Using the sequential method, Pone Hill Company allocates Janitorial Department costs based on square footage serviced. It allocates Cafeteria Department costs based on the number of employees served. It has determined to allocate Janitorial costs before Cafeteria costs. It has the following information about its two service departments and two production departments, Cutting and Assembly: Costs Square Feet Number of Employees Janitorial Department $450,000 100 20 Cafeteria Department 200,000 10,000 10 Cutting Department 1,500,000 2,000 60 Assembly Department 3,000,000 8,000 20 How much of the Janitorial Department's $450,000 costs is allocated to the Cutting Department?
Process Costing
Process costing is a sort of operation costing which is employed to determine the value of a product at each process or stage of producing process, applicable where goods produced from a series of continuous operations or procedure.
Job Costing
Job costing is adhesive costs of each and every job involved in the production processes. It is an accounting measure. It is a method which determines the cost of specific jobs, which are performed according to the consumer’s specifications. Job costing is possible only in businesses where the production is done as per the customer’s requirement. For example, some customers order to manufacture furniture as per their needs.
ABC Costing
Cost Accounting is a form of managerial accounting that helps the company in assessing the total variable cost so as to compute the cost of production. Cost accounting is generally used by the management so as to ensure better decision-making. In comparison to financial accounting, cost accounting has to follow a set standard ad can be used flexibly by the management as per their needs. The types of Cost Accounting include – Lean Accounting, Standard Costing, Marginal Costing and Activity Based Costing.
Using the sequential method, Pone Hill Company allocates Janitorial Department costs based on square footage serviced. It allocates Cafeteria Department costs based on the number of employees served. It has determined to allocate Janitorial costs before Cafeteria costs.
It has the following information about its two service departments and two production departments, Cutting and Assembly:
Costs | Square Feet | Number of Employees |
|
Janitorial Department | $450,000 | 100 | 20 |
Cafeteria Department | 200,000 | 10,000 | 10 |
Cutting Department | 1,500,000 | 2,000 | 60 |
Assembly Department | 3,000,000 | 8,000 | 20 |
How much of the Janitorial Department's $450,000 costs is allocated to the Cutting Department?
Trending now
This is a popular solution!
Step by step
Solved in 2 steps