Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Job Job Job Beginning balance Charged to the jobs during October: Job A256 A257 A258 A260 $ 1,200 $ 500 $ 0 $ 0 Direct $ 2,600 $ 3,500 $1,400 $ 3,500 materials Direct labor $ 800 $ 1,000 $ 600 $ 400 Manufacturing overhead applied $ 1,200 $ 1,500 $ 900 $ 600 Units completed 100 0 200 0 Units in process at the end of ° 400 0 500 October Units sold during October 80 ° 40 ° Jobs A256 and A258 were completed during October. The other two jobs had not yet been completed at the end of October. There was no finished goods inventory on October 1. In October, overhead was overapplied by $800. The company adjusts its cost of goods sold every month for the amount of the underapplied or overapplied overhead. Required: 1. Using the direct method, what is the cost of goods sold for October? (Round your intermediate calculations to 2 decimal places.) 2. What is the total value of the finished goods inventory at the end of October? (Round your intermediate calculations to 2 decimal places.) 3. What is the total value of the work in process inventory at the end of October?

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter5: Product And Service Costing: Job-order System
Section: Chapter Questions
Problem 17E: During August, Skyler Company worked on three jobs. Data relating to these three jobs follow:...
icon
Related questions
Question
Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data:
Job Job
Job
Beginning
balance
Charged to the
jobs during
October:
Job
A256 A257 A258 A260
$ 1,200
$ 500 $
0 $
0
Direct
$ 2,600
$ 3,500 $1,400 $ 3,500
materials
Direct labor
$ 800
$ 1,000 $ 600 $
400
Manufacturing
overhead applied
$ 1,200
$ 1,500 $
900 $
600
Units completed
100
0
200
0
Units in process
at the end of
°
400
0
500
October
Units sold
during October
80
°
40
°
Jobs A256 and A258 were completed during October. The other two jobs had
not yet been completed at the end of October. There was no finished goods
inventory on October 1.
In October, overhead was overapplied by $800. The company adjusts its cost of
goods sold every month for the amount of the underapplied or overapplied
overhead.
Transcribed Image Text:Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Job Job Job Beginning balance Charged to the jobs during October: Job A256 A257 A258 A260 $ 1,200 $ 500 $ 0 $ 0 Direct $ 2,600 $ 3,500 $1,400 $ 3,500 materials Direct labor $ 800 $ 1,000 $ 600 $ 400 Manufacturing overhead applied $ 1,200 $ 1,500 $ 900 $ 600 Units completed 100 0 200 0 Units in process at the end of ° 400 0 500 October Units sold during October 80 ° 40 ° Jobs A256 and A258 were completed during October. The other two jobs had not yet been completed at the end of October. There was no finished goods inventory on October 1. In October, overhead was overapplied by $800. The company adjusts its cost of goods sold every month for the amount of the underapplied or overapplied overhead.
Required:
1.
Using the direct method, what is the cost of goods sold for October? (Round your intermediate
calculations to 2 decimal places.)
2.
What is the total value of the finished goods inventory at the end of October? (Round
your intermediate calculations to 2 decimal places.)
3.
What is the total value of the work in process inventory at the end of October?
Transcribed Image Text:Required: 1. Using the direct method, what is the cost of goods sold for October? (Round your intermediate calculations to 2 decimal places.) 2. What is the total value of the finished goods inventory at the end of October? (Round your intermediate calculations to 2 decimal places.) 3. What is the total value of the work in process inventory at the end of October?
Expert Solution
steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning