The following processes are being scheduled using a preemptive, priority-based, round-robin scheduling algorithm. Process priority Burst Arrival P1 8 15 0 P2 3 20 0 P3 4 20 20 P4 4 20 25 P5 5 5 45 P6 5 15 55 Each process is assigned a numerical priority, with a higher number indicating a higher relative priority. For processes with the same priority, a round-robin scheduler will be used with a time quantum of 10 units. If a process is preempted by a higher-priority process, the preempted process is placed at the end of the queue. Show the scheduling order of the processes using a Gantt chart. What is the turnaround time for each process? What is the waiting time for each process?
The following processes are being scheduled using a preemptive, priority-based, round-robin scheduling
Process priority Burst Arrival
P1 8 15 0
P2 3 20 0
P3 4 20 20
P4 4 20 25
P5 5 5 45
P6 5 15 55
Each process is assigned a numerical priority, with a higher number indicating a higher relative priority. For processes with the same priority, a round-robin scheduler will be used with a time quantum of 10 units. If a process is preempted by a higher-priority process, the preempted process is placed at the end of the queue.
- Show the scheduling order of the processes using a Gantt chart.
- What is the turnaround time for each process?
- What is the waiting time for each process?