weeks at a cost of less than P75,100 in direct cost? From the following data, perform crashing the project. Cost ILLUSTRATION 8-3 Cost Crash 10,000 7,000 3,200 10,0000 5,200 14,000 8,100 9,600 8,000 per week 2,000 Time in Weeks Normal Normal Crash Activity 1-2-(A) 1-3-(B) 2-4-(C) 3-4-(D) 3-5-(E) 4-6-(F) 5-6-(G) 5-7-(H) 6-7-(i) 2,000 4,000 2,000 8,000 2,000 10,000 6,000 6,000 4,000 6. 600 400 8 500 12 8 800 2,000 7. 3 3 1 700 900 11 1,000 10 6. Total 33 18 P44,000 P75,100 Č=7 F = 3 4 A = 6 D= 12 G = 5 |= 10 3 B= 8 E = 7 H = 11 FIGURE 8-5 The normal time Critical Path B-D-F-I is equal to 33 weekS. Direct cost is.....P 44,000 Question: Can we finish the project in 18 weeks instead of 35 weeks at a cost of less than P75,100 in direct cost? SOLUTION: 234
weeks at a cost of less than P75,100 in direct cost? From the following data, perform crashing the project. Cost ILLUSTRATION 8-3 Cost Crash 10,000 7,000 3,200 10,0000 5,200 14,000 8,100 9,600 8,000 per week 2,000 Time in Weeks Normal Normal Crash Activity 1-2-(A) 1-3-(B) 2-4-(C) 3-4-(D) 3-5-(E) 4-6-(F) 5-6-(G) 5-7-(H) 6-7-(i) 2,000 4,000 2,000 8,000 2,000 10,000 6,000 6,000 4,000 6. 600 400 8 500 12 8 800 2,000 7. 3 3 1 700 900 11 1,000 10 6. Total 33 18 P44,000 P75,100 Č=7 F = 3 4 A = 6 D= 12 G = 5 |= 10 3 B= 8 E = 7 H = 11 FIGURE 8-5 The normal time Critical Path B-D-F-I is equal to 33 weekS. Direct cost is.....P 44,000 Question: Can we finish the project in 18 weeks instead of 35 weeks at a cost of less than P75,100 in direct cost? SOLUTION: 234
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
100%
![PROJEC
ILLUSTRATION 8-3
From the following data, perform crashing the project.
Cost
Cost
Time in Weeks
Normal
Crash
Crash
10,000
7,000
3,200
10,0000
5,200
14,000
8,100
9,600
8,000
per week
2,000
Normal
2,000
4,000
2,000
8,000
Activity
1-2-(A)
1-3-(B)
2-4-(C)
3-4-(D)
3-5-(E)
4-6-(F)
5-6-(G)
5-7-(H)
6-7-(i)
600
8
400
7.
4.
500
800
2,000
12
2,000
10,000
6,000
6,000
4,000
7.
3.
700
900
11
1,000
10
6.
Total
33
18
P44,000
P75,100
Č=7
F = 3
A = 6
D= 12
G = 5
| = 10
B= 8
E = 7
H = 11
FIGURE 8-5
The normal time Critical Path B-D-F-I is equal to 33 weekS.
Direct cost is .....P 44,000
Question: Can we finish the project in 18 weeks instead of 35
weeks at a cost of less than P75,100 in direct cost?
SOLUTION:
1. Determine the different path lengths and identify the cine
cal path.
190](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fbbb9cac7-e718-419e-9e46-079cbf1a0013%2F788d619e-4a77-4f5b-9692-8f6484d63d2a%2F1fri2nd_processed.jpeg&w=3840&q=75)
Transcribed Image Text:PROJEC
ILLUSTRATION 8-3
From the following data, perform crashing the project.
Cost
Cost
Time in Weeks
Normal
Crash
Crash
10,000
7,000
3,200
10,0000
5,200
14,000
8,100
9,600
8,000
per week
2,000
Normal
2,000
4,000
2,000
8,000
Activity
1-2-(A)
1-3-(B)
2-4-(C)
3-4-(D)
3-5-(E)
4-6-(F)
5-6-(G)
5-7-(H)
6-7-(i)
600
8
400
7.
4.
500
800
2,000
12
2,000
10,000
6,000
6,000
4,000
7.
3.
700
900
11
1,000
10
6.
Total
33
18
P44,000
P75,100
Č=7
F = 3
A = 6
D= 12
G = 5
| = 10
B= 8
E = 7
H = 11
FIGURE 8-5
The normal time Critical Path B-D-F-I is equal to 33 weekS.
Direct cost is .....P 44,000
Question: Can we finish the project in 18 weeks instead of 35
weeks at a cost of less than P75,100 in direct cost?
SOLUTION:
1. Determine the different path lengths and identify the cine
cal path.
190
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning