Your task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided. Project 1 Activity Immediate Predecessor Duration A none 3 A 4 none D none 2 E D 5 F B, C, E 2 Project 2 Activity Immediate Predecessor Duration A none 6 B none 3 A D B 5 B 4 F D G E 8

Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
icon
Related questions
Question
Your task for this assignment is to create a network diagram for two projects. The activity,
immediate predecessor and duration are given. You are to layout-long-hand or using some
software-a network diagram for each project. For each diagram conduct a forward and
backward pass, calculate the slack, and identify the critical path. When noting your early start,
early finish, late start, late finish and slack, please use the format provided.
Project 1
Activity
Immediate Predecessor
Duration
A
none
3
В
A
4
none
6
D
none
2
D
5
F
В, С, Е
2
Project 2
Activity
Immediate Predecessor
Duration
A
none
6
B
none
3
A
9
B
E
в
4
D
2
G
E
8.
*Note: please use this format.
Early
Start
Duration Early
Finish
Activity
Float
Late
Start
Late
Finish
Transcribed Image Text:Your task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided. Project 1 Activity Immediate Predecessor Duration A none 3 В A 4 none 6 D none 2 D 5 F В, С, Е 2 Project 2 Activity Immediate Predecessor Duration A none 6 B none 3 A 9 B E в 4 D 2 G E 8. *Note: please use this format. Early Start Duration Early Finish Activity Float Late Start Late Finish
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 10 steps with 8 images

Blurred answer
Knowledge Booster
Phases of web development
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Database System Concepts
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education