The production schedule at Mazda calls for 1,250 Mazdas to be produced during each of 22 production days in January and 1,050 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from the Gesundheit. The safety stock policy variable, a, is 0.08. The container (a delivery truck) size is 250 tires. The average waiting time plus material handling time is 0.50 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing per container in January is 0.50 day. February processing time will average 0.10 day per container. How many containers should be authorized for January? containers. (Enter your response rounded up to the next whole number.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The production schedule at Mazda calls for 1,250 Mazdas to be produced during each of 22 production days in January and 1,050 Mazdas to be produced
during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases
four tires per vehicle from the Gesundheit. The safety stock policy variable, a, is 0.08. The container (a delivery truck) size is 250 tires. The average waiting
time plus material handling time is 0.50 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing per
container in January is 0.50 day. February processing time will average 0.10 day per container.
How many containers should be authorized for January?
containers. (Enter your response rounded up to the next whole number.)
Transcribed Image Text:The production schedule at Mazda calls for 1,250 Mazdas to be produced during each of 22 production days in January and 1,050 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from the Gesundheit. The safety stock policy variable, a, is 0.08. The container (a delivery truck) size is 250 tires. The average waiting time plus material handling time is 0.50 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing per container in January is 0.50 day. February processing time will average 0.10 day per container. How many containers should be authorized for January? containers. (Enter your response rounded up to the next whole number.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question
The production schedule at Mazda calls for 1,250 Mazdas to be produced during each of 22 production days in January and 1,050 Mazdas to be produced
during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases
four tires per vehicle from the Gesundheit. The safety stock policy variable, a, is 0.08. The container (a delivery truck) size is 250 tires. The average waiting
time plus material handling time is 0.50 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing per
container in January is 0.50 day. February processing time will average 0.10 day per container.
How many containers should be authorized for January? 22 containers. (Enter your response rounded up to the next whole number.)
How many containers should be authorized for February?
containers. (Enter your response rounded up to the next whole number.)
Transcribed Image Text:The production schedule at Mazda calls for 1,250 Mazdas to be produced during each of 22 production days in January and 1,050 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from the Gesundheit. The safety stock policy variable, a, is 0.08. The container (a delivery truck) size is 250 tires. The average waiting time plus material handling time is 0.50 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing per container in January is 0.50 day. February processing time will average 0.10 day per container. How many containers should be authorized for January? 22 containers. (Enter your response rounded up to the next whole number.) How many containers should be authorized for February? containers. (Enter your response rounded up to the next whole number.)
Solution
Bartleby Expert
SEE SOLUTION
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.