The following information is provided to you: Direct labour needed to make first machine. 1000 hours Learning curve. 80% Direct labour cost. R300 per hour Direct materials cost. R180000 per machine Fixed cost for machines at each cumulative production R800000 Calculate the total direct hours required to manufacture four (4) machines. ( Indicate both average time per unit as well as cumulative time per unit for all the units) Calculate the total costs to manufacture 4 machines
The following information is provided to you:
Time taken to produce first 8 shock pads 640 hours
Time taken to produce first 16 shock pads 1200 hours
Calculate the learning curve
The following information is provided to you:
Direct labour needed to make first machine. 1000 hours
Learning curve. 80%
Direct labour cost. R300 per hour
Direct materials cost. R180000 per machine
Fixed cost for machines at each cumulative production R800000
Calculate the total direct hours required to manufacture four (4) machines. ( Indicate both average time per unit as well as cumulative time per unit for all the
units)
Calculate the total costs to manufacture 4 machines