SummerTyme Inc is considering a new three year expansion project that requires an initial fixed asset investment of $3.9 million. The fixed asset will be depreciated straight-line to zero over its three-year life, after which time it will be worthless. The project is estimated to generate $2,650,000 in annual sales, with costs of $840,000. The tax rate is 35%. The discount rate is 12%. 3. What is the OCF each year for this project? Assuming the required return on this project is 12%, what is the project's NPV? What is the project's IRR? Should you accept or reject this project? Suppose the project requires an initial investment in net working capital of $300,000, and the fixed asset will have a market value of $210,000 at the end of the project. What is the project's year 0 net cash flow? Year 1? Year 2? Year 3? What is the new NPV? а. b. с. d. Discuss how sunk costs, opportunity costs, side effects, financing costs, and taxes should be treated in capital budgeting analysis and why. Limit your answer to two sentences for each. е.

Essentials Of Investments
11th Edition
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Chapter1: Investments: Background And Issues
Section: Chapter Questions
Problem 1PS
icon
Related questions
Topic Video
Question

answer last 3 questions 

SummerTyme Inc is considering a new three year expansion project that requires an initial fixed asset
investment of $3.9 million. The fixed asset will be depreciated straight-line to zero over its three-year life,
after which time it will be worthless. The project is estimated to generate $2,650,000 in annual sales, with
costs of $840,000. The tax rate is 35%. The discount rate is 12%.
3.
What is the OCF each year for this project?
Assuming the required return on this project is 12%, what is the project's NPV?
What is the project's IRR? Should you accept or reject this project?
Suppose the project requires an initial investment in net working capital of $300,000, and the fixed asset will
have a market value of $210,000 at the end of the project. What is the project's year 0 net cash flow? Year
1? Year 2? Year 3? What is the new NPV?
а.
b.
с.
d.
Discuss how sunk costs, opportunity costs, side effects, financing costs, and taxes should be treated in capital
budgeting analysis and why. Limit your answer to two sentences for each.
е.
Transcribed Image Text:SummerTyme Inc is considering a new three year expansion project that requires an initial fixed asset investment of $3.9 million. The fixed asset will be depreciated straight-line to zero over its three-year life, after which time it will be worthless. The project is estimated to generate $2,650,000 in annual sales, with costs of $840,000. The tax rate is 35%. The discount rate is 12%. 3. What is the OCF each year for this project? Assuming the required return on this project is 12%, what is the project's NPV? What is the project's IRR? Should you accept or reject this project? Suppose the project requires an initial investment in net working capital of $300,000, and the fixed asset will have a market value of $210,000 at the end of the project. What is the project's year 0 net cash flow? Year 1? Year 2? Year 3? What is the new NPV? а. b. с. d. Discuss how sunk costs, opportunity costs, side effects, financing costs, and taxes should be treated in capital budgeting analysis and why. Limit your answer to two sentences for each. е.
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Accounting Equation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Essentials Of Investments
Essentials Of Investments
Finance
ISBN:
9781260013924
Author:
Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:
Mcgraw-hill Education,
FUNDAMENTALS OF CORPORATE FINANCE
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:
9781260013962
Author:
BREALEY
Publisher:
RENT MCG
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage
Foundations Of Finance
Foundations Of Finance
Finance
ISBN:
9780134897264
Author:
KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:
Pearson,
Fundamentals of Financial Management (MindTap Cou…
Fundamentals of Financial Management (MindTap Cou…
Finance
ISBN:
9781337395250
Author:
Eugene F. Brigham, Joel F. Houston
Publisher:
Cengage Learning
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Corporate Finance (The Mcgraw-hill/Irwin Series i…
Finance
ISBN:
9780077861759
Author:
Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:
McGraw-Hill Education