Why is it essential to specify CPM for the project?
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Why is it essential to specify CPM for the project?
Expert Solution
Step 1
The Critical Path Method ( CPM) is a technique of project modelling which project managers use to identify the relevant deadlines and complete a project on time.
Step 2
The critical path in a project is the greatest distance from start to finish, along with all the activities and their duration.
Step 3
To find this, project managers use the CPM method to identify the minimum amount of time it takes to complete each job with the least slack.
Step by step
Solved in 6 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning