Concept explainers
Project Analysis [LO1, 2, 3, 4] You are considering a new product launch. The project will cost $1,750,000, have a four-year life, and have no salvage value;
a. Based on your experience, you think the unit sales, variable cost, and fixed cost projections given here are probably accurate to within ±10 percent. What are the upper and lower bounds for these projections? What is the base-case
b. Evaluate the sensitivity of your base-case NPV to changes in fixed costs.
c. What is the cash break-even level of output for this project (ignoring taxes)?
d. What is the accounting break-even level of output for this project? What is the degree of operating leverage at the accounting break-even point? How do you interpret this number?
a)
To determine: The upper and lower bounds of unit sales, variable costs, and fixed costs projections under the scenario analysis.
Introduction:
Fixed costs remain the same as the total costs despite of the changes in the level of activity. However, the fixed cost per unit has a negative relationship with activity, that is, if the activity volume increases then total cost will decrease and vice-versa.
Variable costs are the type of costs that would vary according to the production output. It depends on the production volume.
Answer to Problem 19QP
Under the scenario analysis, the lower (worst scenario) and upper (best scenario) bounds of unit sales, variable costs, and fixed costs projections are as follows:
Scenarios |
Unit sales (in units) |
Variable cost (in $) |
Fixed cost (in $) |
Base | 190 | 10,400 | 515,000 |
Best | 209 | 9,360 | 463,500 |
Worst | 171 | 11,440 | 566,500 |
Explanation of Solution
Given information:
The unit sales is 190 units, variable costs is $10,400, and fixed costs is $515,000. The accurate estimate is ±10%.
Formula:
The formula to calculate upper bounds of unit sales projection under the scenario analysis:
The formula to calculate upper bounds of variable costs projection under the scenario analysis:
The formula to calculate upper bounds of fixed costs projection under the scenario analysis:
The formula to calculate lower bounds of unit sales projection under the scenario analysis:
The formula to calculate lower bounds of variable costs projection under the scenario analysis:
The formula to calculate lower bounds of fixed costs projection under the scenario analysis:
Compute the upper bounds of unit sales projection under the scenario analysis:
Hence, the upper bounds of unit sales projection under the scenario analysis are 209 units.
Compute the upper bounds of variable costs projection under the scenario analysis:
Hence, the upper bounds of variable costs projection under the scenario analysis are $9,360.
Compute the upper bounds of fixed costs projection under the scenario analysis:
Hence, the upper bounds of fixed costs projection under the scenario analysis are $463,500.
Compute the lower bounds of unit sales projection under the scenario analysis:
Hence, the lower bounds of unit sales projection under the scenario analysis are 171 units.
Compute the lower bounds of variable costs projection under the scenario analysis:
Hence, the lower bounds of variable costs projection under the scenario analysis are $11,440.
Compute the lower bounds of fixed costs projection under the scenario analysis:
Hence, the lower bounds of fixed costs projection under the scenario analysis are $566,500.
To determine: The base-case Net present value (NPV)
Introduction:
Net present value (NPV) refers to the discounted value of the future cash flows at present. The company should accept the project, if the net present value is positive or greater than zero and vice-versa. If there are two mutually exclusive projects, then the company has to select the project that has higher net present value.
Answer to Problem 19QP
The NPV for the base-case scenario is $286,619.11.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year and the initial cost of the project is $1,750,000 for the lifetime of 4 years. The variable cost per unit is $10,400 and the price per unit of the project is $17,300. The unit sold is 190 units per year, the required rate of return is 12%, and the tax rate is 35%.
The formula to calculate the operating cash flow under the base-case scenario:
Where,
P refers to the price per unit of the project
v refers to the variable cost per unit
Q refers to the number of unit sold
FC refers to the fixed costs
The formula to calculate the NPV of base-case operating cash flow:
Compute the operating cash flow in the base-case scenario:
Hence, the operating cash flow under the base-case scenario is $670,525.
Compute the NPV for the base-case scenario:
Note: To determine the present value of annuity of $1 period for 4 period at a discount rate of 12% refer the PV of an annuity of $1 table. Then find out 12% discount rate and period of 8 years value from the table. Here, the value for the rate 12% and 4 years period is 3.03735.
Hence, the NPV for the base-case scenario is $286,619.11.
To determine: The worst-case scenario
Introduction:
Worst-case scenario is a particular case under the scenario analysis to determine the worst scenarios of the project. The financial managers of the company use this worst-case technique to anticipate potential losses and operational issues of the project.
Answer to Problem 19QP
The NPV for the worst-case scenario is -$1,309,315.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year and initial cost of the project is $1,750,000 for the life time of 4 years. The variable cost per unit is $10,400 and price per unit of the project is $17,300. The unit sold is 190 units per year, required rate of return is 12%, and tax rate is 35%.
The formula to calculate the operating cash flow for worst-case scenario:
Where,
P refers to the price per unit of the project
v refers to the variable cost per unit
Q refers to the number of unit sold
FC refers to the fixed costs
The formula to calculate the NPV for worst- case operating cash flow:
Compute the operating cash flow under the worst-case scenario:
Hence, the operating cash flow under the worst-case scenario is $440,685.
Compute the NPV for worst case scenario:
Hence, the NPV for the worst-case scenario is -$1,309,315.
b)
To determine: The sensitivity of base-case NPV to change in fixed costs
Introduction:
Sensitivity analysis is analyzing the impact of changing only one variable of the net present value. It helps to identify the areas in which the forecasting errors would be severe. The basic concept of sensitivity analysis is to freeze all the variables except one variable.
Answer to Problem 19QP
The sensitivity of NPV to change in the sales value is -$1.97.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year and initial cost of the project is $1,750,000 for the life time of 4 years. The variable cost per unit is $10,400 and price per unit of the project is $17,300. The unit sold is 190 units per year, required rate of return is 12%, and tax rate is 35%. Assume the fixed cost has $516,000.
Formula:
The formula to calculate the sensitivity of NPV to make changes in the sales value:
The formula to calculate the NPV of the new case operating cash flow:
The formula to calculate the new case operating cash flow:
Where,
P refers to the price per unit of the project
v refers to the variable cost per unit
Q refers to the number of unit sold
FC refers to the fixed costs
Compute the new case operating cash flow:
Hence, the new case operating cash flow is $669,875.
Compute the NPV of new case operating cash flow:
Note: To determine the present value of annuity of $1 period for 4 period at a discount rate of 12% refer the PV of an annuity of $1 table. Then find out 12% discount rate and period of 8 years value from the table. Here, the value for the rate 12% and 4 years period is 3.03735.
Hence, the NPV of the new case operating cash flow is $284,644.83.
Compute the sensitivity of NPV to change in the sales value:
Hence, the sensitivity of NPV to change in the sales value is -$1.97. As a result, for every dollar of fixed cost, the NPV decrease by $1.97.
c)
To determine: The cash break-even level of output of the project
Introduction:
Cash break-even point specifies a sales level which can result in zero operating cash flow.
Answer to Problem 19QP
The cash break-even level of output is 74.64 units.
Explanation of Solution
Given information:
The unit price is $17,300, unit variable costs are $10,400, and fixed costs are $515,000.
The formula to calculate the cash break-even quantity:
Compute the cash break-even quantity:
Hence, the cash breakeven quantity is 74.64 units.
d)
To determine: The accounting break-even level of output
Introduction:
Accounting break-even is a sales point at which there is no profit or loss. It is the most widely used measure of break-even point.
Answer to Problem 19QP
The accounting break-even level of output is 138.04 units.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year. The initial cost of the project is $1,750,000 for the life time of 4 years. The variable cost per unit is $10,400 and price per unit of the project is $17,300.
The formula to calculate the accounting break-even quantity:
Compute the accounting break-even quantity:
Hence, the accounting breakeven quantity is 138.04 units.
To determine: The degree of operating leverage
Introduction:
Degree of operating leverage is a measure that indicates the sensitivity on the fixed cost of a project. It interprets that a company with more high operating leverage indicates higher fixed costs and vice versa.
Answer to Problem 19QP
The degree of operating leverage is 2.18 times.
Explanation of Solution
Given information:
The fixed costs of the project are $515,000 per year. The operating cash is $$670,525.
The formula to calculate the degree of operating leverage:
Compute the degree of operating leverage:
Hence, the degree of operating leverage is 1.76 times. The operating cash flows will increase by 1.76% for each 1% increase in unit sales.
Want to see more full solutions like this?
Chapter 11 Solutions
Fundamentals of Corporate Finance
- General Financearrow_forwardAs CFO for Everything.Com, you are shopping for 6,000 square feet of usable office space for 25 of your employees in Center City, USA. A leasing broker shows you space in Apex Atrium, a 10-story multitenanted office building. This building contains 360,000 square feet of gross building area. A total of 54,000 square feet is interior space and is nonrentable. The nonrentable space consists of areas contained in the basement, elevator core, and other mechanical and structural components. An additional 36,000 square feet of common area is the lobby area usable by all tenants. The 6,000 square feet of usable area that you are looking for is on the seventh floor, which contains 33,600 square feet of rentable area, and is leased by other tenants who occupy a combined total of 24,000 square feet of usable space. The leasing broker indicated that base rents will be $30 per square foot of rentable area Required: a. Calculate total rentable area in the building as though it would be rented to…arrow_forwardDon't used Ai solutionarrow_forward
- General Finance Questionarrow_forwardConsider the following simplified financial statements for the Yoo Corporation (assuming no income taxes): Income Statement Balance Sheet Sales Costs $ 40,000 Assets 34,160 $26,000 Debt Equity $ 7,000 19,000 Net income $ 5,840 Total $26,000 Total $26,000 The company has predicted a sales increase of 20 percent. Assume Yoo pays out half of net income in the form of a cash dividend. Costs and assets vary with sales, but debt and equity do not. Prepare the pro forma statements. (Input all amounts as positive values. Do not round intermediate calculations and round your answers to the nearest whole dollar amount.) Pro forma income statement Sales Costs $ 48000 40992 Assets $ 31200 Pro forma balance sheet Debt 7000 Equity 19000 Net income $ 7008 Total $ 31200 Total 30304 What is the external financing needed? (Do not round intermediate calculations. Negative amount should be indicated by a minus sign.) External financing needed $ 896arrow_forwardAn insurance company has liabilities of £7 million due in 10 years' time and £9 million due in 17 years' time. The assets of the company consist of two zero-coupon bonds, one paying £X million in 7 years' time and the other paying £Y million in 20 years' time. The current interest rate is 6% per annum effective. Find the nominal value of X (i.e. the amount, IN MILLIONS, that bond X pays in 7 year's time) such that the first two conditions for Redington's theory of immunisation are satisfied. Express your answer to THREE DECIMAL PLACES.arrow_forward
- An individual is investing in a market where spot rates and forward rates apply. In this market, if at time t=0 he agrees to invest £5.3 for two years, he will receive £7.4 at time t=2 years. Alternatively, if at time t=0 he agrees to invest £5.3 at time t=1 for either one year or two years, he will receive £7.5 or £7.3 at times t=2 and t=3, respectively. Calculate the price per £5,000 nominal that the individual should pay for a fixed-interest bond bearing annual interest of 6.6% and is redeemable after 3 years at 110%. State your answer at 2 decimal places.arrow_forwardThe one-year forward rates of interest, f+, are given by: . fo = 5.06%, f₁ = 6.38%, and f2 = 5.73%. Calculate, to 4 decimal places (in percentages), the three-year par yield.arrow_forward1. Give one new distribution channels for Virtual Assistance (freelance business) that is not commonly used. - show a chart/diagram to illustrate the flow of the distribution channels. - explain the rationale behind it. (e.g., increased market reach, improved customer experience, cost-efficiency). - connect the given distribution channel to the marketing mix: (How does it align with the overall marketing strategy? Consider product, price, promotion, and place.). - define the target audience: (Age, gender, location, interests, etc.). - lastly, identify potential participants: (Wholesalers, retailers, online platforms, etc.)arrow_forward
- Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningIntermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage Learning
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningSurvey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage Learning