Subcontracting (V) User interface Software coding Prototype testing Suppliers selection. Contract negotiation Minimum number of weeks a. Determine the minimum number of weeks for completing the project. 12 13 14 The duration of the project will V1 V2 to D2 12 11, 13 weeks. S1,S2 14, V1 b. Your boss would like you to study the impact of making two changes to how the project is organized. The first change involves using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P (product specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships within a subproject-all tasks within a subproject would be worked on at the same time and each would take the same amount of time- as originally specified. With this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V. The second change your boss would like you to consider would be to select the suppliers during subproject P and have them work directly with the dedicated teams as described in the first change. This would involve adding an additional activity to subproject P called supplier selection and contract negotiation (P5) with a duration of 12 weeks. This new activity would be done in parallel with P1, P2, P3, and P4. Subprojects S and V would be eliminated from the project. What would be the expected impact on how long it would take to complete the project if this additional change were made? 4 4 4 10 2
Subcontracting (V) User interface Software coding Prototype testing Suppliers selection. Contract negotiation Minimum number of weeks a. Determine the minimum number of weeks for completing the project. 12 13 14 The duration of the project will V1 V2 to D2 12 11, 13 weeks. S1,S2 14, V1 b. Your boss would like you to study the impact of making two changes to how the project is organized. The first change involves using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P (product specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships within a subproject-all tasks within a subproject would be worked on at the same time and each would take the same amount of time- as originally specified. With this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V. The second change your boss would like you to consider would be to select the suppliers during subproject P and have them work directly with the dedicated teams as described in the first change. This would involve adding an additional activity to subproject P called supplier selection and contract negotiation (P5) with a duration of 12 weeks. This new activity would be done in parallel with P1, P2, P3, and P4. Subprojects S and V would be eliminated from the project. What would be the expected impact on how long it would take to complete the project if this additional change were made? 4 4 4 10 2
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Q14
![You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your
supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project
activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow
morning!
You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each
activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully
completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject "P" involves developing specifications for the new cell phone. Here,
decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a
customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will
actually make the new cell phone in subproject "S" supplier specifications. These involve engineering details for how the product will
perform.
The individual components that make up the product are the focus of subproject "D." Subproject "I" brings all the components
together, and a working prototype is built and tested.
Finally, in subproject "V" suppliers are selected and contracts are negotiated.
Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
MAJOR SUBPROJECTS/ACTIVITIES.
Product Specifications (P)
Market research.
Overall product specifications
Supplier specifications (S)
Product design (D)
Product integration (1)
Hardware
Software
Subcontracting (V)
Hardware
Software
Battery
Display
Camera
Outer cover
Hardware
User interface
Software coding
Prototype testing
Suppliers selection
Contract negotiation.
ACTIVITY IDENTIFICATION
2 O ANA SS
P3
S2
I1
12
13
14
V1
V2
DEPENDENCY
P1
P2
P3
P4
P4
S1
S1
S1
D1, D2, D3
D4
D2
12
11, 13
S1,S2
14, V1
DURATION (WEEKS)
2
4
5
5
5
6
1
2
1
4
3
4
4
4
10
2](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fdd26d85a-e013-4a48-a762-d5bd9e4b812c%2F55eefa5e-3569-4a0c-9e2c-d70e65b77643%2Fg40r3ud_processed.jpeg&w=3840&q=75)
Transcribed Image Text:You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your
supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project
activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow
morning!
You have been given the information in Exhibit 4.13. It includes all the activities required in the project and the duration of each
activity. Also, dependencies between the activities have been identified. Remember that the preceding activity must be fully
completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject "P" involves developing specifications for the new cell phone. Here,
decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a
customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will
actually make the new cell phone in subproject "S" supplier specifications. These involve engineering details for how the product will
perform.
The individual components that make up the product are the focus of subproject "D." Subproject "I" brings all the components
together, and a working prototype is built and tested.
Finally, in subproject "V" suppliers are selected and contracts are negotiated.
Exhibit 4.13: Work Breakdown Structure and Activities for the Cell Phone Design Project
MAJOR SUBPROJECTS/ACTIVITIES.
Product Specifications (P)
Market research.
Overall product specifications
Supplier specifications (S)
Product design (D)
Product integration (1)
Hardware
Software
Subcontracting (V)
Hardware
Software
Battery
Display
Camera
Outer cover
Hardware
User interface
Software coding
Prototype testing
Suppliers selection
Contract negotiation.
ACTIVITY IDENTIFICATION
2 O ANA SS
P3
S2
I1
12
13
14
V1
V2
DEPENDENCY
P1
P2
P3
P4
P4
S1
S1
S1
D1, D2, D3
D4
D2
12
11, 13
S1,S2
14, V1
DURATION (WEEKS)
2
4
5
5
5
6
1
2
1
4
3
4
4
4
10
2
![Subcontracting (V)
User interface
Software coding
Prototype testing
Suppliers selection
Contract negotiation
Minimum number of weeks
SS HEN
a. Determine the minimum number of weeks for completing the project.
The duration of the project will
14
to
V2
D2
12
11, 13
weeks.
S1,S2
14, V1
b. Your boss would like you to study the impact of making two changes to how the project is organized. The first change involves
using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P (product
specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships
within a subproject-all tasks within a subproject would be worked on at the same time and each would take the same amount of time
as originally specified. With this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V.
The second change your boss would like you to consider would be to select the suppliers during subproject P and have them work
directly with the dedicated teams as described in the first change. This would involve adding an additional activity to subproject P
called supplier selection and contract negotiation (P5) with a duration of 12 weeks. This new activity would be done in parallel with P1,
P2, P3, and P4. Subprojects S and V would be eliminated from the project. What would be the expected impact on how long it would
take to complete the project if this additional change were made?
444 22
10](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fdd26d85a-e013-4a48-a762-d5bd9e4b812c%2F55eefa5e-3569-4a0c-9e2c-d70e65b77643%2Fim0chak_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Subcontracting (V)
User interface
Software coding
Prototype testing
Suppliers selection
Contract negotiation
Minimum number of weeks
SS HEN
a. Determine the minimum number of weeks for completing the project.
The duration of the project will
14
to
V2
D2
12
11, 13
weeks.
S1,S2
14, V1
b. Your boss would like you to study the impact of making two changes to how the project is organized. The first change involves
using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P (product
specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships
within a subproject-all tasks within a subproject would be worked on at the same time and each would take the same amount of time
as originally specified. With this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V.
The second change your boss would like you to consider would be to select the suppliers during subproject P and have them work
directly with the dedicated teams as described in the first change. This would involve adding an additional activity to subproject P
called supplier selection and contract negotiation (P5) with a duration of 12 weeks. This new activity would be done in parallel with P1,
P2, P3, and P4. Subprojects S and V would be eliminated from the project. What would be the expected impact on how long it would
take to complete the project if this additional change were made?
444 22
10
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
Step 1 - Introduction
Given data is
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.