Zapato Company produces two types of boots: vaquero and vaquera. There are four activities associated with the two products. Drivers for the four activities are as follows:   Vaquero Vaquera Cutting hours 4,000   5,900   Assembly hours 2,650   4,750   Inspection hours 945   2,390   Rework hours 200   600   The following activity data have been collected: Cutting $277,200 Assembling $222,000 Inspecting $53,360 Reworking $48,000 This information has been collected in the Microsoft Excel Online file. Open the spreadsheet, perform the required analysis, and input your answers in the question below.

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter4: Activity-based Costing
Section: Chapter Questions
Problem 8CE: Electan Company produces two types of printers. The company uses ABC, and all activity drivers are...
icon
Related questions
Topic Video
Question
100%

Activity Rates

Zapato Company produces two types of boots: vaquero and vaquera. There are four activities associated with the two products. Drivers for the four activities are as follows:

  Vaquero Vaquera
Cutting hours 4,000   5,900  
Assembly hours 2,650   4,750  
Inspection hours 945   2,390  
Rework hours 200   600  

The following activity data have been collected:

Cutting $277,200
Assembling $222,000
Inspecting $53,360
Reworking $48,000

This information has been collected in the Microsoft Excel Online file. Open the spreadsheet, perform the required analysis, and input your answers in the question below.

 

Calculate the activity rates that would be used to assign costs to each product. If required, round your answers to the nearest cent.
Cutting
per Cutting hour
Assembling
per Assembling hour
Inspecting
$
per Inspecting hour
Reworking
$
per Reworking hour
Transcribed Image Text:Calculate the activity rates that would be used to assign costs to each product. If required, round your answers to the nearest cent. Cutting per Cutting hour Assembling per Assembling hour Inspecting $ per Inspecting hour Reworking $ per Reworking hour
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning