Project Analysis [LO1, 2, 3, 4] You are considering a new product launch. The project will cost $1,750,000, have a four-year life, and have no salvage value;
a. Based on your experience, you think the unit sales, variable cost, and fixed cost projections given here are probably accurate to within ±10 percent. What are the upper and lower bounds for these projections? What is the base-case
b. Evaluate the sensitivity of your base-case NPV to changes in fixed costs.
c. What is the cash break-even level of output for this project (ignoring taxes)?
d. What is the accounting break-even level of output for this project? What is the degree of operating leverage at the accounting break-even point? How do you interpret this number?
a)
![Check Mark](/static/check-mark.png)
To determine: The upper and lower bounds of unit sales, variable costs, and fixed costs projections under the scenario analysis.
Introduction:
Fixed costs remain the same as the total costs despite of the changes in the level of activity. However, the fixed cost per unit has a negative relationship with activity, that is, if the activity volume increases then total cost will decrease and vice-versa.
Variable costs are the type of costs that would vary according to the production output. It depends on the production volume.
Answer to Problem 19QP
Under the scenario analysis, the lower (worst scenario) and upper (best scenario) bounds of unit sales, variable costs, and fixed costs projections are as follows:
Scenarios |
Unit sales (in units) |
Variable cost (in $) |
Fixed cost (in $) |
Base | 190 | 10,400 | 515,000 |
Best | 209 | 9,360 | 463,500 |
Worst | 171 | 11,440 | 566,500 |
Explanation of Solution
Given information:
The unit sales is 190 units, variable costs is $10,400, and fixed costs is $515,000. The accurate estimate is ±10%.
Formula:
The formula to calculate upper bounds of unit sales projection under the scenario analysis:
The formula to calculate upper bounds of variable costs projection under the scenario analysis:
The formula to calculate upper bounds of fixed costs projection under the scenario analysis:
The formula to calculate lower bounds of unit sales projection under the scenario analysis:
The formula to calculate lower bounds of variable costs projection under the scenario analysis:
The formula to calculate lower bounds of fixed costs projection under the scenario analysis:
Compute the upper bounds of unit sales projection under the scenario analysis:
Hence, the upper bounds of unit sales projection under the scenario analysis are 209 units.
Compute the upper bounds of variable costs projection under the scenario analysis:
Hence, the upper bounds of variable costs projection under the scenario analysis are $9,360.
Compute the upper bounds of fixed costs projection under the scenario analysis:
Hence, the upper bounds of fixed costs projection under the scenario analysis are $463,500.
Compute the lower bounds of unit sales projection under the scenario analysis:
Hence, the lower bounds of unit sales projection under the scenario analysis are 171 units.
Compute the lower bounds of variable costs projection under the scenario analysis:
Hence, the lower bounds of variable costs projection under the scenario analysis are $11,440.
Compute the lower bounds of fixed costs projection under the scenario analysis:
Hence, the lower bounds of fixed costs projection under the scenario analysis are $566,500.
![Check Mark](/static/check-mark.png)
To determine: The base-case Net present value (NPV)
Introduction:
Net present value (NPV) refers to the discounted value of the future cash flows at present. The company should accept the project, if the net present value is positive or greater than zero and vice-versa. If there are two mutually exclusive projects, then the company has to select the project that has higher net present value.
Answer to Problem 19QP
The NPV for the base-case scenario is $286,619.11.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year and the initial cost of the project is $1,750,000 for the lifetime of 4 years. The variable cost per unit is $10,400 and the price per unit of the project is $17,300. The unit sold is 190 units per year, the required rate of return is 12%, and the tax rate is 35%.
The formula to calculate the operating cash flow under the base-case scenario:
Where,
P refers to the price per unit of the project
v refers to the variable cost per unit
Q refers to the number of unit sold
FC refers to the fixed costs
The formula to calculate the NPV of base-case operating cash flow:
Compute the operating cash flow in the base-case scenario:
Hence, the operating cash flow under the base-case scenario is $670,525.
Compute the NPV for the base-case scenario:
Note: To determine the present value of annuity of $1 period for 4 period at a discount rate of 12% refer the PV of an annuity of $1 table. Then find out 12% discount rate and period of 8 years value from the table. Here, the value for the rate 12% and 4 years period is 3.03735.
Hence, the NPV for the base-case scenario is $286,619.11.
![Check Mark](/static/check-mark.png)
To determine: The worst-case scenario
Introduction:
Worst-case scenario is a particular case under the scenario analysis to determine the worst scenarios of the project. The financial managers of the company use this worst-case technique to anticipate potential losses and operational issues of the project.
Answer to Problem 19QP
The NPV for the worst-case scenario is -$1,309,315.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year and initial cost of the project is $1,750,000 for the life time of 4 years. The variable cost per unit is $10,400 and price per unit of the project is $17,300. The unit sold is 190 units per year, required rate of return is 12%, and tax rate is 35%.
The formula to calculate the operating cash flow for worst-case scenario:
Where,
P refers to the price per unit of the project
v refers to the variable cost per unit
Q refers to the number of unit sold
FC refers to the fixed costs
The formula to calculate the NPV for worst- case operating cash flow:
Compute the operating cash flow under the worst-case scenario:
Hence, the operating cash flow under the worst-case scenario is $440,685.
Compute the NPV for worst case scenario:
Hence, the NPV for the worst-case scenario is -$1,309,315.
b)
![Check Mark](/static/check-mark.png)
To determine: The sensitivity of base-case NPV to change in fixed costs
Introduction:
Sensitivity analysis is analyzing the impact of changing only one variable of the net present value. It helps to identify the areas in which the forecasting errors would be severe. The basic concept of sensitivity analysis is to freeze all the variables except one variable.
Answer to Problem 19QP
The sensitivity of NPV to change in the sales value is -$1.97.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year and initial cost of the project is $1,750,000 for the life time of 4 years. The variable cost per unit is $10,400 and price per unit of the project is $17,300. The unit sold is 190 units per year, required rate of return is 12%, and tax rate is 35%. Assume the fixed cost has $516,000.
Formula:
The formula to calculate the sensitivity of NPV to make changes in the sales value:
The formula to calculate the NPV of the new case operating cash flow:
The formula to calculate the new case operating cash flow:
Where,
P refers to the price per unit of the project
v refers to the variable cost per unit
Q refers to the number of unit sold
FC refers to the fixed costs
Compute the new case operating cash flow:
Hence, the new case operating cash flow is $669,875.
Compute the NPV of new case operating cash flow:
Note: To determine the present value of annuity of $1 period for 4 period at a discount rate of 12% refer the PV of an annuity of $1 table. Then find out 12% discount rate and period of 8 years value from the table. Here, the value for the rate 12% and 4 years period is 3.03735.
Hence, the NPV of the new case operating cash flow is $284,644.83.
Compute the sensitivity of NPV to change in the sales value:
Hence, the sensitivity of NPV to change in the sales value is -$1.97. As a result, for every dollar of fixed cost, the NPV decrease by $1.97.
c)
![Check Mark](/static/check-mark.png)
To determine: The cash break-even level of output of the project
Introduction:
Cash break-even point specifies a sales level which can result in zero operating cash flow.
Answer to Problem 19QP
The cash break-even level of output is 74.64 units.
Explanation of Solution
Given information:
The unit price is $17,300, unit variable costs are $10,400, and fixed costs are $515,000.
The formula to calculate the cash break-even quantity:
Compute the cash break-even quantity:
Hence, the cash breakeven quantity is 74.64 units.
d)
![Check Mark](/static/check-mark.png)
To determine: The accounting break-even level of output
Introduction:
Accounting break-even is a sales point at which there is no profit or loss. It is the most widely used measure of break-even point.
Answer to Problem 19QP
The accounting break-even level of output is 138.04 units.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year. The initial cost of the project is $1,750,000 for the life time of 4 years. The variable cost per unit is $10,400 and price per unit of the project is $17,300.
The formula to calculate the accounting break-even quantity:
Compute the accounting break-even quantity:
Hence, the accounting breakeven quantity is 138.04 units.
![Check Mark](/static/check-mark.png)
To determine: The degree of operating leverage
Introduction:
Degree of operating leverage is a measure that indicates the sensitivity on the fixed cost of a project. It interprets that a company with more high operating leverage indicates higher fixed costs and vice versa.
Answer to Problem 19QP
The degree of operating leverage is 2.18 times.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year. The operating cash is $$670,525.
The formula to calculate the degree of operating leverage:
Compute the degree of operating leverage:
Hence, the degree of operating leverage is 1.76 times. The operating cash flows will increase by 1.76% for each 1% increase in unit sales.
Want to see more full solutions like this?
Chapter 11 Solutions
Connect 1 Semester Access Card for Fundamentals of Corporate Finance
- Ends Feb 23 Explain in detail what is Risk as defined for financial assets and what is Beta? Also discuss in detail what is the Capital Asset Pricing Model (CAPM) and its purpose.arrow_forwardThe slope parameter ß1 measures the change in annual salary, in thousands of dollars, when return on equity increases by one percentage point. Because a higher roe is good for the company, we think ß1 > 0.The data set CEOSAL1 contains information on 209 CEOs for the year 1990; these data were obtained from Business Week (5/6/91). In this sample, the average annual salary is $1,281,120, with the smallest and largest being $223,000 and $14,822,000, respectively. The average return on equity for the years 1988, 1989, and 1990 is 17.18%, with the smallest and largest values being 0.5% and 56.3%, respectively.Using the data in CEOSAL1, the OLS regression line relating salary to roe is :arrow_forwardFor the population of people in the workforce in 1976, let y = wage, where wage is measured in dollars per hour. Thus, for a particular person, if wage = 6.75, the hourly wage is $6.75. Let x = educ denote years of schooling; for example, educ =12 corresponds to a complete high school education. Because the average wage in the sample is $5.90, the Consumer Price Index indicates that this amount is equivalent to $24.90 in 2016 dollars.Using the data in WAGE1 where n = 526 individuals, we obtain the following OLS regression line (or sample regression function):arrow_forward
- Define the following: Callable bond Puttable bond Zero-coupon bond Premium bond Discount bond Crossover bonds Even though most corporate bonds in the United States make coupon payments semiannually, bonds issued elsewhere often have annual coupon payments. Suppose a German company issues a bond with a par value of EUR 1,000, 15 years to maturity, a coupon rate of 7.2%. If the yield to maturity is 6.3%, what is the current price of the bond? Rhiannon Corporation has bonds on the market with 13 years to maturity, a YTM of 7.6%, a par value of $1,000, a current market price of $1,075. The bonds make semiannual payments. What must the coupon rate be on these bonds? What would be coupon rate if the current market price is $962.68? What would be the coupon rate if the bonds make quarterly payments? Suppose that a bond has a face value of $1,000 and a YTM of 8% per annum. If the bond pays monthly coupons with an annual coupon rate of 9.6%, what will be the current price of…arrow_forwardWildcat, Incorporated, has estimated sales (in millions) for the next four quarters as follows: Q1 Q2 Q3 Sales $ 195 $ 215 $ 235 Q4 $ 265 Sales for the first quarter of the following year are projected at $210 million. Accounts receivable at the beginning of the year were $83 million. Wildcat has a 45-day collection period. Wildcat's purchases from suppliers in a quarter are equal to 50 percent of the next quarter's forecast sales, and suppliers are normally paid in 36 days. Wages, taxes, and other expenses run about 20 percent of sales. Interest and dividends are $18 million per quarter. Wildcat plans a major capital outlay in the second quarter of $98 million. Finally, the company started the year with a $84 million cash balance and wishes to maintain a $40 million minimum balance. a-1. Assume that Wildcat can borrow any needed funds on a short-term basis at a rate of 3 percent per quarter and can invest any excess funds in short-term marketable securities at a rate of 2 percent per…arrow_forwardConsider the following two bonds: Bond A Bond B Face value $1,000 $1,000 Coupon rate (annual) 8% 8% YTM 9% 7% Maturity 10 years 10 years Price (PV) ? ? Calculate the price for each bond. What is the primary factor affecting the prices of the bonds? Indicate which bond is premium and which one is discount. Is there any relationship between the YTM and the coupon rate in case of premium/discount bonds? Now, consider the following two bonds: Bond X Bond Y Face value $1,000 $1,000 Coupon rate (annual) 8% 8% YTM 11% 11% Maturity 5 years 10 years Price (PV) ? ? Calculate the price for each bond. What is the relationship between bond price and maturity, all else equal? A bond with a par value of $1,000 and a maturity of 8 years is selling for $925. If the annual coupon rate is 7%, what’s the yield on the bond? What would be the yield if the bond had semiannual payments?…arrow_forward
- Don't used hand raitingarrow_forwardDon't used Ai solutionarrow_forwardAssume an investor deposits $116,000 in a professionally managed account. One year later, the account has grown in value to $136,000 and the investor withdraws $43,000. At the end of the second year, the account value is $107,000. No other additions or withdrawals were made. During the same two years, the risk-free rate remained constant at 3.94 percent and a relevant benchmark earned 9.58 percent the first year and 6.00 percent the second. Calculate geometric average of holding period returns over two years. (You need to calculate IRR of cash flows over two years.) Round the answer to two decimals in percentage form.arrow_forward
- Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningIntermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage Learning
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningSurvey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305627734/9781305627734_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305970663/9781305970663_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337395083/9781337395083_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337514835/9781337514835_smallCoverImage.jpg)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337115773/9781337115773_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305961883/9781305961883_smallCoverImage.gif)