You are working on a bid to build two city parks a year for the next three years. This project requires the purchase of $185,000 of equipment that will be depreciated using straight-line depreciation to a zero book value over the 3-year project life. The equipment can be sold at the end of the project for $34,000. You will also need $20,000 in net working capital for the duration of the project. The fixed costs will be $18,000 a year and the variable costs will be $168,000 per park. Your required rate of return is 15 percent and your tax rate is 34 percent. What is the minimal amount you should bid per park?

Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
icon
Related questions
icon
Concept explainers
Topic Video
Question
You are working on a bid to build two city parks a year for the next three years. This project requires the purchase of $185,000 of
equipment that will be depreciated using straight-line depreciation to a zero book value over the 3-year project life. The equipment
can be sold at the end of the project for $34,000. You will also need $20,000 in net working capital for the duration of the project.
The fixed costs will be $18,000 a year and the variable costs will be $168,000 per park. Your required rate of return is 15 percent and
your tax rate is 34 percent. What is the minimal amount you should bid per park?
A $128,600
B $154,300
C) $72,500
E
$219,900
$189,100
Transcribed Image Text:You are working on a bid to build two city parks a year for the next three years. This project requires the purchase of $185,000 of equipment that will be depreciated using straight-line depreciation to a zero book value over the 3-year project life. The equipment can be sold at the end of the project for $34,000. You will also need $20,000 in net working capital for the duration of the project. The fixed costs will be $18,000 a year and the variable costs will be $168,000 per park. Your required rate of return is 15 percent and your tax rate is 34 percent. What is the minimal amount you should bid per park? A $128,600 B $154,300 C) $72,500 E $219,900 $189,100
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Capital Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Essentials Of Investments
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
FUNDAMENTALS OF CORPORATE FINANCE
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:
9781260013962
Author:
BREALEY
Publisher:
RENT MCG
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Foundations Of Finance
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education