The contractor's construction expenses and owner's payments for a construction project are expressed in then-current inflated dollars in the table below. The monthly interest rate required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped for two months at the end of month 5 due to a labor strike while the monthly inflation rate is 0.7 percent. Under the terms of the contract between the owner and the contractor, suppose that the owner's payments will be delayed but not adjusted for inflation. Find the cumulative net cash flow with interest due to overdrafting for the following conditions: (a) if there were no labor strike and (b) when there is a strike for two months at the end of month 5.

Principles of Economics 2e
2nd Edition
ISBN:9781947172364
Author:Steven A. Greenlaw; David Shapiro
Publisher:Steven A. Greenlaw; David Shapiro
Chapter22: Inflation
Section: Chapter Questions
Problem 34P: The total price of purchasing a basket of goods in the United Kingdom over four years is: year...
icon
Related questions
Question
**See Instructions For Solving @ Bottom** The contractor's construction expenses and owner's payments
for a construction project are expressed in then-current inflated dollars in the table below. The monthly
interest rate required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped for
two months at the end of month 5 due to a labor strike while the monthly inflation rate is 0.7 percent.
Under the terms of the contract between the owner and the contractor, suppose that the owner's
payments will be delayed but not adjusted for inflation. Find the cumulative net cash flow with interest due
to overdrafting for the following conditions: (a) if there were no labor strike and (b) when there is a strike
for two months at the end of month 5. **Instructions** 1)Calculate Net Cash Flow - At 2)Calculate : *Et &
Et i/2 3)Calculate The Cumulative Cash Flow Before Payment = Ft with & with out interest 4)Calculate Nt =
Nt-1 + It-Et + Pt 5) Calculate: It = Nt i - Eti/2 6)Calculate Cumulative Net Cash Flow = Nt with & with out
interest *Annual Interest - It *Cumulative Cash Flow Before Payment Ft with interest *Cumulative Net Cash
Flow with interest NT with interest *All Calculations For All Equations for 14 Periods Must Be Shown I Need
to Verify my calculations
The contractor's construction expenses and owner's payments for a construction project are
expressed in then-current inflated dollars in the table below. The monthly interest rate
required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped
for two months at the end of month 5 due to a labor strike while the monthly inflation rate
is 0.7 percent. Under the terms of the contract between the owner and the contractor,
suppose that the owner's payments will be delayed but not adjusted for inflation. Find the
cumulative net cash flow with interest due to overdrafting for the following conditions:
(a) if there were no labor strike and (b) when there is a strike for two months at the end of
month 5.
End of month, Contractor's
t
expenses Et
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Total
-$200,000
-251,250
-404,000
-527,852
-642,726
-799,734
-772,800
-683,430
-447,501
-397,442
-348,965
-270,438
-437,420
0
0
$6,183,558
Owner's
Payment Pt
0
$225,000
360,000
468,000
567,000
702,000
675,000
594,000
387,000
342,000
298,800
230,400
370,800
1,080,000
600,000
$6,900,000
Transcribed Image Text:**See Instructions For Solving @ Bottom** The contractor's construction expenses and owner's payments for a construction project are expressed in then-current inflated dollars in the table below. The monthly interest rate required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped for two months at the end of month 5 due to a labor strike while the monthly inflation rate is 0.7 percent. Under the terms of the contract between the owner and the contractor, suppose that the owner's payments will be delayed but not adjusted for inflation. Find the cumulative net cash flow with interest due to overdrafting for the following conditions: (a) if there were no labor strike and (b) when there is a strike for two months at the end of month 5. **Instructions** 1)Calculate Net Cash Flow - At 2)Calculate : *Et & Et i/2 3)Calculate The Cumulative Cash Flow Before Payment = Ft with & with out interest 4)Calculate Nt = Nt-1 + It-Et + Pt 5) Calculate: It = Nt i - Eti/2 6)Calculate Cumulative Net Cash Flow = Nt with & with out interest *Annual Interest - It *Cumulative Cash Flow Before Payment Ft with interest *Cumulative Net Cash Flow with interest NT with interest *All Calculations For All Equations for 14 Periods Must Be Shown I Need to Verify my calculations The contractor's construction expenses and owner's payments for a construction project are expressed in then-current inflated dollars in the table below. The monthly interest rate required by the bank is 1.3 percent regardless of inflation. Suppose that the work is stopped for two months at the end of month 5 due to a labor strike while the monthly inflation rate is 0.7 percent. Under the terms of the contract between the owner and the contractor, suppose that the owner's payments will be delayed but not adjusted for inflation. Find the cumulative net cash flow with interest due to overdrafting for the following conditions: (a) if there were no labor strike and (b) when there is a strike for two months at the end of month 5. End of month, Contractor's t expenses Et 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Total -$200,000 -251,250 -404,000 -527,852 -642,726 -799,734 -772,800 -683,430 -447,501 -397,442 -348,965 -270,438 -437,420 0 0 $6,183,558 Owner's Payment Pt 0 $225,000 360,000 468,000 567,000 702,000 675,000 594,000 387,000 342,000 298,800 230,400 370,800 1,080,000 600,000 $6,900,000
Expert Solution
steps

Step by step

Solved in 5 steps with 38 images

Blurred answer
Knowledge Booster
Interest rate
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Economics 2e
Principles of Economics 2e
Economics
ISBN:
9781947172364
Author:
Steven A. Greenlaw; David Shapiro
Publisher:
OpenStax
Economics:
Economics:
Economics
ISBN:
9781285859460
Author:
BOYES, William
Publisher:
Cengage Learning
ECON MACRO
ECON MACRO
Economics
ISBN:
9781337000529
Author:
William A. McEachern
Publisher:
Cengage Learning
Survey Of Economics
Survey Of Economics
Economics
ISBN:
9781337111522
Author:
Tucker, Irvin B.
Publisher:
Cengage,