PRIN.OF CORPORATE FINANCE
13th Edition
ISBN: 9781260013900
Author: BREALEY
Publisher: RENT MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 11, Problem 5PS
Biased forecasts Look back to the cash flows for projects F and G in Section 5-3. The cost of capital was assumed to be 10%. Assume that the forecasted cash flows for projects of this type are overstated by 8% on average. That is, the
- a. What are the projects’ true NPVs?
- b. What are the NPVs at the 18% discount rate?
- c. Are there any circumstances in which the 18% discount rate would give the correct NPVs? (Hint: Could upward bias be more severe for more-distant cash flows?)
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Which of the following is FALSE regarding various methods of project analysis?
Both NPV and IRR consider the time value of money.
Average Accounting Return ignores the time value of money.
Payback focuses on liquidity.
O Profitability Index is able to rank projects in the situation of capital rationing.
() Payback considers the time value of money.
Next Page
Page 17 of 3
Previous Page
Submit Quiz
O of 30 questions saved
Which one of the following statements is correct concerning the payback rule?
a. The payback period is computed using the present value of each of the cash flows.
b. The rule says that you should accept a project if the payback period is greater than 1.0.
c. The rule is biased in favour of long-term projects.
d. The rule is flawed because it ignores all cash flows after some arbitrary point in time.
Last month, Lloyd's Systems analyzed the project whose cash flows are shown below. However, before the decision to accept or reject the project, the Federal Reserve took actions that changed interest rates and therefore the firm's WACC. The Fed's action did not affect the forecasted cash flows. By how much did the change in the WACC affect the project's forecasted NPV? Note that a project's projected NPV can be negative, in which case it should be rejected.
Old WACC:
10.00%
New WACC:
9.50%
Year
0
1
2
3
Cash flows
-$1,000
$410
$410
$410
Chapter 11 Solutions
PRIN.OF CORPORATE FINANCE
Ch. 11 - Capital budgeting process True or false? a. The...Ch. 11 - Capital budgeting process Explain how each of the...Ch. 11 - Capital budgeting process Draw up an outline or...Ch. 11 - Prob. 4PSCh. 11 - Biased forecasts Look back to the cash flows for...Ch. 11 - Prob. 6PSCh. 11 - Prob. 7PSCh. 11 - Prob. 8PSCh. 11 - Market prices Suppose the current price of gold is...Ch. 11 - Prob. 10PS
Ch. 11 - Prob. 11PSCh. 11 - Prob. 12PSCh. 11 - Prob. 13PSCh. 11 - Economic rents True or false? a. A firm that earns...Ch. 11 - Prob. 16PSCh. 11 - Economic rents Thanks to acquisition of a key...Ch. 11 - Prob. 18PSCh. 11 - Prob. 19PSCh. 11 - Prob. 20PSCh. 11 - Prob. 21PSCh. 11 - Prob. 22PSCh. 11 - Economic rents Taxes are a cost, and, therefore,...Ch. 11 - Prob. 1MCCh. 11 - Libby Flannery, the regional manager of Ecsy-Cola,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- Last month, Lloyd's Systems analyzed the project whose cash flows are shown below. However, before the decision to accept or reject the project, the Federal Reserve took actions that changed interest rates and therefore the firm's WACC. The Fed's action did not affect the forecasted cash flows. By how much did the change in the WACC affect the project's forecasted NPV? Note that a project's projected NPV can be negative, in which case it should be rejected. Old WACC: Year Cash flows. a. $14.28 b. $7.58 c. $13.50 d. $20.10 e. $8.05 10.00% 0 -$1,000 1 $430 New WACC: 2 $430 9.25% 3 $430 Chank My Work (1 remaining)arrow_forwardHardchoice Corp. is a firm considering prospective capital budgeting projects. Selected data on the projects follow: Image attached 1b) Ignoring the information in question (1a), assume instead that projects A and C are independent, Hardchoice is subject to capital rationing (i.e., it may not be able to afford both projects), and the relevant discount rate is 10%. a) What is the IRR of Project A? Project C? b) How would you rank Project A compared to Project C? Pls show formula used. Final dollar answers should be rounded to two decimal places. Interest rate answers should be rounded to 6 decimal places if expressed as a decimal or 4 decimal places if expressed as a percent. Use timeline if necessary. No excel .Thanks!arrow_forwardWhich of the following statements is FALSE? A. When evaluating a capital budgeting decision, we generally include interest expense. B. Only include as incremental expenses in your capital budgeting analysis the additional overhead expenses that arise because of the decision to take on the project. C. Many projects use a resource that the company already owns. O D. As a practical matter, to derive the forecasted cash flows of a project, financial managers often begin by forecasting earnings.arrow_forward
- The payback method helps firms establish and identify a maximum acceptable payback period that helps in their capital budgeting decisions. Consider the case of Blue Hamster Manufacturing Inc.: Blue Hamster Manufacturing Inc. is a small firm, and several of its managers are worried about how soon the firm will be able to recover its initial investment from Project Sigma’s expected future cash flows. To answer this question, Blue Hamster’s CFO has asked that you compute the project’s payback period using the following expected net cash flows and assuming that the cash flows are received evenly throughout each year. Complete the following table and compute the project’s conventional payback period. For full credit, complete the entire table. (Note: Round the conventional payback period to two decimal places. If your answer is negative, be sure to use a minus sign in your answer.) Year 0 Year 1 Year 2 Year 3 Expected cash flow -$6,000,000 $2,400,000 $5,100,000…arrow_forwardWhat will happen to the internal rate of return (IRR) of a project if the discount rate is decreased from 8% to 6%? Select one: a. We cannot determine the direction of the effect on IRR from the information provided. b. The change in discount rate will not affect IRR. c. IRR will always increase. d. IRR will always decrease.arrow_forwardA finance director has been asked to explain various methods of project appraisal to his board colleagues. The operations director has already explained to the maring director that: The payback method is a good evaluation tool as it takes into account the liquidity of an individual project The Internal Rate of Return (IRR) calculation is irrelevant as the company does not need to borrow funds for its future projects (1) (2) (3) (4) The Net Present Value (NPV) method is too complicated as various discount rates have to be tried until a zero NPV can be found The Accounting Rate of Return (ARR) would be a good method after the audited accounts are completed and the company's profit margin can be ascertained The finance director has decided he should first inform the managing director that his board colleague has not accurately explained the alternatives, as DA. only statement (1) is true B. only statement (2) is true only statement (3) is true one of the statements are truearrow_forward
- 3. Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. Answer One drawback of the regular payback for evaluating projects is that this method does not properly account for the time value of money. If a project's payback is positive, then the project should be rejected because it must have a negative NPV. The regular payback ignores cash flows beyond the payback pericod, but the discounted payback method overcomes this problem. If a company uses the same payback requirement to evaluate all projects, say it requires a payback of 4 years or less, then the company will tend to reject projects with relatively short lives and accept long-lived projects, and this will cause its risk to increase over time. The longer a project's payback period, the more desirable the project is normally considered to be by this criterion.arrow_forwardWhat information does the payback period provide? Payback period essentially provides the number of years it would take for a project to recover the initial investment from its operating cash flows. As the model was criticized, the model evolved incorporating time value of money to create the discounted payback method. The models still reflected faulty ranking criteria but they provided important information about liquidity and risk. Cash flows expected in the distant future are ____________ risky than cash flows received in the near-term—which suggests that the payback period can also serve as an indicator of project risk. (more or less) Suppose Praxis Corporation’s CFO is evaluating a project with the following cash inflows. She does not know the project’s initial cost; however, she does know that the project’s regular payback period is 2.5 years. Year Cash Flow Year 1 $350,000 Year 2 425,000 Year 3 425,000 Year 4 450,000 If the project’s…arrow_forwardWhich of the following statement about the payback period method for capital budgeting decisions is not correct? The paybackperiod method ignores the time valueof money. A shorter payback period does not always mean that one investment is more desirable than another. When the annual net cash inflow isthe same each year, the payback period = Investment required/Annual netcash inflow. When the net cash flows change from year to year, the payback period = Investment required/Average netcash inflow per year.arrow_forward
- Companies often use several methods to evaluate the project’s cash flows and each of them has its benefits and disadvantages. Based on your understanding of the capital budgeting evaluation methods, which of the following conclusions about capital budgeting are valid? Check all that apply. The discounted payback period improves on the regular payback period by accounting for the time value of money. For most firms, the reinvestment rate assumption in the NPV is more realistic than the assumption in the IRR. Because the MIRR and NPV use the same reinvestment rate assumption, they always lead to the same accept/reject decision for mutually exclusive projects. True or False: Sophisticated firms use only the NPV method in capital budgeting decisions.arrow_forwardThe payback method helps firms establish and identify a maximum acceptable payback period that helps in their capital budgeting decisions. Consider the case of Cold Goose Metal Works Inc.: Cold Goose Metal Works Inc. is a small firm, and several of its managers are worried about how soon the firm will be able to recover its initial investment from Project Beta’s expected future cash flows. To answer this question, Cold Goose’s CFO has asked that you compute the project’s payback period using the following expected net cash flows and assuming that the cash flows are received evenly throughout each year. Complete the following table and compute the project’s conventional payback period. For full credit, complete the entire table. (Note: Round the conventional payback period to the nearest two decimal places. If your answer is negative use a minus sign.) Year 0 Year 1 Year 2 Year 3 Expected cash flow -$4,500,000 $1,800,000 $3,825,000 $1,575,000 Cumulative…arrow_forwardThe payback method helps firms establish and identify a maximum acceptable payback period that helps in their capital budgeting decisions. Consider the case of Cold Goose Metal Works Inc.: Cold Goose Metal Works Inc. is a small firm, and several of its managers are worried about how soon the firm will be able to recover its initial investment from Project Beta’s expected future cash flows. To answer this question, Cold Goose’s CFO has asked that you compute the project’s payback period using the following expected net cash flows and assuming that the cash flows are received evenly throughout each year. Complete the following table and compute the project’s conventional payback period. For full credit, complete the entire table. (Note: Round the conventional payback period to two decimal places. If your answer is negative, be sure to use a minus sign in your answer.) Year 0 Year 1 Year 2 Year 3 Expected cash flow -$4,500,000 $1,800,000 $3,825,000 $1,575,000…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage Learning
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License