You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president asked you to review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find the company has never used a flexible budget, and you suggest preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you estimated the following cost formulas and gathered the following actual cost data for March: Utilities. Maintenance Supplies. Indirect labor Depreciation O Cost Formula $16,200+ $0.17 per machine-hour $38,300+ $1.80 per machine-hour $0.80 per machine-hour $94,500+ $1.40 per machine-hour $67,800 Actual Cost in March $ 21,230 $ 66,300 $ 15,000 $ 122,000 $ 69,500 During March, the company worked 17,000 machine-hours and produced 11,000 units. The company originally planned to work 19,000 machine-hours during March. Required: 1. Calculate the activity variances for March. 2. Calculate the spending variances for March.
You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president asked you to review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find the company has never used a flexible budget, and you suggest preparing such a budget would be an excellent first step in overhead planning and control. After much effort and analysis, you estimated the following cost formulas and gathered the following actual cost data for March: Utilities. Maintenance Supplies. Indirect labor Depreciation O Cost Formula $16,200+ $0.17 per machine-hour $38,300+ $1.80 per machine-hour $0.80 per machine-hour $94,500+ $1.40 per machine-hour $67,800 Actual Cost in March $ 21,230 $ 66,300 $ 15,000 $ 122,000 $ 69,500 During March, the company worked 17,000 machine-hours and produced 11,000 units. The company originally planned to work 19,000 machine-hours during March. Required: 1. Calculate the activity variances for March. 2. Calculate the spending variances for March.
Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter8: Budgeting For Planning And Control
Section: Chapter Questions
Problem 40P: The controller for Muir Companys Salem plant is analyzing overhead in order to determine appropriate...
Related questions
Concept explainers
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Topic Video
Question
Complète both requirement asap please

Transcribed Image Text:Complete this question by entering your answers in the tabs below.
Required 1 Required 2
Calculate the activity variances for March.
Note: Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e.,
zero variance). Input all amounts as positive values.
FAB Corporation
Activity Variances
For the Month Ended March 31
164,890 X F
68,900 None
13,600 X U
118,300 X F
67,800 X U
$ 433,490 X F
Utilities
Maintenance
Supplies
Indirect labor
Depreciation
Total
Answer is not complete.
X
X
✓
X
>

Transcribed Image Text:You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president
asked you to review the company's costing system and "do what you can to help us get better control of our manufacturing overhead
costs." You find the company has never used a flexible budget, and you suggest preparing such a budget would be an excellent first
step in overhead planning and control.
After much effort and analysis, you estimated the following cost formulas and gathered the following actual cost data for March:
Utilities
Maintenance
Supplies
Indirect labor
Depreciation
Cost Formula
$16,200+ $0.17 per machine-hour
$38,300+ $1.80 per machine-hour
$0.80 per machine-hour
$94,500+ $1.40 per machine-hour
$67,800
Required:
1. Calculate the activity variances for March.
2. Calculate the spending variances for March.
Actual Cost
in March
$ 21, 230
$ 66,300
$ 15,000
During March, the company worked 17,000 machine-hours and produced 11,000 units. The company originally planned to work 19,000
machine-hours during March.
$ 122,000
$ 69,500
Required 1 Required 2
X Answer is not complete.
Complete this question by entering your answers in the tabs below.
Calculate the activity variances for March.
Note: Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e.,
zero variance). Input all amounts as positive values.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you

Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning

Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning