TASK DESCRIPTION A Requirement/Need Analysis IT System Design Software development Develop IT Equipment List and order Hardware arrival & Installation [m]0|n|u|u B C D E F New IT system integration with current system Complete system testing G H Training and support I Handover and Go-live DURATION PREDECESSOR (S) (days) 5 15 25 15 30 10 10 5 55 5 A B BB B C, D E, F EGH Н

Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
icon
Related questions
Question
100%

See the given task table of the upcoming IT System upgrade project. Assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks start as soon as possible.  Which path is the critical path? (You may use a piece of paper to draw the PERT chart to calculate the critical path).

 

TASK DESCRIPTION
A Requirement/Need Analysis
IT System Design
B
C Software development
D
E
F
G
H
I
Develop IT Equipment List and order
Hardware arrival & Installation
New IT system integration with current
system
Complete system testing
Training and support
Handover and Go-live
DURATION PREDECESSOR (S)
(days)
5
15
25
15
30
10
10
5
5
ABBB
C, D
| | | |
E, F
G
Transcribed Image Text:TASK DESCRIPTION A Requirement/Need Analysis IT System Design B C Software development D E F G H I Develop IT Equipment List and order Hardware arrival & Installation New IT system integration with current system Complete system testing Training and support Handover and Go-live DURATION PREDECESSOR (S) (days) 5 15 25 15 30 10 10 5 5 ABBB C, D | | | | E, F G
Expert Solution
Step 1

Introduction :

Project management involves a series of complex activities, which need to be planned, organized, and executed efficiently to achieve the project goals. One of the essential aspects of project management is determining the critical path. The critical path is the longest sequence of dependent activities that must be completed on time for the project to be finished within the scheduled timeline. In this task, we are given a table of activities with their duration, and we need to determine the critical path by creating a PERT chart and calculating the earliest start time, earliest finish time, latest start time, and latest finish time for each task.

PERT Chart :

Program Evaluation and Review Technique (PERT) chart is a graphical representation of a project's tasks, their dependencies, and the expected time required to complete each task. A PERT chart helps to visualize and organize a project's timeline, allowing project managers to identify the critical path and optimize resources to complete the project on time.

How to Determine :

To determine the critical path using a PERT chart, we calculate the earliest start time (EST), earliest finish time (EFT), latest start time (LST), and latest finish time (LFT) for each task. The critical path is the sequence of tasks that must be completed on time to ensure that the entire project is completed on schedule. The critical path is determined by identifying the tasks that have no slack or float, which means that any delay in completing these tasks will result in a delay in the entire project. The critical path is the longest sequence of tasks from the first task to the last task that has no slack or float.

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Project Roles
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Database System Concepts
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education