Sultan Company uses an activity-based costing system. At the beginning of the year, the company mad cost and activity for its five activity cost pools Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Required: Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Expected Overhead Cost $ 400,000 $11,150 $82,820 $ 73,000 $ 279,500 Expected Activity 40,000 DLHS 223 orders 101 part types 1,640 boards 21,500 s

FINANCIAL ACCOUNTING
10th Edition
ISBN:9781259964947
Author:Libby
Publisher:Libby
Chapter1: Financial Statements And Business Decisions
Section: Chapter Questions
Problem 1Q
icon
Concept explainers
Topic Video
Question
 

Accounting

Required 1 Required 2
Using the ABC data, determine the total amount of overhead cost assigned to each product.
Overhead Cost Overhead Cost Overhead Cost Overhead Cost
Assigned
Product A
Assigned
Product D
Activity Cost Pool
Labor-related (DLHS)
Purchase orders (orders)
Parts management (part types)
Board etching (boards)
General factory (MHs)
Total
Assigned
Product B
< Required 1
Assigned
Product C
R640
Transcribed Image Text:Required 1 Required 2 Using the ABC data, determine the total amount of overhead cost assigned to each product. Overhead Cost Overhead Cost Overhead Cost Overhead Cost Assigned Product A Assigned Product D Activity Cost Pool Labor-related (DLHS) Purchase orders (orders) Parts management (part types) Board etching (boards) General factory (MHs) Total Assigned Product B < Required 1 Assigned Product C R640
Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of
cost and activity for its five activity cost pools
Activity Cost Pool
Labor-related
Purchase orders
Parts management
Board etching
General factory
Activity Measure
Direct labor-hours
Number of orders
Number of part types
Number of boards
Machine-hours
Activity Cost Pool
Labor-related (DLHS)
Purchase orders (orders)
Parts management (part types)
Board etching (boards)
General factory ()
Required:
1. Compute the activity rate for each of the activity cost pools.
2. The expected activity for the year was distributed among the company's four products as follows:
Required 1 Required 2
Compute the activity rate for each of the activity cost pools.
Activity Cost Pool
Activity Rate
per DLH
Labor-related
Purchase orders
Parts management
Board etching
General factory
Expected
Overhead Cost
$ 400,000
$11,150
$82,820
$ 73,800
$ 279,500
Product A
6,700
4,300
63
39
36
37
15
30
300
760
580
3,900
8,800
2,500
Using the ABC data, determine the total amount of overhead cost assigned to each product.
Complete this question by entering your answers in the tabs below.
per order
per part type
per board
per MH
Bombine
Expected Activity
40,000 DLHS
223 orders
Expected Activity
Product B
23,300
101 part types
1,640 boards
21,500 s
Product C
Product D
5,700
85
11
0
6,300
4
Transcribed Image Text:Sultan Company uses an activity-based costing system. At the beginning of the year, the company made the following estimates of cost and activity for its five activity cost pools Activity Cost Pool Labor-related Purchase orders Parts management Board etching General factory Activity Measure Direct labor-hours Number of orders Number of part types Number of boards Machine-hours Activity Cost Pool Labor-related (DLHS) Purchase orders (orders) Parts management (part types) Board etching (boards) General factory () Required: 1. Compute the activity rate for each of the activity cost pools. 2. The expected activity for the year was distributed among the company's four products as follows: Required 1 Required 2 Compute the activity rate for each of the activity cost pools. Activity Cost Pool Activity Rate per DLH Labor-related Purchase orders Parts management Board etching General factory Expected Overhead Cost $ 400,000 $11,150 $82,820 $ 73,800 $ 279,500 Product A 6,700 4,300 63 39 36 37 15 30 300 760 580 3,900 8,800 2,500 Using the ABC data, determine the total amount of overhead cost assigned to each product. Complete this question by entering your answers in the tabs below. per order per part type per board per MH Bombine Expected Activity 40,000 DLHS 223 orders Expected Activity Product B 23,300 101 part types 1,640 boards 21,500 s Product C Product D 5,700 85 11 0 6,300 4
Expert Solution
steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Recommended textbooks for you
FINANCIAL ACCOUNTING
FINANCIAL ACCOUNTING
Accounting
ISBN:
9781259964947
Author:
Libby
Publisher:
MCG
Accounting
Accounting
Accounting
ISBN:
9781337272094
Author:
WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:
Cengage Learning,
Accounting Information Systems
Accounting Information Systems
Accounting
ISBN:
9781337619202
Author:
Hall, James A.
Publisher:
Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis…
Horngren's Cost Accounting: A Managerial Emphasis…
Accounting
ISBN:
9780134475585
Author:
Srikant M. Datar, Madhav V. Rajan
Publisher:
PEARSON
Intermediate Accounting
Intermediate Accounting
Accounting
ISBN:
9781259722660
Author:
J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:
McGraw-Hill Education
Financial and Managerial Accounting
Financial and Managerial Accounting
Accounting
ISBN:
9781259726705
Author:
John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:
McGraw-Hill Education