The FWO has just made the winning bid of 54 million Rs. to construct a new Building. Company has assigned you to this project to help ensure that it stays on schedule. The contract includes the following provisions: • A penalty of 300,0000 Rs. if Project has not completed construction by the deadline 47 weeks. • To provide additional incentive for speedy construction, a bonus of 150,0000 Rs. will be paid to if the building is completed within 40 weeks. Activity Activity Description A B C D E F G H I J K L M N Excavate Lay the foundation Put up the rough wall Put up the roof Exterior plumbing Interior plumbing Exterior siding Exterior painting Electrical work Put up the wallboard Install the flooring Interior painting Exterior fixtures Interior fixtures Immediate Predecessors A B C C E D E, G C F, I J J H K, L Estimated Duration (Weeks) 2 4 10 6 4 5 7 9 7 8 4 5 2 6 Crew size Norm. 5 3 6 6 3 3 5 3 3 4 4 4 2 3 Min. 2 2 3 3 2 2 3 2 1 2 2 2 1 1 Develop a comprehensive plan based on AOA or AON diagram that includes answers to the following questions. 1) Total time required to complete the project if no delays occur? 2) When do the individual activities need to start and finish (at the latest) to meet this project completion time? 3) When can the individual activities start and finish (at the earliest) if no delays occur? 4) Highlight the critical bottleneck activities where any delays must be avoided to prevent delaying project completion? 5) For the other activities, how much delay can be tolerated without delaying project completion? 6) Plan the daily work force for the project for a maximum crew size of 15 workers per day. Also draw the histogram.
The FWO has just made the winning bid of 54 million Rs. to construct a new Building. Company has assigned you to this project to help ensure that it stays on schedule. The contract includes the following provisions: • A penalty of 300,0000 Rs. if Project has not completed construction by the deadline 47 weeks. • To provide additional incentive for speedy construction, a bonus of 150,0000 Rs. will be paid to if the building is completed within 40 weeks. Activity Activity Description A B C D E F G H I J K L M N Excavate Lay the foundation Put up the rough wall Put up the roof Exterior plumbing Interior plumbing Exterior siding Exterior painting Electrical work Put up the wallboard Install the flooring Interior painting Exterior fixtures Interior fixtures Immediate Predecessors A B C C E D E, G C F, I J J H K, L Estimated Duration (Weeks) 2 4 10 6 4 5 7 9 7 8 4 5 2 6 Crew size Norm. 5 3 6 6 3 3 5 3 3 4 4 4 2 3 Min. 2 2 3 3 2 2 3 2 1 2 2 2 1 1 Develop a comprehensive plan based on AOA or AON diagram that includes answers to the following questions. 1) Total time required to complete the project if no delays occur? 2) When do the individual activities need to start and finish (at the latest) to meet this project completion time? 3) When can the individual activities start and finish (at the earliest) if no delays occur? 4) Highlight the critical bottleneck activities where any delays must be avoided to prevent delaying project completion? 5) For the other activities, how much delay can be tolerated without delaying project completion? 6) Plan the daily work force for the project for a maximum crew size of 15 workers per day. Also draw the histogram.
Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
Related questions
Question

Transcribed Image Text:The FWO has just made the winning bid of 54 million Rs. to construct a new Building.
Company has assigned you to this project to help ensure that it stays on schedule. The
contract includes the following provisions:
• A penalty of 300,0000 Rs. if Project has not completed construction by the deadline 47
weeks.
• To provide additional incentive for speedy construction, a bonus of 150,0000 Rs. will be
paid to if the building is completed within 40 weeks.
Estimated
Duration
Crew size
Activity Activity Description
Immediate
Predecessors
(Weeks)
Norm,
Min.
A
Excavate
2
2
B Lay the foundation
A
4
3
C
Put up the rough
в
10
6
3
wall
D
Put up the roof
C
6
6
3
Exterior plumbing
C
4
2
F
Interior plumbing
3
G
Exterior siding
D
3
Exterior painting
E, G
3
Electrical work
C
3
1
J
Put up the
F, I
4
wallboard
K
Install the flooring
J
4
4
2
Interior painting
J
4
2
Exterior fixtures
Interior fixtures
M
2
1
N
K, L
6
3
1
Develop a comprehensive plan based on AOA or AON diagram that includes answers to the
following questions.
1) Total time required to complete the project if no delays occur?
2) When do the individual activities need to start and finish (at the latest) to meet
this project completion time?
3) When can the individual activities start and finish (at the earliest) if no delays
occur?
4) Highlight the critical bottleneck activities where any delays must be avoided to
prevent delaying project completion?
5) For the other activities, how much delay can be tolerated without delaying project
completion?
6) Plan the daily work force for the project for a maximum crew size of 15 workers
per day. Also draw the histogram.
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 5 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you

Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press

Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education

Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press

Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON

Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education

Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY

Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning

Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY