The ledger of Sheffield Company has the following work in process account.
Work in Process—Painting
|
5/1 |
Balance |
3,690 |
5/31 |
Transferred out |
? |
5/31 |
Materials |
5,890 |
|
|
|
5/31 |
Labor |
5,252 |
|
|
|
5/31 |
Overhead |
1,680 |
|
|
|
5/31 |
Balance |
? |
|
|
|
Production records show that there were 400 units in the beginning inventory, 30% complete, 1,700 units started, and 1,500 units transferred out. The beginning work in process had materials cost of $3,140 and conversion costs of $550. The units in ending inventory were 40% complete. Materials are entered at the beginning of the painting process.
|
|
|
|
|
How many units are in process at May 31?
Work in process, May 31 |
|
|
units |
|
|
|
|
|
What is the unit materials cost for May? (Round unit cost to 2 decimal places, e.g. 2.25.)
The unit materials cost for May |
|
|
|
|
|
|
|
What is the unit conversion cost for May? (Round unit cost to 2 decimal places, e.g. 2.25.)
The unit conversion cost for May |
|
|
|
|
|
|
|
What is the total cost of units transferred out in May?
The total cost of units transferred out in May |
|
|
|
|
|
|
|
What is the cost of the May 31 inventory?
|
|
|
Definition Definition Indirect costs incurred while producing goods or services. Overhead costs cannot be directly attributed to products or services. Overhead includes indirect material cost, indirect labor cost, rent, utilities expenses, and depreciation. Since these costs directly affect the profitability of a company, managing overhead becomes an important task for management.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images