The demand for subassembly S is 130 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers). The product structure. The time-phased product structure. Q Level V ° W T T(2) U(1) X 1 More Info Y U Z 2 V(2) W(1) X(2) Y(2) Z(2) 3 5 Time in weeks Week Item 1 2 3 4 5 6 7 S Gross req On hand Net req Order receipt Order release T Gross req U V W X Y On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Z Gross req On hand Net req Order receipt Order release Item On-Hand Inventory On-Hand Item Inventory ST>> 20 W 25 20 U 40 20 XN 30 40 140 Lead Time (weeks) 2 1 2 2 3 1 2 1

Algebra & Trigonometry with Analytic Geometry
13th Edition
ISBN:9781133382119
Author:Swokowski
Publisher:Swokowski
Chapter9: Systems Of Equations And Inequalities
Section: Chapter Questions
Problem 52RE
icon
Related questions
Question
The demand for subassembly S is 130 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 2 units of X. Finally, each unit of U requires 2
units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to
make Y, and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Click the icon to view the on-hand inventory.
Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers).
The product structure.
The time-phased product structure.
Q
Level
V
°
W
T
T(2)
U(1)
X
1
More Info
Y
U
Z
2 V(2) W(1) X(2) Y(2) Z(2)
3
5
Time in weeks
Week
Item
1
2
3
4
5
6
7
S
Gross req
On hand
Net req
Order receipt
Order release
T
Gross req
U
V
W
X
Y
On hand
Net req
Order receipt
Order release
Gross req
On hand
Net req
Order receipt
Order release
Gross req
On hand
Net req
Order receipt
Order release
Gross req
On hand
Net req
Order receipt
Order release
Gross req
On hand
Net req
Order receipt
Order release
Gross req
On hand
Net req
Order receipt
Order release
Z
Gross req
On hand
Net req
Order receipt
Order release
Item
On-Hand
Inventory
On-Hand
Item
Inventory
ST>>
20
W
25
20
U
40
20
XN
30
40
140
Lead Time
(weeks)
2
1
2
2
3
1
2
1
Transcribed Image Text:The demand for subassembly S is 130 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 2 units of V, 1 unit of W, and 2 units of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers). The product structure. The time-phased product structure. Q Level V ° W T T(2) U(1) X 1 More Info Y U Z 2 V(2) W(1) X(2) Y(2) Z(2) 3 5 Time in weeks Week Item 1 2 3 4 5 6 7 S Gross req On hand Net req Order receipt Order release T Gross req U V W X Y On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Gross req On hand Net req Order receipt Order release Z Gross req On hand Net req Order receipt Order release Item On-Hand Inventory On-Hand Item Inventory ST>> 20 W 25 20 U 40 20 XN 30 40 140 Lead Time (weeks) 2 1 2 2 3 1 2 1
Expert Solution
steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Recommended textbooks for you
Algebra & Trigonometry with Analytic Geometry
Algebra & Trigonometry with Analytic Geometry
Algebra
ISBN:
9781133382119
Author:
Swokowski
Publisher:
Cengage
Algebra: Structure And Method, Book 1
Algebra: Structure And Method, Book 1
Algebra
ISBN:
9780395977224
Author:
Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:
McDougal Littell
Linear Algebra: A Modern Introduction
Linear Algebra: A Modern Introduction
Algebra
ISBN:
9781285463247
Author:
David Poole
Publisher:
Cengage Learning
Algebra for College Students
Algebra for College Students
Algebra
ISBN:
9781285195780
Author:
Jerome E. Kaufmann, Karen L. Schwitters
Publisher:
Cengage Learning