The baseline plan in Table 1 shows that 6 work units (WBS A-F) would be completed as shown. You fill in the PV $ (Planned Value) and Earned Value $ lines based on this data. Table 1- Baseline Plan Work Units WBS Budget $ % Scheduled PV $ % Completed A 100 100 Planned Value (S) Earned Value ($) B 150 100 100 Table 2- Schedule Variance Work Units Earned Value ($) Actual Cost ($) с 100 100 100 100 40 100 0 I As work is performed, it is "earned" on the same basis as it was planned, in dollars or other quantifiable units such as labor hours. Planned value compared with earned value measures the dollar volume of work planned vs. the equivalent dollar volume of work accomplished. Any difference is called a schedule variance. In contrast to what was planned, Table 2 shows that work in unit D was not completed and work unit F was never started. D 250 100 A B C D E F Table 3- Cost Variance Work Units A B C 90 220 80 b. Calculate the cost variance (S) c. Are we under or over budget? (Prove your answer) d. What is the Project Cost-to-date? e. What is the $ of work remaining? f. What is the CPI? E 200 100 a. Calculate the schedule variance of the work planned for this period that was not done ($) Earned value compared with the actual cost incurred (from the contractors accounting system) for the work performed provides an objective measure of planned and actual cost. Any difference is called the cost variance. A negative variance means more money was spent for the work accomplished than was planned. Table 3 shows the data for Cost Variance. DE F 300 220 0 Total g. What is the likely cost to complete the project? h. What is likely project cost at completion? F 300 67 Total 1100 Total 910
The baseline plan in Table 1 shows that 6 work units (WBS A-F) would be completed as shown. You fill in the PV $ (Planned Value) and Earned Value $ lines based on this data. Table 1- Baseline Plan Work Units WBS Budget $ % Scheduled PV $ % Completed A 100 100 Planned Value (S) Earned Value ($) B 150 100 100 Table 2- Schedule Variance Work Units Earned Value ($) Actual Cost ($) с 100 100 100 100 40 100 0 I As work is performed, it is "earned" on the same basis as it was planned, in dollars or other quantifiable units such as labor hours. Planned value compared with earned value measures the dollar volume of work planned vs. the equivalent dollar volume of work accomplished. Any difference is called a schedule variance. In contrast to what was planned, Table 2 shows that work in unit D was not completed and work unit F was never started. D 250 100 A B C D E F Table 3- Cost Variance Work Units A B C 90 220 80 b. Calculate the cost variance (S) c. Are we under or over budget? (Prove your answer) d. What is the Project Cost-to-date? e. What is the $ of work remaining? f. What is the CPI? E 200 100 a. Calculate the schedule variance of the work planned for this period that was not done ($) Earned value compared with the actual cost incurred (from the contractors accounting system) for the work performed provides an objective measure of planned and actual cost. Any difference is called the cost variance. A negative variance means more money was spent for the work accomplished than was planned. Table 3 shows the data for Cost Variance. DE F 300 220 0 Total g. What is the likely cost to complete the project? h. What is likely project cost at completion? F 300 67 Total 1100 Total 910
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Please do fast
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 5 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.