The plan Regarding cost. • Our team has been tasked with planting the trees on the plot of land behind our company's new factory We are were 400 AC 350 300 PV The plan: - 30 batches of 20 trees (600 trees) - 5 batches per day (100 trees) - budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ 250 200 EV K We should have been here 150 100 50 Start 1st day After the first day.. Regarding schedule... • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees 400 could be planted) AC 350 300 PV • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) 250 200 EV K We are here 150 100 50 Simple EVM calculation: - Earned Value 40 trees planted x 2.90$ 203$ Start 1st day Which is where we should have been then - Planned Value 100 trees planned per day x 2.90$ = 290$ - Actual Cost- 40 trees planted x 290$ + 147$ for the machine » 350$ Planiśware Visually. Regarding schedule... 400 400 Actual cost = 350$ AC 350 350 300 - 290$ 300 Planned Value PV 250 250 Earned Value =203$ EV 200 200 150 150 100 100 50 50 Start 1st day Start 1st day Schedule variance in hours
The plan Regarding cost. • Our team has been tasked with planting the trees on the plot of land behind our company's new factory We are were 400 AC 350 300 PV The plan: - 30 batches of 20 trees (600 trees) - 5 batches per day (100 trees) - budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ 250 200 EV K We should have been here 150 100 50 Start 1st day After the first day.. Regarding schedule... • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees 400 could be planted) AC 350 300 PV • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) 250 200 EV K We are here 150 100 50 Simple EVM calculation: - Earned Value 40 trees planted x 2.90$ 203$ Start 1st day Which is where we should have been then - Planned Value 100 trees planned per day x 2.90$ = 290$ - Actual Cost- 40 trees planted x 290$ + 147$ for the machine » 350$ Planiśware Visually. Regarding schedule... 400 400 Actual cost = 350$ AC 350 350 300 - 290$ 300 Planned Value PV 250 250 Earned Value =203$ EV 200 200 150 150 100 100 50 50 Start 1st day Start 1st day Schedule variance in hours
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
100%
Thank youu i'll give upvote
![The plan
Regarding cost..
• Our team has been tasked with planting the trees on
the plot of land behind our company's new factory
We are here
400
AC
350
300
PV
The plan:
- 30 batches of 20 trees (600 trees)
250
200
EV
K We sould have been here
150
- 5 batches per day (100 trees)
100
50
budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$
for the slow release fertiliser)
→ total budget 1,740$
Start
1st day
After the first day..
Regarding schedule..
• 70 trees were planted (the team hit a patch with
stones that had to be removed before the trees
400
could be planted)
AC
350
300
PV
• Total cost was 350 $ (we had to rent a special
machine to help remove the stones which cost 147$
for the day)
250
200
EV
We are here
150
100
50
Simple EVM calculation:
Start
1st day
Earned Value = 70 trees planted × 2.90$ = 203$
Which is where we
should have been then
- Planned Value = 100 trees planned per day x 2.90$ = 290$
%3D
%3D
Actual Cost = 70 trees planted × 2.90$ + 147$ for the machine = 350$ Planišware
Visuall.
Regarding schedule..
400
400
AC
Actual cost = 350$
350
350
300
Planned Value = 290$
300
PV
250
250
Earned Value = 203$
EV
200
200
150
150
100
100
50
50
Start
1st day
Start
1st day
Schedule variance
in hours](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Faee38e48-d4a0-4650-8824-3430c788a264%2F70cf1010-6487-4783-acd3-a512dc417145%2Fd1nrpq8_processed.jpeg&w=3840&q=75)
Transcribed Image Text:The plan
Regarding cost..
• Our team has been tasked with planting the trees on
the plot of land behind our company's new factory
We are here
400
AC
350
300
PV
The plan:
- 30 batches of 20 trees (600 trees)
250
200
EV
K We sould have been here
150
- 5 batches per day (100 trees)
100
50
budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$
for the slow release fertiliser)
→ total budget 1,740$
Start
1st day
After the first day..
Regarding schedule..
• 70 trees were planted (the team hit a patch with
stones that had to be removed before the trees
400
could be planted)
AC
350
300
PV
• Total cost was 350 $ (we had to rent a special
machine to help remove the stones which cost 147$
for the day)
250
200
EV
We are here
150
100
50
Simple EVM calculation:
Start
1st day
Earned Value = 70 trees planted × 2.90$ = 203$
Which is where we
should have been then
- Planned Value = 100 trees planned per day x 2.90$ = 290$
%3D
%3D
Actual Cost = 70 trees planted × 2.90$ + 147$ for the machine = 350$ Planišware
Visuall.
Regarding schedule..
400
400
AC
Actual cost = 350$
350
350
300
Planned Value = 290$
300
PV
250
250
Earned Value = 203$
EV
200
200
150
150
100
100
50
50
Start
1st day
Start
1st day
Schedule variance
in hours
![Determine the following:
Cost Variance, Cost Performance Index,
Schedule Variance, Schedule
Performance Index.](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Faee38e48-d4a0-4650-8824-3430c788a264%2F70cf1010-6487-4783-acd3-a512dc417145%2Fkmvx1cii_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Determine the following:
Cost Variance, Cost Performance Index,
Schedule Variance, Schedule
Performance Index.
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Accounting](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
![Accounting Information Systems](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
![Horngren's Cost Accounting: A Managerial Emphasis…](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
![Intermediate Accounting](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
![Financial and Managerial Accounting](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education