Concept explainers
a)
To determine: Weeks of supply for Company A.
Introduction:
a)

Answer to Problem 6P
Weeks of supply for Company A is 3.85.
Explanation of Solution
Given information:
Company A | |
Net revenue | $16,500.00 |
Cost of sales | $13,500.00 |
Inventory | $1,000.00 |
Total assets | $8,600.00 |
Formula to calculate week of supply:
Calculation of week of supply:
Sale per week is calculated by dividing the annual sales with the number of weeks in a year. Annual sales $13,500 is divided with 52 which give $259.60.
Week of supply is calculated by dividing inventory with sales per week. The inventory $1,000 is divided with $259.60 yields 3.85 as weeks of supply for company A.
Hence, weeks of supply for Company A is 3.85.
b)
To determine: Percentage of assets committed to inventory in Company A.
b)

Answer to Problem 6P
Answer: 11.63% of total assets of Company A is committed to inventory.
Explanation of Solution
Given information:
Company A | |
Net revenue | $16,500.00 |
Cost of sales | $13,500.00 |
Inventory | $1,000.00 |
Total assets | $8,600.00 |
Formula to inventory investment:
Calculation of inventory investment:
Percentage of assets committed to inventory can be calculated by computing inventory investment. Inventory investment is calculated by dividing inventory with the total assets. The inventory $1,000 is divided with total assets $8,600 which yields 11.63% of assets of Company A is committed to inventory.
Hence, 11.63% of total assets of Company A are committed to inventory.
c)
To determine: Inventory turnover of Company A.
c)

Answer to Problem 6P
The turnover of Company B is 13.5.
Explanation of Solution
Given information:
Company A | |
Net revenue | $16,500.00 |
Cost of sales | $13,500.00 |
Inventory | $1,000.00 |
Total assets | $8,600.00 |
Formula to calculate turnover:
Calculation of turnover:
The turnover is calculated by dividing cost of sales with inventory. The cost of sales $13,500 is divided with inventory $1,000 which yields turnover of 13.5 for company A.
Hence, the turnover of Company A is 13.5.
d)
To Compare: Performance of Company A with industry leaders.
d)

Answer to Problem 6P
Company A needs to improve its performance.
Explanation of Solution
Given information:
Company A | Company B | |
Net revenue | $16,500.00 | $27,500.00 |
Cost of sales | $13,500.00 | $21,500.00 |
Inventory | $1,000.00 | $1,250.00 |
Total assets | $8,600.00 | $16,600.00 |
Formula:
Comparison calculation of turnover and inventory investment:
Company A | Company B | |
Net revenue | $16,500.00 | $27,500.00 |
Cost of sales | $13,500.00 | $21,500.00 |
Inventory | $1,000.00 | $1,250.00 |
Total assets | $8,600.00 | $16,600.00 |
Turn over | 13.5 | 17.2 |
Inventory investment | 11.63% | 7.53% |
From the above calculation of turnover and inventory investment it can be inferred that Company A has a turnover of 13.5 when the turnover of Company B is 17.2. The inventory investment of Company A is 11.63% when the Company B has 7.53%.
In both the aspects, Company B is far ahead of Company A. So, the performance of Company A has to be better and the management team must look into the aspects to improve the performance.
Hence, Company A needs to improve its performance.
Want to see more full solutions like this?
Chapter 11 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
- At Quick Car Wash, the wash process is advertised to take less than 6 minutes. Consequently, management has set a target average of 330 seconds for the wash process. Suppose the average range for a sample of 7 cars is 10 seconds. Use the accompanying table to establish control limits for sample means and ranges for the car wash process. Click the icon to view the table of factors for calculating three-sigma limits for the x-chart and R-chart. The UCLR equals seconds and the LCLR equals seconds. (Enter your responses rounded to two decimal places.)arrow_forwardIf Jeremy who is the VP for the operations, proceeds with their existing prototype (which is option a), the firm can then expect sales to be 120,000 units at $550 each. And with a probability of 0.52 and a 0.48 probability of 65,000 at $550. we However, he uses his value analysis team (option b), the firm expects sales of 75,000 units at $770, with a probability of 0.78 and a 0.22 probability of 65,000 units at $770. Value engineering, at a cost of $100,000, is only used in option b. Which option for this has the highest expected monetary value (EMV)? The EMV for option a is $? The EMV for option b is $? Which has the highest expected monetary value. A or B?arrow_forwardPart 1 of 2 Jim's Outfitters, Inc., makes custom western shirts. The shirts could be flawed in various ways, including flaws in the weave or color of the fabric, loose buttons or decorations, wrong dimensions, and uneven stitches. Jim randomly examined 10 shirts, with the following results shown to the right. Shirt Defects 1 7 2 1 4 13 3 10 2 8 5 9 10 8 7 a. Assuming that 10 observations are adequate for these purposes, determine the three-sigma control limits for defects per shirt. The UCLC equals and the LCL equals (Enter your responses rounded to two decimal places. If your answer for LCL is negative, enter this value as 0.)arrow_forward
- Management at Webster Chemical Company is concerned as to whether caulking tubes are being properly capped. If a significant proportion of the tubes are not being sealed, Webster is placing its customers in a messy situation. Tubes are packaged in large boxes of 144. Several boxes are inspected, and the following numbers of leaking tubes are found: Sample Tubes Sample Tubes Sample Tubes 1 7 8 7 15 7 2 7 9 8 16 9 3 6 10 7 17 3 4 4 11 1 18 7 5 8 12 8 19 7 6 7 2 9 13 14 1 20 6 7 Total 121 Calculate p-chart three-sigma control limits to assess whether the capping process is in statistical control. The UCLp equals and the LCLp equals (Enter your responses rounded to three decimal places. If your answer for LCLp is negative, enter this value as 0.)arrow_forwardAspen Plastics produces plastic bottles to customer order. The quality inspector randomly selects four bottles from the bottle machine and measures the outside diameter of the bottle neck, a critical quality dimension that determines whether the bottle cap will fit properly. The dimensions (in.) from the last six samples are Bottle Sample 1 2 3 4 1 0.624 0.586 0.602 0.591 2 0.613 0.599 0.578 0.618 3 0.606 0.585 0.587 0.623 4 0.581 0.623 0.571 0.610 5 0.609 0.610 0.623 0.617 6 0.605 0.573 0.570 0.602 Click the icon to view the table of factors for calculating three-sigma limits for the x-chart and R-chart. Suppose that the specification for the bottle neck diameter is 0.600 ± 0.050 in. and the population standard deviation is 0.014 in. a. What is the process capability index? The Cpk is (Enter your response rounded to two decimal places.)arrow_forwardHow would you handle the Apple 'batterygate' scandal as an operations manager? What quality measures would you take to fix the problem and prevent it from happening again? When would you implement these measures and communicate with the stakeholders?arrow_forward
- Perosnal Thoughts about the articlearrow_forwardRevenue retrieval for Brew Mini= $ round response to two decimal places What would be the best design alternative? Brew master or brew miniarrow_forwardThe revenue retrieval for PG Glass design is ?. Enter response as a whole number). The revenue retrieval for Glass Unlimited design is ? (enter your response as a whole number). What is The best design alternative? Glass unlimited or PG Glass?arrow_forward
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningContemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning
- MarketingMarketingISBN:9780357033791Author:Pride, William MPublisher:South Western Educational Publishing