You are given the following scenarios. Identify the problem related to the software crisis for a given scenario. The problem can be Time Slippage, Missed Requirements, Cost Slippage, Failure at the customer Site.
Scenario A: Software for financial systems was delivered to the customer. The customer informed the development team to make the verification of biometric but the developers implement in another way.
Scenario B: A polar the satellite launch vehicle was scheduled for the launch on August 15th. The auto-pilot of the rocket to be delivered for the integration of the rocket on may 15th. The design and development of the software for the auto-pilot required more effort than planned and they need to engage extra resources for more implementation.
Step by step
Solved in 2 steps