The plan Regarding cost. • Our team has been tasked with planting the trees on the plot of land behind our company's new factory We are were 400 AC 350 300 PV The plan: - 30 batches of 20 trees (600 trees) - 5 batches per day (100 trees) - budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ 250 200 EV K We should have been here 150 100 50 Start 1st day After the first day.. Regarding schedule... • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees 400 could be planted) AC 350 300 PV • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) 250 200 EV K We are here 150 100 50 Simple EVM calculation: - Earned Value 40 trees planted x 2.90$ 203$ Start 1st day Which is where we should have been then - Planned Value 100 trees planned per day x 2.90$ = 290$ - Actual Cost- 40 trees planted x 290$ + 147$ for the machine » 350$ Planiśware Visually. Regarding schedule... 400 400 Actual cost = 350$ AC 350 350 300 - 290$ 300 Planned Value PV 250 250 Earned Value =203$ EV 200 200 150 150 100 100 50 50 Start 1st day Start 1st day Schedule variance in hours

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question
100%

Thank youu i'll give upvote

The plan
Regarding cost..
• Our team has been tasked with planting the trees on
the plot of land behind our company's new factory
We are here
400
AC
350
300
PV
The plan:
- 30 batches of 20 trees (600 trees)
250
200
EV
K We sould have been here
150
- 5 batches per day (100 trees)
100
50
budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$
for the slow release fertiliser)
→ total budget 1,740$
Start
1st day
After the first day..
Regarding schedule..
• 70 trees were planted (the team hit a patch with
stones that had to be removed before the trees
400
could be planted)
AC
350
300
PV
• Total cost was 350 $ (we had to rent a special
machine to help remove the stones which cost 147$
for the day)
250
200
EV
We are here
150
100
50
Simple EVM calculation:
Start
1st day
Earned Value = 70 trees planted × 2.90$ = 203$
Which is where we
should have been then
- Planned Value = 100 trees planned per day x 2.90$ = 290$
%3D
%3D
Actual Cost = 70 trees planted × 2.90$ + 147$ for the machine = 350$ Planišware
Visuall.
Regarding schedule..
400
400
AC
Actual cost = 350$
350
350
300
Planned Value = 290$
300
PV
250
250
Earned Value = 203$
EV
200
200
150
150
100
100
50
50
Start
1st day
Start
1st day
Schedule variance
in hours
Transcribed Image Text:The plan Regarding cost.. • Our team has been tasked with planting the trees on the plot of land behind our company's new factory We are here 400 AC 350 300 PV The plan: - 30 batches of 20 trees (600 trees) 250 200 EV K We sould have been here 150 - 5 batches per day (100 trees) 100 50 budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ Start 1st day After the first day.. Regarding schedule.. • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees 400 could be planted) AC 350 300 PV • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) 250 200 EV We are here 150 100 50 Simple EVM calculation: Start 1st day Earned Value = 70 trees planted × 2.90$ = 203$ Which is where we should have been then - Planned Value = 100 trees planned per day x 2.90$ = 290$ %3D %3D Actual Cost = 70 trees planted × 2.90$ + 147$ for the machine = 350$ Planišware Visuall. Regarding schedule.. 400 400 AC Actual cost = 350$ 350 350 300 Planned Value = 290$ 300 PV 250 250 Earned Value = 203$ EV 200 200 150 150 100 100 50 50 Start 1st day Start 1st day Schedule variance in hours
Determine the following:
Cost Variance, Cost Performance Index,
Schedule Variance, Schedule
Performance Index.
Transcribed Image Text:Determine the following: Cost Variance, Cost Performance Index, Schedule Variance, Schedule Performance Index.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Financial Statements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education