The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs 3 hours per unit at $0.78 per hour 3 hours per unit at $1.98 per hour Fixed overhead (based on 10,000 hours) Variable overhead Actual Costs Total variable cost, $17,800 Total fixed cost, $8,000 The variable factory overhead controllable variance is Oa. $1,168 favorable Ob. 50 Oc. $1,168 unfavorable Od. $934 favorable
Variance Analysis
In layman's terms, variance analysis is an analysis of a difference between planned and actual behavior. Variance analysis is mainly used by the companies to maintain a control over a business. After analyzing differences, companies find the reasons for the variance so that the necessary steps should be taken to correct that variance.
Standard Costing
The standard cost system is the expected cost per unit product manufactured and it helps in estimating the deviations and controlling them as well as fixing the selling price of the product. For example, it helps to plan the cost for the coming year on the various expenses.
Please do not give solution in image format thanku
Trending now
This is a popular solution!
Step by step
Solved in 3 steps