White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined overhead rate in each department. The Cutting Department bases its rate on machine-hours, and the Finishing Department bases its rate on direct labor-hours. At the beginning of the year, the company made the following estimates: Department Cutting Finishing Direct labor-hours 8,400 84,000 Machine-hours 65,600 1,000 Total fixed manufacturing overhead cost $ 390,000 $ 482,000 Variable manufacturing overhead per machine-hour $ 3.00 — Variable manufacturing overhead per direct labor-hour — $ 2.75 Required: 1. Compute the predetermined overhead rate for each department. 2. The job cost sheet for Job 203, which was started and completed during the year, showed the following: Department Cutting Finishing Direct labor-hours 6 18 Machine-hours 87 3 Direct materials $ 730 $ 360 Direct labor cost $ 132 $ 396 Using the predetermined overhead rates that you computed in requirement (1), compute the total manufacturing cost assigned to Job 203. 3. Would you expect substantially different amounts of overhead cost to be assigned to some jobs if the company used a plantwide predetermined overhead rate based on direct labor-hours, rather than using departmental rates?
White Company has two departments, Cutting and Finishing. The company uses a job-order costing system and computes a predetermined
Department | ||||
Cutting | Finishing | |||
Direct labor-hours | 8,400 | 84,000 | ||
Machine-hours | 65,600 | 1,000 | ||
Total fixed manufacturing overhead cost | $ | 390,000 | $ | 482,000 |
Variable manufacturing overhead per machine-hour | $ | 3.00 | — | |
Variable manufacturing overhead per direct labor-hour | — | $ | 2.75 | |
Required:
1. Compute the predetermined overhead rate for each department.
2. The
Department | ||||||||
Cutting | Finishing | |||||||
Direct labor-hours | 6 | 18 | ||||||
Machine-hours | 87 | 3 | ||||||
Direct materials | $ | 730 | $ | 360 | ||||
Direct labor cost | $ | 132 | $ | 396 | ||||
Using the predetermined overhead rates that you computed in requirement (1), compute the total
3. Would you expect substantially different amounts of overhead cost to be assigned to some jobs if the company used a plantwide predetermined overhead rate based on direct labor-hours, rather than using departmental rates?