a)
To determine:
NPV of the project.
Introduction:
The difference between the
a)
Explanation of Solution
Given information:
The initial investment for the project is $67,800,000 and it generates an annual
Explanation:
The given information helps us to conclude that the project has a positive NPV and a very high IRR with initial outflow and subsequent cash inflows. Thus, the project should have a cost of capital less than the IRR value.
b)
To determine:
Cost of capital of the firm.
Introduction:
The difference between the present value of cash inflows and the present value of cash outflows over a period of time is known as the Net Present value. Cost of capital is the cost of long term financing of the firm.
b)
Explanation of Solution
Given information:
The initial investment for the project is $67,800,000 and it generates an annual cash inflow of $30,450,000 for 5 years. The project NPV is $44,200,000 and the IRR is 34.8%.
Explanation:
When the initial investment I0 ,annual cash flow (AC), rate of interest r, and the time period n is given NPV can be calculated using the equation (1) ,
By trial and error method let us assume the cost of capital to be 0.11.
When substituting 11%, NPV is $44,740,064. Since the calculated NPV is greater than the given NPV, increase the interest rate 11.19%.
When the interest rate is 11.19%, the NPV is nearly equal to the given NPV $44,200,000. Thus, cost of capital of the firm is 11.19% (approx..).
c)
To determine:
The payback period of the firm.
Introduction:
Every investment requires a time period to pay back the cost of investment. The time period taken to recover the cost of an investment is known as the payback period.
c)
Explanation of Solution
Given information:
The initial investment for the project is $67,800,000 and it generates an annual cash inflow of $30,450,000 for 5 years. The project NPV is $44,200,000 and the IRR is 34.8%.
Explanation:
Payback period for project can be calculated as follows:
The payback period for project is 2 years and 3 months.
Want to see more full solutions like this?
Chapter 10 Solutions
MyLab Finance with Pearson eText -- Access Card -- for Principles of Managerial Finance
- Bella Ltd wishes to invest in either project X or project Y, and has provided you with the following information. Project X Project Y Initial Investment Shs. 20,000 Shs. 30,000 Estimated Life 5 years 5 years Scrap Value Shs. 1,000 Shs. 2,000 The profits before depreciation and after taxation (cash flows) are as follows: Year 1 Year 2 Year 3 Year 4 Year 5 Project x Shs. Shs. Shs. Shs. Shs. 5,000 10,000 10,000 3,000 2,000 Project y 20,000 10,000 5,000 3,000 2,000…arrow_forward: According to the data given in the table below and to the annual equivalent expenditure method, which project should be preferred? Cash flows Project A Project B Project C Investment Amount (TL) 1500000 3475000 5900000 Operating expense (TL / year) Salvage Value (TL) Economic life of the project (years) Discount rate (%) 750000 500000 300000 250000 150000 100000 20 18 15 20 18 15arrow_forwardThe following table presents information on a potential project currently being evaluated by XYZ. Which assertion about statement 1 and statement 2 is true? Cost of capital Expected cash flows (number of years from today) 0 1 2 3 4 -$82,000.00 $38,000.00 $20,000.00 $31,000.00 $7,000.00 12.13% Statement 1: XYZ would accept the project based on the project's net present value and the NPV rule. Statement 2: XYZ would accept the project based on the project's payback period and the payback rule if the payback threshold is 3.75 years Statement 1 is true and statement 2 is true Statement 1 is true and statement 2 is false Statement 1 is false and statement 2 is true Statement 1 is false and statement 2 is falsearrow_forward
- You are given the following data for a project that is to be evaluated using the APV method. Year EBIT CAPEX 0 O $201.765 O $193,822 O $185,617 O $222,872 O $213,918 1 $127.000 $60,000 2 Depreciation Increase in NWC Year-end net debt $80,000 Cost of net debt = 8% Unlevered cost of capital = 11.8% Corporate tax rate = 30% Calculate the total value of the project at t = 0. using the APV method. $72,000 $50,000 $100,000 $133,000 $40,000 $80,000 $60,000 $140,000 3 $138.500 $10,000 $84,000 $30,000 $140,000arrow_forwardi need solution. i.5arrow_forwardHarris Corporation has provided the following data concerning an investment project that it is considering: Initial investment Annual cash flow Salvage value at the end of the project Expected life of the project Discount rate $ 160,000 $ 54,000 $ 11,000 O $67,000 O $160,516 O $516 O $(5,776) 4 15 per year years % Use Exhibit 7B-1 and Exhibit 7B-2, to determine the appropriate discount factor(s) using the tables provided. The net present value of the project is closest to:arrow_forward
- Coffer Company is analyzing two potential investments. Cost of machine Project X $ 97,090 Net cash flow: Year 1 Year 2 Year 3 Year 4 Project Y $ 72,000 36,500 3,700 36,500 33,500 36,500 33,500 0 13,000 If the company is using the payback period method, and it requires a payback period of three years or less, which project(s) should be selected? Multiple Choice ○ Project Y. ○ Project X. Both X and Y are acceptable projects. Neither X nor Y is an acceptable project. Project Y because it has a lower Initial Investment.arrow_forwardManjiarrow_forwardWhy straight-line depreciation method is used instead of the sinking fund depreciation method?arrow_forward
- Subject:arrow_forwardRefer to the following information. Which of the two projects, A or B, is better in terms of internal rate of return? Kenner Company is considering two projects. Project A $85,000 $20,676 Initial investment Annual cash flows Life of the project Depreciation per year 2 3 4 5 6 7 8 9 10 6 years $14,167 0.926 1.783 2.577 3.312 3.993 4.623 5.206 5.747 6.247 6.710 Present value of an Annuity of $1 in Arrears Periods 8% 12% 1 0.893 1.690 2.402 3.037 3.605 4.111 4.564 4.968 5.328 5.650 Project B $24,000 $6,011 10% 0.909 1.736 2.487 3.170 3.791 4.355 4.868 5.335 5.759 6.145 5 years $4,800 14% 0.877 1.647 2.322 2.914 4.433 3.889 4.288 4.639 4.946 5.216arrow_forwardAnswer all four of the required questions!arrow_forward
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub