
Concept explainers
Most Company has as opportunity to invest in one of two new projects. Project Y requires a $350,000
Investment for new machinery with a four-year life and no salvage value. Projects Z requires a $350,000
Investment for new machinery with a three-year life and no salvage value. The two projects yield the following predicted annual results. The company uses straight-line
Project Y | Project Z | |
Sales…….. | $350,000 | $280,000 |
Expenses | ||
Direct materials | 49,000 | 35,000 |
Direct labor | 70,000 | 42,000 |
126,000 | 126,000 | |
Selling and administrative expenses | 25,000 | 25,000 |
Total expenses | 270,000 | 228,000 |
Pretax Income | 80,000 | 52,000 |
Income taxes (10%) | 24,000 | 85,000 |
Net income | $56,000 | $36,000 |
Required
1. Compute each project’s annual expected net cash flows,(Round the net cash flows to the nearest dollar.)
2. Determine each project’s payback period. (Round the payback period to two decimals.)
3. Compute each project’s accounting
4. Determine each project’s
Analysis Component
5. Identity the project you would recommend to management and explain your choice.

Concept introduction:
Cash flow-it generally defines the advantages and the cost of a future project. As cost is represented through cash outflows and benefits as cash inflow. The present value of a cash flow refers to the discounted value of the present month of prospect sum of money.
Requirement 1:
Computation of each project annual expected net cash flows.
Answer to Problem 2PSA
Cash flow after tax | 143500 | 153066.66 |
Explanation of Solution
Part A
Particulars | Detail | Project Y | Project Z |
Sales | A | 350000 | 280000 |
Expenses | |||
Direct material | 49000 | 35000 | |
Direct labor | 70000 | 42000 | |
Overhead including depreciation | 126000 | 126000 | |
Selling and administrative | 25000 | 25000 | |
Total expenses | B | 270000 | 228000 |
Income before tax | C=A-B | 80000 | 52000 |
Income tax-30% | D=0.3*C | 24000 | 15600 |
Profit after tax | E=C-D | 56000 | 36400 |
Depreciation | F | 87500 | 116666.66 |
Cash flow after tax | G=E+F | 143500 | 153066.66 |

Concept introduction:
Payback period-it helps to indicate the time taken by the investment to realise its cost. It does not take into account the profitability of the investment and the time value of money.
Requirement 2:
To explain:
Each project’s payback period.
Answer to Problem 2PSA
Payback period | 2.44 | 1.83 |
Explanation of Solution
Calculation of pay back period
Payback period =
Particulars | Detail | Project Y | Project Z |
Cost of investment | A | 350000 | 280000 |
Annual cash flows | B | 143500 | 153066.66 |
Payback period | C=A/B | 2.44 | 1.83 |

Concept introduction:
Accounting rate of return is the relationship between standard accounting profits after tax and outlay in the project. It is that ratio which takes into consideration earnings from a project in relative to the investment made in the project. It is determined in percentage.
Requirement 3:
Computation of accounting rate of return.
Answer to Problem 2PSA
Accounting rate of return | 32% | 26% |
Explanation of Solution
There are different views in regards to compute accounting rate of return( ARR).
Method 1-
Accounting rate of return =
Method 2-
Accounting rate of return =
If a company uses a straight line of depreciation method, it can be found the average amount of investment out by using,
Annual average investment =
Particulars | Details | Project Y | Project Z |
Starting investment | A | 350000 | 280000 |
Ending investment | B | 0 | 0 |
Average investment | C=A+B/2 | 175000 | 140000 |
Particulars | Details | Project Y | Project Z |
Average profit after tax | A | 56000 | 36400 |
Average investment | B | 175000 | 140000 |
Accounting rate of return | C=A/B | 32% | 26% |

Concept introduction:
Net present value-it is calculated by discounting future cash flows. It is calculated at the required rate of return of project and afterwards subtracted by cash invested. If project has positive net present value(NPV) it is accepted.
Requirement 4:
Each project’s net present value (NPV) using 8% as the discount rate, assuming cash flow occur at each year end.
Answer to Problem 2PSA
Net present value(NPV) at 8% discounting rate | 125290.20 | 114467.63 |
Explanation of Solution
Particulars | Details | Project Y | Project Z |
Annual net cash flows | A | 143500 | 153066.66 |
The present value at the rate of 8% for cumulative 4 and 3 years | B | 3.31 | 2.58 |
The present value of cash flows | C=A*B | 475290.20 | 394467.63 |
Cost of investment | D | 350000 | 280000 |
Net present value(NPV) | C-D | 125290.20 | 114467.63 |

Concept introduction:
Net present value-it is calculated by discounting future cash flows. It is calculated at the required rate of return of the project and afterward subtracted by cash invested. If the project has a positive net present value(NPV) it is accepted.
Requirement 4:
Identifying the project to be recommended to the management.
Answer to Problem 2PSA
Project Y would be more viable to the company as it has a higher net present value than project Z i.e.$125290.20 and $114467.63
Explanation of Solution
Project Y would be more viable to the company as it has higher net present value than project Z i.e.$125290.20 and $114467.63,apart from that it has higher accounting rate of return than Z i.e. it has 32% rate in comparison to Z i.e. 26%.Though it has longer payback period than project Z then also it is recommended to select project Y, as for selecting any project most appropriate method is to find out project’s net present value(NPV) and the net present value of project Y is positive and higher than Project Z.
Want to see more full solutions like this?
Chapter 11 Solutions
Managerial Accounting
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning


