The following assembly tasks (with performance time in minutes and task precedence) are to be configured into a balanced assembly line layout. There are 12 separate assembly elements (A-L) to complete the product. Note: The target is to produce 6 units per hour (60 min). please select more than 5 workstations in this problem as per the guidelines of the lecture note. Element (Min) Preceded By A B C с D E F G H I J K L Time 2.5 4.5 3.5 4.0 3.2 2.0 2.7 7.0 6.0 3.8 5.0 4.3 A A A B B. C D D E F. G H I. J. K Construct the procedenco diagram b) Determine the total werk-content-time- of Use the Longest Tack Time" rule to assign-work-elements to stations (also known as "Largest Gandidate Mothed". d) Calculate the efficiency of your solution. Complete previous Question using the "Ranked Positional Weight (RPW)" method to assign work elements to stations. Calculate the efficiency of your solution. Compare the performance of LTT and RPW in this case.

Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
icon
Related questions
Question
The following assembly tasks (with performance time in minutes and task precedence) are to be configured into a balanced assembly line layout. There are 12 separate assembly elements (A-L) to complete
the product. Note: The target is to produce 6 units per hour (60 min). please select more than 5 workstations in this problem as per the guidelines of the lecture note.
Element (Min)
Preceded By
a) Construct the procedence diagram
Determine the total work sentent time.
A
B
C
D
E
F
G
H
||
J
K
L
c) Use the "Longest Task Time” rule to assign werk elements to stations (also known
d) Calculate the efficiency of your solution.
Time
2.5
4.5
3.5
4.0
3.2
2.0
2.7
7.0
6.0
3.8
5.0
4.3
A
A
A
B
B. C
D
D
E
F, G
H
I. J. K
nown as "Largest Candidate Method".
Complete previous Question using the "Ranked Positional Weight (RPW)" method to assign work elements to stations. Calculate the efficiency of your solution. Compare the performance of LTT and RPW
in this case.
Transcribed Image Text:The following assembly tasks (with performance time in minutes and task precedence) are to be configured into a balanced assembly line layout. There are 12 separate assembly elements (A-L) to complete the product. Note: The target is to produce 6 units per hour (60 min). please select more than 5 workstations in this problem as per the guidelines of the lecture note. Element (Min) Preceded By a) Construct the procedence diagram Determine the total work sentent time. A B C D E F G H || J K L c) Use the "Longest Task Time” rule to assign werk elements to stations (also known d) Calculate the efficiency of your solution. Time 2.5 4.5 3.5 4.0 3.2 2.0 2.7 7.0 6.0 3.8 5.0 4.3 A A A B B. C D D E F, G H I. J. K nown as "Largest Candidate Method". Complete previous Question using the "Ranked Positional Weight (RPW)" method to assign work elements to stations. Calculate the efficiency of your solution. Compare the performance of LTT and RPW in this case.
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Dynamic Multithreading
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Database System Concepts
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education