The plan Regarding cost. • Our team has been tasked with planting the trees on the plot of land behind our company's new factory We are were 400 AC 350 300 PV The plan: - 30 batches of 20 trees (600 trees) - 5 batches per day (100 trees) - budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ 250 200 EV K We should have been here 150 100 50 Start 1st day After the first day.. Regarding schedule... • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees 400 could be planted) AC 350 300 PV • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) 250 200 EV K We are here 150 100 50 Simple EVM calculation: - Earned Value 40 trees planted x 2.90$ 203$ Start 1st day Which is where we should have been then - Planned Value 100 trees planned per day x 2.90$ = 290$ - Actual Cost- 40 trees planted x 290$ + 147$ for the machine » 350$ Planiśware Visually. Regarding schedule... 400 400 Actual cost = 350$ AC 350 350 300 - 290$ 300 Planned Value PV 250 250 Earned Value =203$ EV 200 200 150 150 100 100 50 50 Start 1st day Start 1st day Schedule variance in hours
The plan Regarding cost. • Our team has been tasked with planting the trees on the plot of land behind our company's new factory We are were 400 AC 350 300 PV The plan: - 30 batches of 20 trees (600 trees) - 5 batches per day (100 trees) - budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ 250 200 EV K We should have been here 150 100 50 Start 1st day After the first day.. Regarding schedule... • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees 400 could be planted) AC 350 300 PV • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) 250 200 EV K We are here 150 100 50 Simple EVM calculation: - Earned Value 40 trees planted x 2.90$ 203$ Start 1st day Which is where we should have been then - Planned Value 100 trees planned per day x 2.90$ = 290$ - Actual Cost- 40 trees planted x 290$ + 147$ for the machine » 350$ Planiśware Visually. Regarding schedule... 400 400 Actual cost = 350$ AC 350 350 300 - 290$ 300 Planned Value PV 250 250 Earned Value =203$ EV 200 200 150 150 100 100 50 50 Start 1st day Start 1st day Schedule variance in hours
Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter16: Cost-volume-profit Analysis
Section: Chapter Questions
Problem 25E
Related questions
Question
100%
Thank youu i'll give upvote
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning