VALEDICTION Construction Co. entered into a P80M fixed price contract for the construction of a private road for FAREWELL SPEECH, Inc. The performance obligation on the contract is satisfied over time. VALEDICTION measures its progress on the contract using the "cost- to-cost" method. The estimated total contract cost is P40M. The following were the actual costs incurred by VALEDICTION during the first year of the construction: 400,000 12,000,000 2,000,000 4,000,000 800,000 480,000 240,000 160,000 560,000 80,000 Costs of negotiating the contract (charged immediately as expense) Costs of materials used in construction Costs of materials purchased but not yet used in construction Site labor costs Site supervision costs Depreciation of equipment used in construction Depreciation of idle construction equipment Costs of moving plant, equipment and materials to and from the contract site Costs of hiring plant and equipment Advance payments to subcontractors (subcontracted work is not yet started)

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

1. Determine the amount of construction in progress that will be reported.

2. How much revenue is recognized as of the end of the first year?

VALEDICTION Construction Co. entered into a P80M fixed price contract for the construction of a private road for FAREWELL SPEECH,
Inc. The performance obligation on the contract is satisfied over time. VALEDICTION measures its progress on the contract using the "cost-
to-cost" method. The estimated total contract cost is P40M. The following were the actual costs incurred by VALEDICTION during the first
year of the construction:
400,000
12,000,000
2,000,000
4,000,000
800,000
480,000
240,000
160,000
560,000
80,000
Costs of negotiating the contract (charged immediately as expense)
Costs of materials used in construction
Costs of materials purchased but not yet used in construction
Site labor costs
Site supervision costs
Depreciation of equipment used in construction
Depreciation of idle construction equipment
Costs of moving plant, equipment and materials to and from the contract site
Costs of hiring plant and equipment
Advance payments to subcontractors (subcontracted work is not yet started)
Transcribed Image Text:VALEDICTION Construction Co. entered into a P80M fixed price contract for the construction of a private road for FAREWELL SPEECH, Inc. The performance obligation on the contract is satisfied over time. VALEDICTION measures its progress on the contract using the "cost- to-cost" method. The estimated total contract cost is P40M. The following were the actual costs incurred by VALEDICTION during the first year of the construction: 400,000 12,000,000 2,000,000 4,000,000 800,000 480,000 240,000 160,000 560,000 80,000 Costs of negotiating the contract (charged immediately as expense) Costs of materials used in construction Costs of materials purchased but not yet used in construction Site labor costs Site supervision costs Depreciation of equipment used in construction Depreciation of idle construction equipment Costs of moving plant, equipment and materials to and from the contract site Costs of hiring plant and equipment Advance payments to subcontractors (subcontracted work is not yet started)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Borrowing costs
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education