The plan Regarding cost. • Our team has been tasked with planting the trees on the plot of land behind our company's new factory We are were 400 AC 350 300 PV The plan: - 30 batches of 20 trees (600 trees) - 5 batches per day (100 trees) - budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ 250 200 EV K We should have been here 150 100 50 Start 1st day After the first day.. Regarding schedule... • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees 400 could be planted) AC 350 300 PV • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) 250 200 EV K We are here 150 100 50 Simple EVM calculation: - Earned Value 40 trees planted x 2.90$ 203$ Start 1st day Which is where we should have been then - Planned Value 100 trees planned per day x 2.90$ = 290$ - Actual Cost- 40 trees planted x 290$ + 147$ for the machine » 350$ Planiśware Visually. Regarding schedule... 400 400 Actual cost = 350$ AC 350 350 300 - 290$ 300 Planned Value PV 250 250 Earned Value =203$ EV 200 200 150 150 100 100 50 50 Start 1st day Start 1st day Schedule variance in hours
The plan Regarding cost. • Our team has been tasked with planting the trees on the plot of land behind our company's new factory We are were 400 AC 350 300 PV The plan: - 30 batches of 20 trees (600 trees) - 5 batches per day (100 trees) - budgeted cost per tree 2.90$ (2.5$ per baby tree / 0.40$ for the slow release fertiliser) → total budget 1,740$ 250 200 EV K We should have been here 150 100 50 Start 1st day After the first day.. Regarding schedule... • 70 trees were planted (the team hit a patch with stones that had to be removed before the trees 400 could be planted) AC 350 300 PV • Total cost was 350 $ (we had to rent a special machine to help remove the stones which cost 147$ for the day) 250 200 EV K We are here 150 100 50 Simple EVM calculation: - Earned Value 40 trees planted x 2.90$ 203$ Start 1st day Which is where we should have been then - Planned Value 100 trees planned per day x 2.90$ = 290$ - Actual Cost- 40 trees planted x 290$ + 147$ for the machine » 350$ Planiśware Visually. Regarding schedule... 400 400 Actual cost = 350$ AC 350 350 300 - 290$ 300 Planned Value PV 250 250 Earned Value =203$ EV 200 200 150 150 100 100 50 50 Start 1st day Start 1st day Schedule variance in hours
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
Related questions
Question
100%
Thank youu i'll give upvote
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Recommended textbooks for you
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education