Tulsa Company is considering investing in new bottling equipment and has two options: Option A has a lower initial cost but would require a significant expenditure to rebuild the machine after four years; Option B has higher maintenance costs but also has a higher salvage value at the end of its useful life. Tulsa's cost of capital is 11 percent. The following estimates of the cash flows were developed by Tulsa's controller: Initial investment Annual cash inflows. Annual cash outflows Costs to rebuild Salvage value Estimated useful life Required 1 Required 2 Required: 1. Calculate NPV. (Future Value of $1,Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) 2. Determine which option Tulsa should select? Option A: Complete this question by entering your answers in the tabs below. Initial Investment Annual Cash Flows Cost to Rebuild Salvage Net Present Value Option B: Initial Investment Annual Cash Flows Cost to Rebuild Salvage Net Present Value Calculate NPV. (Future Value of $1,Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) Note: Use appropriate factor(s) from the tables provided. Negative amounts should be indicated by a minus sign. Round your "Present Values" to 2 decimal places. Year Option A $ 320,000 150,000 70,000 120,000 0 1-8 4 8 0 8 years Year 0 1-8 4 8 Option B $ 454,000 160,000 75,000 0 Cash Flows 24,000 8 years Cash Flows < Required 1 PV factor PV factor 11% 11% Present Value Present Value Required 2 >
Tulsa Company is considering investing in new bottling equipment and has two options: Option A has a lower initial cost but would require a significant expenditure to rebuild the machine after four years; Option B has higher maintenance costs but also has a higher salvage value at the end of its useful life. Tulsa's cost of capital is 11 percent. The following estimates of the cash flows were developed by Tulsa's controller: Initial investment Annual cash inflows. Annual cash outflows Costs to rebuild Salvage value Estimated useful life Required 1 Required 2 Required: 1. Calculate NPV. (Future Value of $1,Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) 2. Determine which option Tulsa should select? Option A: Complete this question by entering your answers in the tabs below. Initial Investment Annual Cash Flows Cost to Rebuild Salvage Net Present Value Option B: Initial Investment Annual Cash Flows Cost to Rebuild Salvage Net Present Value Calculate NPV. (Future Value of $1,Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.) Note: Use appropriate factor(s) from the tables provided. Negative amounts should be indicated by a minus sign. Round your "Present Values" to 2 decimal places. Year Option A $ 320,000 150,000 70,000 120,000 0 1-8 4 8 0 8 years Year 0 1-8 4 8 Option B $ 454,000 160,000 75,000 0 Cash Flows 24,000 8 years Cash Flows < Required 1 PV factor PV factor 11% 11% Present Value Present Value Required 2 >
Chapter10: Capital Budgeting: Decision Criteria And Real Option
Section10.A: Mutually Exclusive Investments Having Unequal Lives
Problem 4P
Related questions
Question
Please do not give solution in image format thanku
![=
Tulsa Company is considering investing in new bottling equipment and has two options: Option A has a lower initial cost but would
require a significant expenditure to rebuild the machine after four years; Option B has higher maintenance costs but also has a higher
salvage value at the end of its useful life. Tulsa's cost of capital is 11 percent. The following estimates of the cash flows were developed
by Tulsa's controller:
Initial investment
Annual cash inflows
Annual cash outflows
Costs to rebuild
Salvage value
Estimated useful life
Required 1 Required 2
Required:
1. Calculate NPV. (Future Value of $1,Present Value of $1. Future Value Annuity of $1, Present Value Annuity of $1.)
2. Determine which option Tulsa should select?
Complete this question by entering your answers in the tabs below.
Option A:
Initial Investment
Annual Cash Flows
Cost to Rebuild
Salvage
Net Present Value
Option B:
Calculate NPV. (Future Value of $1,Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.)
Note: Use appropriate factor(s) from the tables provided. Negative amounts should be indicated by a minus sign. Round your
"Present Values" to 2 decimal places.
Initial Investment
Annual Cash Flows
Cost to Rebuild
Salvage
Net Present Value
Year
Option A
$ 320,000
150,000
70,000
120,000
0
1-8
4
8
0
8 years
Year
0
1-8
4
8
Option B
$ 454,000
160,000
75,000
0
24,000
8 years
Cash Flows
Cash Flows
< Required 1
PV factor
PV factor
11%
11%
Present Value
Present Value
Required 2 >](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F3eeb2206-9ee8-46b0-ad5b-d8867fe9ecf8%2F8bfcce77-aee1-495a-8157-799c81c6fb71%2F99ybsd_processed.png&w=3840&q=75)
Transcribed Image Text:=
Tulsa Company is considering investing in new bottling equipment and has two options: Option A has a lower initial cost but would
require a significant expenditure to rebuild the machine after four years; Option B has higher maintenance costs but also has a higher
salvage value at the end of its useful life. Tulsa's cost of capital is 11 percent. The following estimates of the cash flows were developed
by Tulsa's controller:
Initial investment
Annual cash inflows
Annual cash outflows
Costs to rebuild
Salvage value
Estimated useful life
Required 1 Required 2
Required:
1. Calculate NPV. (Future Value of $1,Present Value of $1. Future Value Annuity of $1, Present Value Annuity of $1.)
2. Determine which option Tulsa should select?
Complete this question by entering your answers in the tabs below.
Option A:
Initial Investment
Annual Cash Flows
Cost to Rebuild
Salvage
Net Present Value
Option B:
Calculate NPV. (Future Value of $1,Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.)
Note: Use appropriate factor(s) from the tables provided. Negative amounts should be indicated by a minus sign. Round your
"Present Values" to 2 decimal places.
Initial Investment
Annual Cash Flows
Cost to Rebuild
Salvage
Net Present Value
Year
Option A
$ 320,000
150,000
70,000
120,000
0
1-8
4
8
0
8 years
Year
0
1-8
4
8
Option B
$ 454,000
160,000
75,000
0
24,000
8 years
Cash Flows
Cash Flows
< Required 1
PV factor
PV factor
11%
11%
Present Value
Present Value
Required 2 >
![es
Tulsa Company is considering investing in new bottling equipment and has two options: Option A has a lower initial cost but would
require a significant expenditure to rebuild the machine after four years; Option B has higher maintenance costs but also has a higher
salvage value at the end of its useful life. Tulsa's cost of capital is 11 percent. The following estimates of the cash flows were developed
by Tulsa's controller:
Initial investment
Annual cash inflows
Annual cash outflows
Costs to rebuild
Salvage value
Estimated useful life
Required 1
Option A
$ 320,000
150,000
70,000
120,000
Required 2
0
8 years
Required:
1. Calculate NPV. (Future Value of $1,Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.)
2. Determine which option Tulsa should select?
Determine which option Tulsa should select?
Determine which option Tulsa should select?
Complete this question by entering your answers in the tabs below.
Option B
$ 454,000
160,000
75,000
24,000
8 years
< Required 1
Required 2 >](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F3eeb2206-9ee8-46b0-ad5b-d8867fe9ecf8%2F8bfcce77-aee1-495a-8157-799c81c6fb71%2Fd9wyw1s_processed.png&w=3840&q=75)
Transcribed Image Text:es
Tulsa Company is considering investing in new bottling equipment and has two options: Option A has a lower initial cost but would
require a significant expenditure to rebuild the machine after four years; Option B has higher maintenance costs but also has a higher
salvage value at the end of its useful life. Tulsa's cost of capital is 11 percent. The following estimates of the cash flows were developed
by Tulsa's controller:
Initial investment
Annual cash inflows
Annual cash outflows
Costs to rebuild
Salvage value
Estimated useful life
Required 1
Option A
$ 320,000
150,000
70,000
120,000
Required 2
0
8 years
Required:
1. Calculate NPV. (Future Value of $1,Present Value of $1, Future Value Annuity of $1, Present Value Annuity of $1.)
2. Determine which option Tulsa should select?
Determine which option Tulsa should select?
Determine which option Tulsa should select?
Complete this question by entering your answers in the tabs below.
Option B
$ 454,000
160,000
75,000
24,000
8 years
< Required 1
Required 2 >
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
![EBK CONTEMPORARY FINANCIAL MANAGEMENT](https://www.bartleby.com/isbn_cover_images/9781337514835/9781337514835_smallCoverImage.jpg)
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
![Managerial Accounting: The Cornerstone of Busines…](https://www.bartleby.com/isbn_cover_images/9781337115773/9781337115773_smallCoverImage.gif)
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
![Cornerstones of Cost Management (Cornerstones Ser…](https://www.bartleby.com/isbn_cover_images/9781305970663/9781305970663_smallCoverImage.gif)
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
![EBK CONTEMPORARY FINANCIAL MANAGEMENT](https://www.bartleby.com/isbn_cover_images/9781337514835/9781337514835_smallCoverImage.jpg)
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
![Managerial Accounting: The Cornerstone of Busines…](https://www.bartleby.com/isbn_cover_images/9781337115773/9781337115773_smallCoverImage.gif)
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
![Cornerstones of Cost Management (Cornerstones Ser…](https://www.bartleby.com/isbn_cover_images/9781305970663/9781305970663_smallCoverImage.gif)
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
![Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781337912020/9781337912020_smallCoverImage.jpg)
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
![Financial And Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781337902663/9781337902663_smallCoverImage.jpg)
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College