Using PERT, Ed Rose was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months and the project variance is 4. What is the probability that the project will be completed in 17 months or less? What is the probability that the project will be completed in 20 months or less? What is the probability that the project will be completed in 23 months or less? What is the probability that the project will be completed in 25 months or less?
Contingency Table
A contingency table can be defined as the visual representation of the relationship between two or more categorical variables that can be evaluated and registered. It is a categorical version of the scatterplot, which is used to investigate the linear relationship between two variables. A contingency table is indeed a type of frequency distribution table that displays two variables at the same time.
Binomial Distribution
Binomial is an algebraic expression of the sum or the difference of two terms. Before knowing about binomial distribution, we must know about the binomial theorem.
Using PERT, Ed Rose was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months and the project variance is 4.
-
What is the
probability that the project will be completed in 17 months or less? -
What is the probability that the project will be completed in 20 months or less?
-
What is the probability that the project will be completed in 23 months or less?
-
What is the probability that the project will be completed in 25 months or less?