best explains what it means when a project has an NPV of $0? O When a project has an NPV of $0, the project is earning a rate of return less than the project's weighted average cost of capital. It's OK to accept the project, as long as the project's profit is positive. O When a project has an NPV of $0, the project is earning a rate of return equal to the project's weighted average cost of capital. It's OK to accept a project with an NPV of $0, because the project is earning the required minimum rate of return. O When a project has an NPV of $0, the project is earning a profit of $0. A firm should reject any project with an NPV of $0, because the project is not profitable.arrow_forward
- A firm has to choose between two possible projects, the outcome of which depend on whether the economy is in recession or boom: Probability Project A NPV (£m) Project B NPV (£m) Recession 0.6 -100 -50 Boom 0.4 +250 +200 Using ENPV which project should be chosen?arrow_forwardF3arrow_forwardCalculating Flotation Costs [LO4] Suppose your company needs $24 million to build a new assembly line. Your target debt-equity ratio is .75. The flotation cost for new equity is 7 percent, but the flotation cost for debt is only 3 percent. Your boss has decided to fund the project by borrowing money because the flotation costs are lower and the needed funds are relatively small.a. What do you think about the rationale behind borrowing the entire amount?b. What is your company’s weighted average flotation cost, assuming all equity is raised externally?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Financial & Managerial AccountingAccountingISBN:9781285866307Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Financial & Managerial AccountingAccountingISBN:9781337119207Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage LearningAccounting (Text Only)AccountingISBN:9781285743615Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning
Financial & Managerial Accounting
Accounting
ISBN:9781285866307
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Financial & Managerial Accounting
Accounting
ISBN:9781337119207
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Accounting (Text Only)
Accounting
ISBN:9781285743615
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning