You have 3 projects with the following cash flows: (Click on the following icon o in order to copy its contents into a spreadsheet) Year 1 2 3 4 Project 1 Project 2 Project 3 -$151 - 827 21 $21 $40 $59 $81 7,008 80 -6,502 -243 40 59 a. For which of these projects is the IRR rule reliable? b. Estimate the IRR for each project (to the nearest 1%). c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%? a. For which of these projects is the IRR rule reliable? (Select from the drop-down menus.) The IRR rule is reliable for| V Unless all of the V cash flows of the project precede the V ones, the IRR rule may give the wrong answer and should not be used. Furthermore, there may be multiple IRRS or the IRR may not exist b. Estimate the IRR for each project (to the nearest 1%). The IRR for project 1 is%. (Round to the nearest integer) The IRR for project 2 is%. (Round to the nearest integer) The IRR for project 3 is%. (Round to the nearest integer.) c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%? The NPV for project 1 for a cost of capital of 5% is S (Round to the nearest cent.) The NPV for project 1 for a cost of capital of 20% is S (Round to the nearest cent) The NPV for project 1 for a cost of capital of 50% is S (Round to the nearest cent) The NPV for project 2 for a cost of capital of 5% is s (Round to the nearest cent) The NPV for project 2 for a cost of capital of 20% is. (Round to the nearest cent.) The NPV for project 2 for a cost of capital of 50% is S (Round to the nearest cent) The NPV for project 3 for a cost of capital of 5% is S. (Round to the nearest cent) The NPV for project 3 for a cost of capital of 20% is S (Round to the nearest cent)
You have 3 projects with the following cash flows: (Click on the following icon o in order to copy its contents into a spreadsheet) Year 1 2 3 4 Project 1 Project 2 Project 3 -$151 - 827 21 $21 $40 $59 $81 7,008 80 -6,502 -243 40 59 a. For which of these projects is the IRR rule reliable? b. Estimate the IRR for each project (to the nearest 1%). c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%? a. For which of these projects is the IRR rule reliable? (Select from the drop-down menus.) The IRR rule is reliable for| V Unless all of the V cash flows of the project precede the V ones, the IRR rule may give the wrong answer and should not be used. Furthermore, there may be multiple IRRS or the IRR may not exist b. Estimate the IRR for each project (to the nearest 1%). The IRR for project 1 is%. (Round to the nearest integer) The IRR for project 2 is%. (Round to the nearest integer) The IRR for project 3 is%. (Round to the nearest integer.) c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%? The NPV for project 1 for a cost of capital of 5% is S (Round to the nearest cent.) The NPV for project 1 for a cost of capital of 20% is S (Round to the nearest cent) The NPV for project 1 for a cost of capital of 50% is S (Round to the nearest cent) The NPV for project 2 for a cost of capital of 5% is s (Round to the nearest cent) The NPV for project 2 for a cost of capital of 20% is. (Round to the nearest cent.) The NPV for project 2 for a cost of capital of 50% is S (Round to the nearest cent) The NPV for project 3 for a cost of capital of 5% is S. (Round to the nearest cent) The NPV for project 3 for a cost of capital of 20% is S (Round to the nearest cent)
Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
Related questions
Question
![You have 3 projects with the following cash flows: (Click on the following icon in order to copy its contents into a spreadsheet.)
Year
1
4
Project 1
Project 2
Project 3
- $151
$21
$40
$59
$81
- 827
7,008
- 6,502
21
40
59
80
- 243
a. For which of these projects is the IRR rule reliable?
b. Estimate the IRR for each project (to the nearest 1%).
c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%?
a. For which of these projects is the IRR rule reliable? (Select from the drop-down menus.)
The IRR rule is reliable for
V. Unless all of the
cash flows of the project precede the
ones, the IRR rule may give the wrong answer and should not be used. Furthermore, there may be multiple IRRS or the IRR may not exist.
b. Estimate the IRR for each project (to the nearest 1%).
The IRR for project 1 is %. (Round to the nearest integer.)
The IRR for project 2 is %. (Round to the nearest integer.)
The IRR for project 3 is %. (Round to the nearest integer.)
c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%?
The NPV for project 1 for a cost of capital of 5% is S
(Round to the nearest cent.)
The NPV for project 1 for a cost of capital of 20% is $
(Round to the nearest cent.)
The NPV for project 1 for a cost of capital of 50% is S
(Round to the nearest cent.)
The NPV for project 2 for a cost of capital of 5% is S
(Round to the nearest cent.)
The NPV for project 2 for a cost of capital of 20% is. (Round to the nearest cent.)
The NPV for project 2 for a cost of capital of 50% is $
(Round to the nearest cent.)
The NPV for project 3 for a cost of capital of 5% is S. (Round to the nearest cent.)
The NPV for project 3 for a cost of capital of 20% is $
(Round to the nearest cent.)](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Ffe591e3e-c1e9-4180-ad99-642a1f427277%2F0533a720-54a6-4a60-886f-d792e3b0a985%2Fhujrknr_processed.png&w=3840&q=75)
Transcribed Image Text:You have 3 projects with the following cash flows: (Click on the following icon in order to copy its contents into a spreadsheet.)
Year
1
4
Project 1
Project 2
Project 3
- $151
$21
$40
$59
$81
- 827
7,008
- 6,502
21
40
59
80
- 243
a. For which of these projects is the IRR rule reliable?
b. Estimate the IRR for each project (to the nearest 1%).
c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%?
a. For which of these projects is the IRR rule reliable? (Select from the drop-down menus.)
The IRR rule is reliable for
V. Unless all of the
cash flows of the project precede the
ones, the IRR rule may give the wrong answer and should not be used. Furthermore, there may be multiple IRRS or the IRR may not exist.
b. Estimate the IRR for each project (to the nearest 1%).
The IRR for project 1 is %. (Round to the nearest integer.)
The IRR for project 2 is %. (Round to the nearest integer.)
The IRR for project 3 is %. (Round to the nearest integer.)
c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%?
The NPV for project 1 for a cost of capital of 5% is S
(Round to the nearest cent.)
The NPV for project 1 for a cost of capital of 20% is $
(Round to the nearest cent.)
The NPV for project 1 for a cost of capital of 50% is S
(Round to the nearest cent.)
The NPV for project 2 for a cost of capital of 5% is S
(Round to the nearest cent.)
The NPV for project 2 for a cost of capital of 20% is. (Round to the nearest cent.)
The NPV for project 2 for a cost of capital of 50% is $
(Round to the nearest cent.)
The NPV for project 3 for a cost of capital of 5% is S. (Round to the nearest cent.)
The NPV for project 3 for a cost of capital of 20% is $
(Round to the nearest cent.)
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Essentials Of Investments](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781260013924/9781260013924_smallCoverImage.jpg)
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
![FUNDAMENTALS OF CORPORATE FINANCE](https://www.bartleby.com/isbn_cover_images/9781260013962/9781260013962_smallCoverImage.gif)
![Financial Management: Theory & Practice](https://www.bartleby.com/isbn_cover_images/9781337909730/9781337909730_smallCoverImage.gif)
![Essentials Of Investments](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781260013924/9781260013924_smallCoverImage.jpg)
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
![FUNDAMENTALS OF CORPORATE FINANCE](https://www.bartleby.com/isbn_cover_images/9781260013962/9781260013962_smallCoverImage.gif)
![Financial Management: Theory & Practice](https://www.bartleby.com/isbn_cover_images/9781337909730/9781337909730_smallCoverImage.gif)
![Foundations Of Finance](https://www.bartleby.com/isbn_cover_images/9780134897264/9780134897264_smallCoverImage.gif)
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
![Fundamentals of Financial Management (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337395250/9781337395250_smallCoverImage.gif)
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
![Corporate Finance (The Mcgraw-hill/Irwin Series i…](https://www.bartleby.com/isbn_cover_images/9780077861759/9780077861759_smallCoverImage.gif)
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education