(a)
The girder cross section and the spacing of intermediate stiffeners that is required.

Answer to Problem 10.7.7P
Web dimensions
Flange
Explanation of Solution
Given information:
Span length
Uniform dead load
Uniform live load
Dead load
Live load
Depth
Calculation:
Determine girder cross section and girder spacing of intermediate stiffeners.
Calculate design strength.
Try
Determine the trial web size.
Consider the condition for the web to slender.
Estimate the web thickness from the following limitations:
Estimate the web thickness from the following limitations:
From the estimated limit of
Determine area of web.
Determine area of flange.
Determine the breadth of flange.
Conclusion:
Therefore, girder size of
(b)
The size of intermediate and bearing stiffeners.

Answer to Problem 10.7.7P
Web size
Bearing stiffeners
Explanation of Solution
Given information:
Span length
Uniform dead load
Uniform live load
Dead load
Live load
Depth
Calculation:
Calculate the elastic section modulus by using the formula.
Moment of inertia is given by,
Calculate the maximum distance whichis given by,
Elastic section modulus about the axis
From
Radius of gyration is given by,
Calculating the moment of inertia.
Determine area of cross-section.
Radius of gyration is given by,
Unbraced length
Determine the
Determine the
Since
Calculate compression flange strength.
Calculate bending strength reduction factor.
Determine compression flange strength.
For proper flexural strength,
Conclusion:
Therefore, stiffeners are not needed in the middle and use girder size of
(c)
Design of all welds.

Answer to Problem 10.7.7P
Web dimensions
Flanges
Explanation of Solution
Given information:
Span length
Uniform dead load
Uniform live load
Dead load
Live load
Depth
Calculation:
Calculate the elastic section modulus by using the formula,
Moment of inertia is given by,
Calculate the maximum distance which is given by,
Elastic section modulus about the axis
From
Radius of gyration is given by,
Calculating the moment of inertia,
Determine area of cross-section.
Radius of gyration is given by,
Unbraced length
Determine the
Determine the
Since,
To calculate the plate girder strength reduction factor values,
Calculate compression flange strength.
Calculate proper flexural strength.
Calculate nominal shear strength.
Check for design strength.
Compute the value of
Assuming the equation
Hence, equation
Determine the value of
Calculate the value of required shear strength
Compute the value of required shear
Using the curves in the table
Values obtained are shown below,
By interpolation determine the value of
Use the value
Compute the value required to shear strength from the left end,
Compute the value of required shear
Values obtained are shown blow,
By interpolation we get the value of
Use the value
Calculate to shear strength from the left end.
Calculate shear
Values obtained are shown blow,
By interpolation calculate the value of
Use the value
We can use next stiffener will be used at
Calculate distance remaining concentrated load.
Calculate shear strength
Calculate the required shear
Conclusion:
Therefore, girder size of
Want to see more full solutions like this?
Chapter 10 Solutions
Bundle: Steel Design, Loose-leaf Version, 6th + Mindtap Engineering, 1 Term (6 Months) Printed Access Card
- 6. A lake with no outlet is fed by a river with a constant flow of 1200 ft3/s. Water evaporates from the surface at a constant rate of 13 ft3/s per square mile of surface area. The surface area varies with the depth h (in feet) as A (square miles) = 4.5 + 5.5h. What is the equilibrium depth of the lake? Below what river discharge (volume flow rate) will the lake dry up?arrow_forwardProblem 5 (A, B, C and D are fixed). Find the reactions at A and D 8 k B 15 ft A -20 ft C 10 ft Darrow_forwardProblem 4 (A, B, E, D and F are all pin connected and C is fixed) Find the reactions at A, D and F 8 m B 6m E 12 kN D F 4 marrow_forward
- Problem 1 (A, C and D are pins) Find the reactions and A, C and D. D 6 m B 12 kN/m 8 m A C 6 marrow_forwardUniform Grade of Pipe Station of Point A is 9+50.00. Elevation Point A = 250.75.Station of Point B is 13+75.00. Elevation Point B = 244.10 1) Calculate flowline of pipe elevations at every 50 ft. interval (Half Station). 2) Tabulate station and elevation for each station like shown on example 3) Draw Sketcharrow_forward40m 150N B 40marrow_forward
- Note: Please accurately answer it!. I'll give it a thumbs up or down based on the answer quality and precision. Question: What is the group name of Sample B in problem 3 from the image?. By also using the ASTM flow chart!. This unit is soil mechanics btwarrow_forwardPick the rural location of a project site in Victoria, and its catchment area-not bigger than 25 sqkm, and given the below information, determine the rainfall intensity for ARI = 5, 50, 100 year storm event. Show all the details of the procedure. Each student must propose different length of streams and elevations. Use fig below as a sample only. Pt. E-ht. 95.0 200m 600m PLD-M. 91.0 300m Pt. C-93.0 300m PL.B-ht. 92.0 PL.F-ht. 96.0 500m Pt. A-M. 91.00 To be deemed satisfactory the solution must include: Q.F1.1.Choice of catchment location Q.F1.2. A sketch displaying length of stream and elevation Q.F1.3. Catchment's IFD obtained from the Buro of Metheorology for specified ARI Q.F1.4.Calculation of the time of concentration-this must include a detailed determination of the equivalent slope. Q.F1.5.Use must be made of the Bransby-Williams method for the determination of the equivalent slope. Q.F1.6.The graphical display of the estimation of intensities for ARI 5,50, 100 must be shown.arrow_forwardQUANTITY SURVEYINGarrow_forward
- Steel Design (Activate Learning with these NEW ti...Civil EngineeringISBN:9781337094740Author:Segui, William T.Publisher:Cengage Learning