The following information relates to Contract 6502, which was undertaken for the construction of roadways for the City Council. The total value of the contract was $250,000 and it is at a stage where profits can be attributed to it.   Details of the contract are shown in the books:                                                                                                                                                                 $                  Materials sent to site                                                                          85,349 Labour engaged on site                                                                      74,375 Plant installed at cost                                                                        15,000 Direct expenditure                                                                              4,136 General overhead charges                                                                   3,167 Materials returned to store                                                                     549 Work certified                                                                                 195,000 Cost of work not certified                                                                  4,500 Materials on hand, December 31                                                        1,883 Wages accrued on December 31                                                        2,400 Direct expenditure accrued on Dec 31                                                 240 Value of plant December 31                                                             11,000 Cash received on account amount                                                  180,000   Required: Prepare the Contract Account as at December 31, 2019.  Prepare the Contract P&L account for the year ended December 31, 2019.  Prepare the Contractee Account as at December 31, 2019.    Explain the term ‘retention money.’

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Related questions
Question

The following information relates to Contract 6502, which was undertaken for the construction of roadways for the City Council.
The total value of the contract was $250,000 and it is at a stage where profits can be attributed to it.   Details of the contract are shown in the books:

                                               

                                                                                                                $                 

Materials sent to site                                                                          85,349

Labour engaged on site                                                                      74,375

Plant installed at cost                                                                        15,000

Direct expenditure                                                                              4,136

General overhead charges                                                                   3,167

Materials returned to store                                                                     549

Work certified                                                                                 195,000

Cost of work not certified                                                                  4,500

Materials on hand, December 31                                                        1,883

Wages accrued on December 31                                                        2,400

Direct expenditure accrued on Dec 31                                                 240

Value of plant December 31                                                             11,000

Cash received on account amount                                                  180,000

 

Required:

  • Prepare the Contract Account as at December 31, 2019. 

  • Prepare the Contract P&L account for the year ended December 31, 2019. 

  • Prepare the Contractee Account as at December 31, 2019.   

  • Explain the term ‘retention money.’ 



Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Intangible assets
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education