The Below table shows list of activities for a small project with the predecessors and duration for each activity. The project started on (20th May 2024). There are five (5) working days in a week. No works required during the weekend (Saturday and Sunday) and public holidays. Note: there is a public holiday on 30th May, 2024. 1. Based on the information given develop a network diagram using Activity on Node (AON) method. 2. Calculate the ES, EF, LS, LF for each activity on the diagram? 3. What is the critical path of the project? 4. List all the project activities in a table including the ES, LS, EF, LF, FF, TF as a number? 5. List all the project activities in a table including their dates of ES, LS, EF, LF? 6. Draw the Gantt chart for all the activities by Microsoft Excel using date and another Gantt chart using numbers? 7. What is the total project duration? 8. What is the project completion date? DURATION ACTIVITY PREDECESSOR (days) START 0 Clear & Grub 5 START Order & Delivery Reinforcement 10 START Order & Delivery PC Slabs 3 START Excavate Footings and Utilities 6 Clean & Grub Delivery Frames, Channel etc. 7 Clean & Grub RC Footings 9 Order & Delivery Reinforcement Form Footings 12 Excavate Footings and Utilities (SS+2) Masonry & Bearing Walls 4 Order & Delivery PC Slabs, RC Footings (FF +2) Erect Joists and Deck 7 Foundation Block 8 Masonry & Bearing Walls Delivery Frames, Channel etc., RC Footings (FS+3) Backfill 10 Form Footings, Foundation Block FINISH 0 Erect Joists and Deck, Backfill
The Below table shows list of activities for a small project with the predecessors and duration for each activity. The project started on (20th May 2024). There are five (5) working days in a week. No works required during the weekend (Saturday and Sunday) and public holidays. Note: there is a public holiday on 30th May, 2024. 1. Based on the information given develop a network diagram using Activity on Node (AON) method. 2. Calculate the ES, EF, LS, LF for each activity on the diagram? 3. What is the critical path of the project? 4. List all the project activities in a table including the ES, LS, EF, LF, FF, TF as a number? 5. List all the project activities in a table including their dates of ES, LS, EF, LF? 6. Draw the Gantt chart for all the activities by Microsoft Excel using date and another Gantt chart using numbers? 7. What is the total project duration? 8. What is the project completion date? DURATION ACTIVITY PREDECESSOR (days) START 0 Clear & Grub 5 START Order & Delivery Reinforcement 10 START Order & Delivery PC Slabs 3 START Excavate Footings and Utilities 6 Clean & Grub Delivery Frames, Channel etc. 7 Clean & Grub RC Footings 9 Order & Delivery Reinforcement Form Footings 12 Excavate Footings and Utilities (SS+2) Masonry & Bearing Walls 4 Order & Delivery PC Slabs, RC Footings (FF +2) Erect Joists and Deck 7 Foundation Block 8 Masonry & Bearing Walls Delivery Frames, Channel etc., RC Footings (FS+3) Backfill 10 Form Footings, Foundation Block FINISH 0 Erect Joists and Deck, Backfill
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Can u solve question according to table
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 1 images
Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning