Suppose that during the construction of the symmetrical curve in problem # dscovered that left side of the grade intersection falls on a rocky terrain. additional cost of excavation, the symmetrical curve is to be adjusted by ado 0.4174m high on the curve at its lowest point. If the location of the PT and the the tangents remain the same, determine the ff: a. Length of the new vertical parabolic curve b. Stationing and elevation of the new PC
Suppose that during the construction of the symmetrical curve in problem # dscovered that left side of the grade intersection falls on a rocky terrain. additional cost of excavation, the symmetrical curve is to be adjusted by ado 0.4174m high on the curve at its lowest point. If the location of the PT and the the tangents remain the same, determine the ff: a. Length of the new vertical parabolic curve b. Stationing and elevation of the new PC
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Answer only #2 letter c
![1. Given are the stations and elevations of a proposed symmetrical parabolic highway curve.
POINT
ELEVATION (m)
STATION
A
6+075
6+255 (PI)
93.60
90.00
96.48
C
6+435
Note: Lines AB and BC are the tangent lines of the proposed highway curve.
The curve will clear a boulder at Sta. 6+276, and the elevation of the tip of the boulder is
92.65m. Solve for the ff:
a. length of the symmetrical curve
b. stationing and elevation of PC
2. Suppose that during the construction of the symmetrical curve in problem #1, it was
dscovered that left side of the grade intersection falls on a rocky terrain. To avoid
additional cost of excavation, the symmetrical curve is to be adjusted by adding a fill
0.4174m high on the curve at its lowest point. If the location of the PT and the grades of
the tangents remain the same, detemine the ff:
a. Length of the new vertical parabolic curve
b. Stationing and elevation of the new PC
C. Stationing and elevation of lowest point of the new curve](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2F42e81c87-cbe3-4b02-92da-b0c2f3901ee4%2F0a96306f-67dc-4b95-b22f-3cc7672416b8%2Fx4q4c8m_processed.jpeg&w=3840&q=75)
Transcribed Image Text:1. Given are the stations and elevations of a proposed symmetrical parabolic highway curve.
POINT
ELEVATION (m)
STATION
A
6+075
6+255 (PI)
93.60
90.00
96.48
C
6+435
Note: Lines AB and BC are the tangent lines of the proposed highway curve.
The curve will clear a boulder at Sta. 6+276, and the elevation of the tip of the boulder is
92.65m. Solve for the ff:
a. length of the symmetrical curve
b. stationing and elevation of PC
2. Suppose that during the construction of the symmetrical curve in problem #1, it was
dscovered that left side of the grade intersection falls on a rocky terrain. To avoid
additional cost of excavation, the symmetrical curve is to be adjusted by adding a fill
0.4174m high on the curve at its lowest point. If the location of the PT and the grades of
the tangents remain the same, detemine the ff:
a. Length of the new vertical parabolic curve
b. Stationing and elevation of the new PC
C. Stationing and elevation of lowest point of the new curve
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 4 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Structural Analysis](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781337630931/9781337630931_smallCoverImage.jpg)
![Structural Analysis (10th Edition)](https://www.bartleby.com/isbn_cover_images/9780134610672/9780134610672_smallCoverImage.gif)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
![Principles of Foundation Engineering (MindTap Cou…](https://www.bartleby.com/isbn_cover_images/9781337705028/9781337705028_smallCoverImage.gif)
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
![Fundamentals of Structural Analysis](https://www.bartleby.com/isbn_cover_images/9780073398006/9780073398006_smallCoverImage.gif)
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
![Sustainable Energy](https://www.bartleby.com/isbn_cover_images/9781337551663/9781337551663_smallCoverImage.gif)
![Traffic and Highway Engineering](https://www.bartleby.com/isbn_cover_images/9781305156241/9781305156241_smallCoverImage.jpg)
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning