You are within two weeks of turnover of a three-story build-to-suit office building project. Many of the city inspections are complete and it appears that a certificate of occupancy (C of O) will be obtained on time. Only the fire protection, elevator, and life safety inspections remain. The mechanical, electrical, fire protection and life safety were all design-build systems. During the punch list, it is discovered that the fire protection subcontractor has installed a different type of sprinkler head on each floor. The first floor uses concealed heads with white escutcheons to match the ceiling tiles. The second floor uses decorative chrome heads. The subcontractor installed semi-recessed heads on the third floor. This was not picked up prior as a person cannot physically see more than one floor at a time. The client is very upset. QUESTION: Can you require the subcontractor to change them all out now? Would this be a good move given the status of the inspections? What should the general contractor have done to prevent this from happening? What can you do now?

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question

SITUATION 2: You are within two weeks of turnover of a three-story build-to-suit office building project. Many of the city inspections are complete and it appears that a certificate of occupancy (C of O) will be obtained on time. Only the fire protection, elevator, and life safety inspections remain. The mechanical, electrical, fire protection and life safety were all design-build systems. During the punch list, it is discovered that the fire protection subcontractor has installed a different type of sprinkler head on each floor. The first floor uses concealed heads with white escutcheons to match the ceiling tiles. The second floor uses decorative chrome heads. The subcontractor installed semi-recessed heads on the third floor. This was not picked up prior as a person cannot physically see more than one floor at a time. The client is very upset.

QUESTION: Can you require the subcontractor to change them all out now? Would this be a good move given the status of the inspections? What should the general contractor have done to prevent this from happening? What can you do now?

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Methods to determine productivity
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning